RERA projects in Rahta

30 projects under 33 MahaRERA registrations, registered 2017–2026. 48% have a completion date extended beyond the one promised.

Taluka
30RERA projects
33Registrationssome projects hold several
10Completion still due19 past their completion date
4 monthsMedian extension beyond promised date48% of registrations extended
5Regulatory caseson 2 projects
75Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20176
20181
20192
20204
20214
20225
20233
20240
20251
20263

Projects in Rahta

30 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shivay HeightsAdmark BuildersPR101000250233512 Feb 202631 Dec 202730 Apr 2028Extended 4 mo0
Divate ResidencyPrasad Sahebrav NidhanePR10100025020289 Jan 20262 Mar 20282 Jul 2028Extended 4 mo0
Sandal Suites ShirdiSandal Lands Private LimitedPC10100025020026 Jan 202631 Dec 203130 Apr 2032Extended 4 mo0
Rajmudra ApartmentSai Balaji Builders And DevelopersPR101000250150218 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Raoji HeightsBaba EnterprisesP522000518557 Jul 202331 Dec 202830 Apr 2029Extended 4 mo0
Ranmale ResidentialMangesh Bhagwan RanmaleP522000500546 Mar 202326 Jan 202526 Jan 2025Promised date passed0
Dhadiwal Raisoni PlazaDhadiwal Raisoni AssociatesP5220004860210 Jan 202331 Dec 202630 Apr 2027Extended 4 mo0
Sai Hermitage Shirdi - By Ananta Block - 7Harihar Infraventure (India) Private LimitedP522000331389 Feb 202231 Dec 202331 Dec 2023Promised date passed1
Sai Hermitage Shirdi By AnantaHarihar Infraventure (India) Private LimitedP52200032959, P52200032980, P52200032981 +12 Feb 202231 Jan 202431 Jan 2024Promised date passed4
Shri Sai Sindhu Park DevelopersShri Sai Sindhu Park DevelopersP5220002923810 May 202131 Dec 202630 Apr 2027Extended 4 mo0
Swapnapurti NagarSwapnapurtiP5220002895415 Apr 202131 Dec 202431 Dec 2024Promised date passed0
Platinum Phase 2Silveroak Buildcon Pvt. Ltd.P5220002872125 Mar 202123 Dec 202523 Dec 2025Promised date passed0
Silveroak Gold CoastSilver Oak Builders And DevelopersP5220002824718 Feb 202123 Dec 202423 Dec 2025Extended 12 mo0
Bhansali SquareSarthak Bhansali and Siddharth BhansaliP5220002744510 Dec 202030 Jun 202430 Jun 2024Promised date passed0
Sai Ashirwad residencyGlobal Construction ServicesP522000269877 Nov 202030 Sep 202330 Sep 2023Promised date passed0
Shivmudra TowersAshish Sudhakar DandawateP522000256781 Jul 202030 Sep 202430 Sep 2024Promised date passed0
MadhubanPrasad DevelopersP5220002554428 Jun 202012 Feb 203012 Jun 2030Extended 4 mo0
Shree Sai Nirman Dream CityShree Sai Nirman RealtyP5220002337912 Dec 201930 Dec 202431 Dec 2026Extended 24 mo0
Guruprasad ResidencyNaresh Sampatlal Parakh V ItarP5220001970722 Feb 201930 Dec 202331 Dec 2029Extended 72 mo0
Anish RegencyAnish BuildconP522000148448 Jan 201831 Dec 201930 Dec 2022Extended 36 mo0
Renuka ApartmentSomnath Pandurng GadekarP5220001171831 Aug 201731 Dec 201931 Dec 2019Promised date passed0
Sai Krishna DivineIndiana Build Infrastructure Private LimitedP5220001071231 Aug 201731 Dec 201831 Dec 2018Promised date passed0
Sai PrasadSoham PropertiesP5220001091931 Aug 201731 Dec 201831 Dec 2018Promised date passed0
Sai Moreshwar DivineMaatoshree Shelters Pvt LtdP5220000930822 Aug 201731 Mar 202131 Mar 2024Extended 36 mo0
Saichintan Phase 2Silveroak Buildcon Pvt. Ltd.P522000042329 Aug 201730 Jan 202330 Jun 2025Extended 29 mo0

Other talukas in Ahmednagar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Harihar Infraventure (India) Private Limited2 projects
  2. Silveroak Buildcon Pvt. Ltd.2 projects
  3. Admark Builders1 project
  4. Anish Buildcon1 project
  5. Ashish Sudhakar Dandawate1 project
  6. Baba Enterprises1 project
  7. Dhadiwal Raisoni Associates1 project
  8. Global Construction Services1 project
  9. Indiana Build Infrastructure Private Limited1 project
  10. Maatoshree Shelters Pvt Ltd1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology