RERA projects in Shrirampur

47 projects under 47 MahaRERA registrations, registered 2017–2026. 15% have a completion date extended beyond the one promised.

Taluka
47RERA projects
47Registrations
11Completion still due29 past their completion date
4 monthsMedian extension beyond promised date15% of registrations extended
0Regulatory casesnone on MahaRERA's lists
69Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20184
20192
20204
20212
20226
20239
20243
20252
20265

Projects in Shrirampur

47 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Agashe HeightsNeelkanth DevelopersPR10100026021325 Oct 202630 Jun 202930 Jun 2029Not yet due0
Shaurya HeightsPanchamukhi Builders and DevelopersPR101000260149710 Aug 202631 Dec 202831 Dec 2028Not yet due0
Adinath SocietyAdinath DevelopersPM101000260078015 Jun 202631 Dec 202830 Apr 2029Extended 4 mo0
Navdurga HeightsGeniotive Lifespace LLPPM101000260005810 Apr 202612 Feb 202912 Jun 2029Extended 4 mo0
Aashirwad HeightsNeelkanth DevelopersPR101000250208616 Jan 202630 Oct 202828 Feb 2029Extended 4 mo0
Ivaan TowerMudra RealitiesPM101000250074010 Sep 202520 Jun 202720 Oct 2027Extended 4 mo0
Neelkanth Pride ParkNeelkanth DevelopersP5220007897624 Jan 202531 Dec 202730 Apr 2028Extended 4 mo0
Safalya HeightsGaurav Vishvanath AwatiP522000782664 Dec 202424 Aug 202624 Aug 2026Promised date passed0
Satyabhama TowersGaurav Vishvanath AwatiP5220007772523 Oct 20249 Jul 20269 Jul 2026Promised date passed0
Bhagirathi HeightsGaurav Vishwanath AwatiP5220007674825 Jun 20246 May 20266 May 2026Promised date passed0
Anupama HeightsNeelkanth DevelopersP522000538625 Dec 202330 Oct 202630 Oct 2026Not yet due0
Mangal ResidencyGaurav Vishwanath AwatiP5220005156227 Jun 202320 Mar 202520 Mar 2025Promised date passed0
Ashirwad ResidencyIshwar Nandkumar UnhaleP5220005144723 Jun 202331 Mar 202531 Mar 2025Promised date passed0
Kausalya HeightsNeelkanth DevelopersP522000512268 Jun 202331 May 202631 May 2026Promised date passed0
Sarvadnya HeightsPriyanka Krishna AgarkarP5220005095716 May 202331 May 202531 May 2025Promised date passed0
Dhole ComplexGaurav Vishwanath AwatiP522000503191 Apr 20231 May 20241 May 2024Promised date passed0
Weston City Phase 3Weston Land DevelopersP5220005013220 Mar 202331 Dec 202731 Dec 2027Not yet due0
Fatema EliteSameena Anjum ShaikhP5220005009215 Mar 202331 Dec 202931 Dec 2029Not yet due0
Golden LeafGaurav Vishwanath AwatiP5220004944814 Feb 20231 Nov 20241 Nov 2024Promised date passed0
Anantaa City CenterSuvarna Lifespace Developers LLPP522000474662 Nov 20221 Aug 20251 Aug 2025Promised date passed0
Subhadra HeightsNeelkanth DevelopersP5220004650110 Aug 202230 Jun 202630 Jun 2026Promised date passed0
Atharva HeightsGaurav Vishwanath AwatiP5220003387114 Mar 202211 Oct 202411 Oct 2024Promised date passed0
Jai Shriram ComplexVarun Shashikant AgrawalP522000330273 Feb 202231 Dec 202630 Apr 2027Extended 4 mo0
Gouras Developers and ConstructionGouras Developers and ConstructionP5220003272824 Jan 202231 Jul 202531 Jul 2025Promised date passed0
Sai VishwaGaurav Vishwanath AwatiP522000324414 Jan 202211 Sep 202311 Sep 2023Promised date passed0

Other talukas in Ahmednagar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Neelkanth Developers11 projects
  2. Gaurav Vishwanath Awati9 projects
  3. Gaurav Vishvanath Awati2 projects
  4. Weston Land Developers2 projects
  5. Adinath Developers1 project
  6. Geniotive Lifespace LLP1 project
  7. Gouras Developers and Construction1 project
  8. Hirakaka1 project
  9. Ishwar Nandkumar Unhale1 project
  10. M/s Mithila Realty1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology