D R Pride
Deedo IDDP-AHM-649KMahaRERA shows it completed; no MahaRERA orders on record; 0% of its units are booked.
Ahmadnagar (M Corp.), Ahmednagar 414001 · by D R Buildcon
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 27 Mar 2023, completion promised 30 Oct 2026.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52200050251
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52200050251 | 27 Mar 2023 | 30 Oct 2026 | 30 Oct 2026 | D R Buildcon | Project page |
Documents63
2 documents held by Deedo, 61 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Show all 63 documentsShow fewer documents
Legal
- Other – LegalSelf Declaration.pdf · uploaded 12 Jan 2024Source
Migrated
- 1 PAN CardPan Card.pdf · uploaded 13 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Layout.pdf · uploaded 13 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan.pdf · uploaded 13 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentSanction Letter.pdf · uploaded 13 Jan 2023Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement.pdf · uploaded 13 Jan 2023Source
- 1 Declaration in FORM BForm 3.pdf · uploaded 13 Jan 2023Source
- 1 CERSAI detailsCU.pdf · uploaded 13 Jan 2023Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementAFS Deviation.pdf · uploaded 13 Jan 2023Source
- 1 Other – LegalAuthorization Declaration.pdf · uploaded 13 Jan 2023Source
- 2 Other – LegalPARTNERSHIP DEED MARATHI.pdf · uploaded 13 Jan 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 16 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Alottment.pdf · uploaded 16 Jan 2023Source
- 1 Copy of the legal title reportLegal Search.pdf · uploaded 24 Jan 2023Source
- 1 a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 14 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceFinancial Encumbrance.pdf · uploaded 14 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 14 Mar 2023Source
- 2 b Details of encumbrances concerned to LegalFinancial Encumbrance.pdf · uploaded 14 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 14 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure.pdf · uploaded 14 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeprate Bank Ac.pdf · uploaded 14 Mar 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 8 Nov 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Nov 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 8 Nov 2023Source
- 1 Disclosure of sold/ booked inventorysold booked inventory.pdf · uploaded 9 Nov 2023View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 9 Nov 2023Source
- 2 CERSAI detailsCersai.pdf · uploaded 12 Jan 2024Source
- 2 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 12 Jan 2024Source
- 3 Other – LegalSelf Declaration.pdf · uploaded 12 Jan 2024Source
- 1 Other – FinanceSelf Declaration.pdf · uploaded 12 Jan 2024Source
- 1 Other – TechnicalSelf Declaration.pdf · uploaded 12 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2022-23.pdf · uploaded 16 Mar 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 30 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2-A.pdf · uploaded 30 Apr 2024Source
- 3 Disclosure of sold/ booked inventoryForm 2.pdf · uploaded 30 Apr 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Apr 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 30 Apr 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 11 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 11 May 2024Source
- 4 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 11 May 2024View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 11 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 11 May 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 18 Dec 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Deed of Declaration.pdf · uploaded 18 Dec 2024Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)Corrected DOD.pdf · uploaded 18 Dec 2024Source
- 1 Status of ConveyanceDeed of Declaration.pdf · uploaded 18 Dec 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 18 Dec 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 18 Dec 2024View
- 2 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 19 Dec 2024Source
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 11 May 2024Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 30 Apr 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 9/1A PLOT NO 34
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK10 units in all
- Address
- S No 9/1a Plot No 34, S No 9/1a Plot No 34, Rasne Nagar, Rasne NagarPIN 414001
- Village
- Ahmadnagar (M Corp.), Nagar taluka
- Land area for this project
- 402 sq m (4,327 sq ft)
- Permissible built-up area
- 1,213 sq m (13,060 sq ft)
- Sanctioned built-up area
- 1,213 sq m (13,060 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 9/1A PLOT NO 34
Boundaries
- North
- Road
- South
- Lagu S No
- East
- Plot No 32 And 33
- West
- Plot 35
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking10 units
0 of 10 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 70.33 sq m · 757 sq ft | 5 | 0 |
| 3BHK | 90.84 sq m · 978 sq ft | 5 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mayur Kothari | — |
| Chartered accountant | Jeetu Sawalani & Associates | — |
| Engineer | Anmol Jain | — |
| Other | Bhirunath Dhanagar | — |
Source: MahaRERA project page. Contact details are not shown.