RERA projects in Ahmadnagar (M Corp.)

167 projects under 167 MahaRERA registrations, registered 2017–2026. 6% have a completion date extended beyond the one promised.

167RERA projects
167Registrations
51Completion still due116 past their completion date
21 monthsMedian extension beyond promised date6% of registrations extended
1Regulatory caseson 1 project
7Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201737
201817
201916
202015
202117
202223
202322
20248
20258
20264

Projects in Ahmadnagar (M Corp.)

167 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
RainflowerMadhumalti Costruction Pvt LtdPR101000260130024 Jul 202631 Dec 2031—Not yet due0
Platinum PlazaSpy Developers Builders And SuppliersPC101000250294518 Mar 202631 Dec 2030—Not yet due0
Saitej ApartmentGdps Construction LLPPM101000250245023 Feb 20262 Aug 2029—Not yet due0
Jaystu Elite ResidencesDeepak Haribhau BangarPR101000250213921 Jan 202631 Mar 2031—Not yet due0
Sunflower ResidencyAishwary Builders And DevelopersPR101000250099629 Sep 20251 May 2028—Not yet due0
Royal Casa 70 A WingVenkatesh RealityPR101000250058214 Aug 202531 Dec 2029—Not yet due0
Sairaj ParkSairaj ParkP522000809014 Aug 202531 Dec 2026—Not yet due0
Elite 18Nilaya GroupPR101000250027314 Jul 202531 Dec 2031—Not yet due0
Chhatrapati HeightsShri Sanskruti DevelopersP5220008070926 Jun 202531 Dec 2026—Not yet due0
Breeze CourtAnil Bankatlal GandhiP522000799323 Apr 202530 Jul 2027—Not yet due0
Kalyan Castle4k RealtyP5220007981327 Mar 202530 Jun 2030—Not yet due0
Shaniraj HeightsSantosh Machindra ShindeP5220007978526 Mar 202531 Mar 2030—Not yet due0
Swami Vivekanand TowersNavnath Machindra KatoreP5220007813625 Nov 202431 Mar 2029—Not yet due0
R K HeightsBalbhimrao Doke And Rahul Kulthe DevelopersP5220007800319 Nov 202431 Mar 2027—Not yet due0
SnowbellMadhumalti Costruction Pvt LtdP5220007794313 Nov 202431 Dec 2028—Not yet due0
TridentMakarand Madhav KulkarniP5220007791913 Nov 202431 Mar 2029—Not yet due0
Sundarmoti ResidencyDilip Motilalji ChordiaP5220007762817 Oct 202431 Dec 2026—Not yet due0
Rajrajeshwari AppartmentShankarleela DevelopersP5220005636231 May 202431 Dec 2027—Not yet due0
Kamath IrinKamath AssociatesP5220005498321 Feb 20242 Jun 2026—Promised date passed0
Royal WoodsKPGC Ventures Private Ltd.P522000541803 Jan 202431 Dec 2026—Not yet due0
Solitaire Business HubA To Z ConstructionP522000538998 Dec 202331 Mar 2026—Promised date passed0
7 SolitaireInfinity RealtiesP5220005366321 Nov 202331 Dec 2025—Promised date passed0
Mina ApartmentMina Mohan LadP5220005358010 Nov 202331 Dec 2026—Not yet due0
Crystal Tower Phase 2Maharaja DevelopersP5220005320923 Oct 20231 Dec 2027—Not yet due0
Saraswati TowerSaraswati DevelopersP5220005301310 Oct 202331 Dec 2026—Not yet due0
Parth VillaAshok Babanrao KhokaraleP5220005272222 Sep 202331 Dec 2027—Not yet due0
BluestoneMakarand Madhav KulkarniP5220005255811 Sep 202331 Mar 2027—Not yet due0
Parth Heights Phase 3Rajendra Ramchandra PawarP5220005215824 Jul 202331 Dec 2026—Not yet due0
Anand Vihar ResidencyGanga DevelopersP5220005148423 Jun 202323 Dec 2025—Promised date passed0
Sham Sunder PalaceKrushna Construction And Land DevelopersP5220005151123 Jun 202331 Mar 2028—Not yet due0
Adesh Heights Phase 11Suresh Namdev LagadP5220005142314 Jun 202331 Dec 2025—Promised date passed0
Crown PlazaMahavir Infra Plus LLPP5220005112930 May 202331 Mar 2027—Not yet due0
RegentRiselife SpacesP5220005091315 May 202331 Dec 2027—Not yet due0
PasaydanAdiraj DevelopersP522000507663 May 202331 Mar 2027—Not yet due0
Mauli TowerMayur Anand ShindeP5220005074228 Apr 202331 Dec 2025—Promised date passed0
Shivganga PrideAjit Kundlik GhodakeP5220005070628 Apr 202325 May 2026—Promised date passed0
Sky CourtPranali InfraP5220005050117 Apr 202330 Jun 2026—Promised date passed0
D R PrideD R BuildconP5220005025127 Mar 202330 Oct 2026—Not yet due0
Vivekanand Row-BungalowRahul Balasaheb BhosaleP522000498966 Mar 202331 Dec 2026—Not yet due1
AbhiramMakarand Madhav KulkarniP522000494078 Feb 202331 Mar 2026—Promised date passed0
VivantaB And G VenturesP5220004888424 Jan 20231 Dec 2024—Promised date passed0
Saffron EliteDhanraj Lalchand SanchetiP5220004861810 Jan 202331 Dec 2027—Not yet due0
Aai ResidencyVinod Dilip PacharneP5220004815815 Dec 202231 Jul 2025—Promised date passed0
ArabellaMarc DevelopersP522000480578 Dec 202231 Mar 2027—Not yet due0
Sky HeightPranali InfrastructureP522000480327 Dec 202231 Jan 2027—Not yet due0
Nakshatra HeightsShashikant Gopinath BhambareP522000479662 Dec 202231 Dec 2024—Promised date passed0
Nathkrupa PlazaNathkrupa DevelopersP522000479692 Dec 202230 Jun 2025—Promised date passed0
Pink City-IIAmit Ashok MuthaP5220004777528 Nov 202229 Mar 2027—Not yet due0
Kritikka AarambhaKritikka RealtyP5220004772421 Nov 202230 Jun 2027—Not yet due0
Classic AuraSanjay Shantilal GugaleP522000467715 Sep 202231 Dec 2027—Not yet due0
Jlp Business TowerAditya Builders & Developers (Prop. Jalindar Laxman Palve HUF)P5220004653710 Aug 20221 Nov 2024—Promised date passed0
Kuber HeightsMula Pravara CorporationP522000464966 Aug 202230 Apr 2023—Promised date passed0
Adesh Heights Phase 8Suresh Namdev LagadP5220004609920 Jun 202231 Dec 2024—Promised date passed0
Ganesh PrideSanklecha ConstructionP5220004616020 Jun 202231 Dec 2024—Promised date passed0
Vivekanand Row BungalowYogesh Balasaheb MustapureP5220004616120 Jun 202231 Dec 2026—Not yet due0
ArianaMarc DevelopersP5220004598315 Jun 202231 Mar 2027—Not yet due0
Bappa Residencyketan shrikrishna navleP5220004582315 Jun 202231 Mar 2025—Promised date passed0
Team57prideAnand ConstructionP5220003512110 May 202231 Dec 2024—Promised date passed0
Stellar HeightsVision GroupP5220003463220 Apr 202231 Dec 2026—Not yet due0
Nova CasaAllied RealtyP5220003457411 Apr 202231 Dec 2025—Promised date passed0
Swami Vivekanand PalaceVivekanand ConstructionP522000336942 Mar 202231 Dec 2026—Not yet due0
Anand AppartmentOm Sai Trimurti Buildcon LLPP5220003329615 Feb 202231 Dec 2024—Promised date passed0
Oro Residential SchemeImperio TowersP522000332229 Feb 202231 Dec 2027—Not yet due0
Casa Row Colony Phase - 2Casa DevelopersP5220003250510 Jan 20221 Jan 2024—Promised date passed0
Urban RealtyJ G EnterprisesP5220003251210 Jan 202227 Sep 2023—Promised date passed0
Bhagwati TowerBhagwati EnterprisesP5220003231429 Dec 202131 Dec 2027—Not yet due0
Niramay ParkMonarch PropertiesP5220003226622 Dec 202131 Dec 2025—Promised date passed0
Borude EliteExtreme PropertiesP5220003222315 Dec 202131 Dec 2026—Not yet due0
Venkatesh PlazaPratibha Rajendra JoshiP522000317178 Nov 202131 Oct 2025—Promised date passed0
Krushna HeightsKrishna ConstructionsP522000316593 Nov 202131 Dec 2026—Not yet due0
Sky Bridge VillasManoj Madanlal ChhajedP5220003152725 Oct 202131 Dec 2023—Promised date passed0
Ulka SrushtiSai AssociatesP5220003153525 Oct 202131 Mar 2025—Promised date passed0
AarambhA To Z ConstructionP5220003147823 Oct 202131 Mar 2024—Promised date passed0
Kamath ElinaKamath AssociatesP522000310301 Oct 202131 Dec 2025—Promised date passed0
Premium IconPremium Builders & DevelopersP5220003090529 Sep 202131 Aug 2027—Not yet due0
Adesh HeightsSuresh Namdev LagadP5220003036817 Aug 202131 Dec 2023—Promised date passed0
Sadguru TowersBaba DevelopersP5220002998920 Jul 202131 Mar 2025—Promised date passed0
Sandeep PrideVenkatesh BuildconP5220002859925 Mar 202130 Jun 2032—Not yet due0
Saraswati ResidencyPratap Gulab BhogadeP522000284764 Mar 202130 Jun 2023—Promised date passed0
MagnoliaMadhumalti Costruction Pvt LtdP5220002820110 Feb 202130 Jun 2026—Promised date passed0
Shree Ganesh ApartmentShree Ganesh DevelopersP5220002817510 Feb 202130 Oct 2022—Promised date passed0
Sukrutam ApartmentMakarand Krishnaji DeshpandeP522000281274 Feb 202130 Jun 2023—Promised date passed0
Siyaram Phase IIMadhumalti Costruction Pvt LtdP5220002700010 Nov 202030 Jun 2024—Promised date passed0
Sai SurajRavindra Balasaheb KhardeP522000269467 Nov 202030 Jun 2022—Promised date passed0
Casa Row ColonyCasa BuildersP5220002673521 Oct 202030 Sep 2023—Promised date passed0
AKash 21Akash ConstructionP522000266027 Oct 202030 Nov 2022—Promised date passed0
Parth Heights Phase - 2Rajendra Ramchandra PawarP522000265887 Oct 202030 Oct 2022—Promised date passed0
Swapna Saakar - Phase 1Shubh RealityP5220002615025 Aug 202030 Jun 2026—Promised date passed0
Swapna Saakar - Phase 2Shubh RealityP5220002616725 Aug 202030 Jun 2026—Promised date passed0
Classic IconSanjay Shantilal GugaleP5220002588224 Jul 202030 Jun 2026—Promised date passed0
Sai SarthakKamath AssociatesP522000256641 Jul 202030 Jun 2025—Promised date passed0
Aurum Commercial / Business HubSai Midas RealtiesP5220002556728 Jun 202031 Mar 2027—Not yet due0
Shri Swami Samarth ResidencySuman AssociatesP5220002540923 May 202031 Dec 202430 Jun 2026Extended 18 mo0
Adikailas A1 A2Madhumalti Costruction Pvt LtdP5220002531910 Apr 202030 Mar 2025—Promised date passed0
Devgiri ApartmentSandip Balchand SuranaP5220002498518 Mar 202030 Dec 2023—Promised date passed0
Pari AppartmentAnil Mohan GiteP5220002448318 Feb 202030 Jun 202130 Jun 2022Extended 12 mo0
Shivkunj Phase 2Vedanta RealityP5220002404816 Jan 202030 Dec 2022—Promised date passed0
Jayashree TowerPrasad Babanrao AndhaleP522000231885 Dec 201929 Nov 2024—Promised date passed0
Harishila ParkDeepak Haribhau BangarP522000231614 Dec 201930 Dec 2026—Not yet due0
Adarsh Colony Phase 4 and 5Akash ConstructionP522000228851 Nov 201930 Mar 2022—Promised date passed0

Other localities in Nagar

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Madhumalti Costruction Pvt Ltd7 projects
  2. Prasad Babanrao Andhale6 projects
  3. Makarand Madhav Kulkarni5 projects
  4. Kamath Associates4 projects
  5. Marc Developers4 projects
  6. Akash Construction3 projects
  7. Rajendra Ramchandra Pawar3 projects
  8. Suresh Namdev Lagad3 projects
  9. Ambadas Bhagwat Kadam2 projects
  10. Amit Ashok Mutha2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology