Nagar, Ahmednagar
Deedo IDDL-AHM-NAGAR2 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects228
Registrations228
Completion still due56144 past their date
Median extension4 months24% of registrations extended
Regulatory cases2on 2 projects
8 in 10 registrations run late here
228 MahaRERA registrations in Nagar and the places within it
18 not yet due38 extended, not yet due144 past even the latest date28 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nagar
228 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nakshatra HeightsShashikant Gopinath Bhambare | 1 yr 10 mo late | — | 0% |
| Nathkrupa PlazaNathkrupa Developers | 1 yr 4 mo late | — | 0% |
| Pink City-IIAmit Ashok Mutha | Due Jul 2027, extended 4 mo | — | — |
| Kritikka AarambhaKritikka Realty | Due Jun 2027 | — | 0% |
| Classic AuraSanjay Shantilal Gugale | Due Dec 2027 | — | 0% |
| Jlp Business TowerAditya Builders & Developers (Prop. Jalindar Laxman Palve HUF) | 1 yr 11 mo late | — | 30% |
| Kuber HeightsMula Pravara Corporation | 3 yrs 6 mo late | — | 0% |
| Morya ApartmentsMangalmurti Constructions | 10 mo late | — | 0% |
| Adesh Heights Phase 8Suresh Namdev Lagad | 1 yr 10 mo late | — | 0% |
| Ganesh PrideSanklecha Construction | 1 yr 10 mo late | — | 0% |
| Vivekanand Row BungalowYogesh Balasaheb Mustapure | Due Dec 2026 | — | 100% |
| ArianaMarc Developers | Due Mar 2027 | — | 0% |
| Bappa Residencyketan shrikrishna navle | 1 yr 7 mo late | — | 0% |
| Samairakamath and mulay associates | 2 yrs 8 mo late | — | 0% |
| Team57prideAnand Construction | 1 yr 10 mo late | — | 0% |
| Kamath Mithilakamathdevelopers | 2 yrs 10 mo late | — | — |
| Stellar HeightsVision Group | Due Dec 2026 | — | 0% |
| Nova CasaAllied Realty | 10 mo late | — | 0% |
| Kamath Shalomkamathdevelopers | 1 yr 10 mo late | — | 0% |
| Swami Vivekanand PalaceVivekanand Construction | Due Apr 2027, extended 4 mo | — | 0% |
| Anand AppartmentOm Sai Trimurti Buildcon LLP | 1 yr 10 mo late | — | 0% |
| Oro Residential SchemeImperio Towers | Due Dec 2027 | — | 78% |
| Shankar Parvati Park Phase 2Ganesh Shankarrao Fulari | 1 yr late | — | 30% |
| Casa Row Colony Phase - 2Casa Developers | 2 yrs 9 mo late | — | 0% |
| Urban RealtyJ G Enterprises | 3 yrs 1 mo late | — | 0% |
Nearby: other talukas in Ahmednagar
Most active promoters
- Madhumalti Costruction Pvt Ltd7 projects
- Makarand Madhav Kulkarni6 projects
- Prasad Babanrao Andhale6 projects
- Kamath Associates5 projects
- Akash Construction4 projects
- Marc Developers4 projects
- Rajendra Ramchandra Pawar3 projects
- Suresh Namdev Lagad3 projects
- Ambadas Bhagwat Kadam2 projects
- Amit Ashok Mutha2 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology