Deedo IDDL-WAR-SEWAGRAM8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4
Registrations4
Completion still due04 past their date
Median extension18 months25% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
4 MahaRERA registrations in Sewagram
1 completed3 past even the latest date
Extended registrations moved their completion date by a median of 18 months.
Projects in Sewagram
4 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Little Earth Unit 11Sanjay P. Manmode, Ganesh P. Atkar And Mohan P. Manmode | Completed | — | — |
Nearby: other localities in Wardha
Wardha (M Cl) · 22 projectsPipri (Ct) · 13 projectsSawangi (Meghe) (Ct) · 13 projectsUmari (Meghe) · 13 projectsMasala (Ct) · 12 projectsNalwadi · 10 projectsPavnar · 9 projectsSindi Turf Hindnagar (Ct) · 8 projectsPalakwadi (Wardha) · 6 projectsSindi Kh. · 5 projectsBorgaon (Meghe) (Ct) · 4 projectsChichala · 4 projects
Most active promoters
- D H Infrastructures1 project
- Pawan Poddar And Saurabh Poddar1 project
- Pawan Shriram Poddar1 project
- Sanjay P. Manmode, Ganesh P. Atkar And Mohan P. Manmode1 project
Sewagram, in questions
How many projects in Sewagram run late?
8 in 10 MahaRERA registrations (3 of 4): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sewagram by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology