RERA projects in Kalyandombivali (M Corp.)

206 projects under 227 MahaRERA registrations, registered 2017–2025. 40% have a completion date extended beyond the one promised.

Locality
206RERA projects
227Registrationssome projects hold several
58Completion still due169 past their completion date
4 monthsMedian extension beyond promised date40% of registrations extended
36Regulatory caseson 29 projects
293Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201778
201831
201917
202015
202118
202213
202320
202420
202515

Projects in Kalyandombivali (M Corp.)

206 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Satyam Chopra EnclaveSai Satyam Properties LLPP5170005608610 May 202431 Mar 202731 Jul 2027Extended 4 mo0
Shankheshwar PristineShankheshwar KreatersP5170005585323 Apr 202431 Dec 202831 Dec 2028Not yet due0
Mangalmurti GardenShivam UniversalP5170005575716 Apr 202431 Dec 202630 Apr 2027Extended 4 mo0
Raj Empires Building No.2Raj Pritam ChaturvediP5170005576816 Apr 202431 Mar 202731 Jul 2027Extended 4 mo0
Mangalmurti ParadiseShubham ConstructionP5170005507429 Feb 202431 Dec 202630 Apr 2027Extended 4 mo0
Atmaram HeightsVidhi EnterprisesP5170005493421 Feb 202430 Jun 202730 Oct 2027Extended 4 mo0
BileshwarAshapura CombinesP517000547026 Feb 202431 Dec 202830 Apr 2029Extended 4 mo0
Fatima SkyLfka Builders And DevelopersP5170005432215 Jan 202431 Dec 202730 Apr 2028Extended 4 mo0
Swara EmeraldM/S Samarth Savli HomesP5170005424510 Jan 202430 Nov 2025—Promised date passed0
Vishwanath DarshanAshapura CombinesP5170005413129 Dec 202331 Dec 202930 Apr 2030Extended 4 mo0
Ashapura GoldAshapura BuildtechP5170005411827 Dec 202331 Dec 202731 Dec 2027Not yet due0
Vinayak PreranaNakshatra GroupP5170005364421 Nov 202330 Sep 202630 Jan 2027Extended 4 mo0
Sunteck Crescent ParkSunteck Property Holdings Private LimitedP51700053312, P5170005343927 Oct 202331 Dec 203130 Apr 2032Extended 4 mo0
Shreerang KutirShree Prabha ConstructionP5170005299710 Oct 20231 Jun 20261 Oct 2026Extended 4 mo0
Sumati SkylineSubhash Skyline InfraP5170005264015 Sep 202330 Sep 2026—Promised date passed0
Mangalmurti PrideSai Mauli EnterprisesP5170005258811 Sep 202331 Dec 202631 Dec 2026Not yet due0
Nandadeep CHS LtdAditya BuildconP517000524508 Sep 202331 Mar 202831 Jul 2028Extended 4 mo0
Gayatri Sankul NxGayatri BuildersP5170005222431 Jul 202331 Dec 202731 Dec 2027Not yet due0
Seasons GreenJai Balaji Sai RealtorsP5170005157527 Jun 202331 Dec 202730 Apr 2028Extended 4 mo0
Metro LuxuriaNivara EngineersP517000514108 Jun 202331 Dec 202731 Dec 2027Not yet due0
Shree Ram Radha DamodarAditya BuildconP5170005063421 Apr 202331 Mar 202631 Mar 2026Promised date passed0
Lucky HeightLfka Builders And DevelopersP517000503031 Apr 202331 Dec 2025—Promised date passed0
Sd GalaxySomeshwarnath Developers & BuildersP517000498576 Mar 202331 Dec 202730 Apr 2028Extended 4 mo0
Yashlata PalacePradeep Shyam KharbadeP517000499156 Mar 202331 Dec 202431 Dec 2024Promised date passed0
Swami ChetanaOm Sai Builders And DevelopersP5170004974024 Feb 202330 Apr 202531 Dec 2026Extended 20 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Neptune Developers Limited17 projects
  2. Neptune Developers Ltd12 projects
  3. Lfka Builders And Developers5 projects
  4. Ashapura Combines3 projects
  5. Shankheshwar Kreaters3 projects
  6. Aditya Buildcon2 projects
  7. Amber Buildcon2 projects
  8. Anjana Sahebrao Chavan2 projects
  9. Deiv Enterprises2 projects
  10. Ganesha Developers2 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology