Deedo IDDP-THN-CYVPCompletion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.
Hedutane, Thane 421203 · by Lodha Developers Limited · 93% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- This projectRegistered 15 Oct 2024, completion promised 31 Dec 2030, revised to 30 Apr 2031.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700077599
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700077599 | 15 Oct 2024 | 31 Dec 2030 | 30 Apr 2031 | Lodha Developers Limited | Project page |
Documents183
2 documents held by Deedo, 181 filings listed on MahaRERA's project page
Finance
Show all 183 documentsShow fewer documents
Legal
- Declaration Form B1035_001.pdf · uploaded 12 Aug 2024Source
- Declaration Form B1035_001.pdf · uploaded 12 Aug 2024Source
- Declaration Form B1035_001.pdf · uploaded 12 Aug 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
Migrated
- 1 PAN Card1 PAN Card (7).pdf · uploaded 9 Aug 2024Source
- 1 Copy of the legal title reportHedutane Consolidated Title Report_Belvedere.pdf · uploaded 9 Aug 2024Source
- 1 a Details of encumbrances concerned to FinanceFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 a Details of encumbrances concerned to Financelegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentNew CC.pdf · uploaded 9 Aug 2024Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 9 Aug 2024Source
- 1 b Details of encumbrances concerned to LegalFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 b Details of encumbrances concerned to Legallegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (10).pdf · uploaded 9 Aug 2024Source
- 1 PAN Card1 PAN Card (7).pdf · uploaded 9 Aug 2024Source
- 1 Copy of the legal title reportHedutane Consolidated Title Report_Belvedere.pdf · uploaded 9 Aug 2024Source
- 1 a Details of encumbrances concerned to FinanceFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 a Details of encumbrances concerned to Financelegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentNew CC.pdf · uploaded 9 Aug 2024Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 9 Aug 2024Source
- 1 b Details of encumbrances concerned to LegalFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 b Details of encumbrances concerned to Legallegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (10).pdf · uploaded 9 Aug 2024Source
- 1 PAN Card1 PAN Card (7).pdf · uploaded 9 Aug 2024Source
- 1 Copy of the legal title reportHedutane Consolidated Title Report_Belvedere.pdf · uploaded 9 Aug 2024Source
- 1 a Details of encumbrances concerned to FinanceFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 a Details of encumbrances concerned to Financelegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentNew CC.pdf · uploaded 9 Aug 2024Source
- 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 9 Aug 2024Source
- 1 b Details of encumbrances concerned to LegalFiance Enc.pdf · uploaded 9 Aug 2024Source
- 2 b Details of encumbrances concerned to Legallegal encum.pdf · uploaded 9 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (10).pdf · uploaded 9 Aug 2024Source
- 1 Copy of Layout Approval (in case of layout)Belvedere Wing I.pdf · uploaded 10 Aug 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- 1 CERSAI detailsCERSAI_Search_Report_200316662385_For_Asset_Based_Search_10_08_2024_09_55_50_243.pdf · uploaded 10 Aug 2024Source
- 2 CERSAI detailsCersai Decla.pdf · uploaded 10 Aug 2024Source
- 1 Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectSecure unsecure.pdf · uploaded 10 Aug 2024Source
- 1 Copy of Layout Approval (in case of layout)Belvedere Wing I.pdf · uploaded 10 Aug 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- 1 CERSAI detailsCERSAI_Search_Report_200316662385_For_Asset_Based_Search_10_08_2024_09_55_50_243.pdf · uploaded 10 Aug 2024Source
- 2 CERSAI detailsCersai Decla.pdf · uploaded 10 Aug 2024Source
- 1 Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectSecure unsecure.pdf · uploaded 10 Aug 2024Source
- 1 Copy of Layout Approval (in case of layout)Belvedere Wing I.pdf · uploaded 10 Aug 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- 1 CERSAI detailsCERSAI_Search_Report_200316662385_For_Asset_Based_Search_10_08_2024_09_55_50_243.pdf · uploaded 10 Aug 2024Source
- 2 CERSAI detailsCersai Decla.pdf · uploaded 10 Aug 2024Source
- 1 Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectSecure unsecure.pdf · uploaded 10 Aug 2024Source
- 1 Declaration in FORM B1035_001.pdf · uploaded 12 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Aug 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 12 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Letter to MDL.pdf · uploaded 12 Aug 2024Source
- 1 Declaration in FORM B1035_001.pdf · uploaded 12 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Aug 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 12 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Letter to MDL.pdf · uploaded 12 Aug 2024Source
- 1 Declaration in FORM B1035_001.pdf · uploaded 12 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Aug 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 12 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Letter to MDL.pdf · uploaded 12 Aug 2024Source
- 1 Proforma of Allotment letter1 Other – Legal (10).pdf · uploaded 9 Oct 2024Source
- 1 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 2 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Agreement for sale3 Other – Legal (3).pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Allotment letter1 Other – Legal (10).pdf · uploaded 9 Oct 2024Source
- 1 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 2 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Agreement for sale3 Other – Legal (3).pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Allotment letter1 Other – Legal (10).pdf · uploaded 9 Oct 2024Source
- 1 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 2 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Agreement for sale3 Other – Legal (3).pdf · uploaded 9 Oct 2024Source
- 1 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 1 Other – Legalहेदुटणे_25_2_अ_Satbara.pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Agreement for sale3 Other – Legal (3).pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Allotment letter1 Other – Legal (10).pdf · uploaded 9 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)bank Format A.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterAL -Devi Bel.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementDevi AFS Bel.pdf · uploaded 10 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)bank Format A.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterAL -Devi Bel.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementDevi AFS Bel.pdf · uploaded 10 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)bank Format A.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterAL -Devi Bel.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementDevi AFS Bel.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterAL -Devi Bel.pdf · uploaded 10 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementDevi AFS Bel.pdf · uploaded 10 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)bank Format A.pdf · uploaded 10 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold Belvedere I Dec 2024.pdf · uploaded 23 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Belvedere I.pdf · uploaded 24 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Belvedere I - Form 2 and 3 - Dec 24.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Belvedere I - Form 2 and 3 - Dec 24.pdf · uploaded 24 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Belvedere I.pdf · uploaded 2 May 2025Source
- Form 1Form1-Belvedere I -March 25.pdf · uploaded 6 Jun 2025Source
- Form 2Signed Belvedere I Declaration - Form 2 - March 2025.pdf · uploaded 6 Jun 2025Source
- Form 3Signed Belvedere I Declaration - Form 3 - March 2025.pdf · uploaded 6 Jun 2025Source
- Disclosure of Sold and Booked InventorySigned Sold Unsold Belvedere I March 2025.pdf · uploaded 6 Jun 2025Source
- Self-declaration of Quarterly ProgressDeclaration.pdf · uploaded 6 Jun 2025Source
- Form 1Belvedere I - Form1 - June 25 - P51700077599-ok.pdf · uploaded 18 Jul 2025Source
- Form 2Belvedere I Form 2 June 2025.pdf · uploaded 18 Jul 2025Source
- Form 3Belvedere I Form 3 June 2025.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryBelvedere I Sold Unsold June 2025.pdf · uploaded 18 Jul 2025Source
- Self-declaration of Quarterly ProgressUpdated CC.pdf · uploaded 18 Jul 2025Source
- OthersLayout - Belvedere - Cluster 15 01 Wing I.pdf · uploaded 18 Jul 2025Source
- Form 2A (FY 2024-2025)Belvedere I - P51700077599 - Form 2A.pdf · uploaded 25 Jul 2025Source
- Form 5 (FY 2024-2025)Belvedere I.pdf · uploaded 22 Oct 2025Source
- Withdrawal Update Form 1Belvedere I (1).pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 2Form 02 - Belvedere I - Sep 25 signed.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 3Form 03 - Belvedere I - Sep 25 signed.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 1Form-1 Belvedere I--.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 2Belvedere I Form 02 Signed Dec 25.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 3Belvedere I Form 03 Signed Dec 25.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 1Form-1 Belvedere I--.pdf · uploaded 13 Apr 2026Source
- Withdrawal Update Form 2Belvedere I Form 02 Signed Dec 25.pdf · uploaded 13 Apr 2026Source
- Withdrawal Update Form 3Belvedere I Form 03 Signed Dec 25.pdf · uploaded 13 Apr 2026Source
- Withdrawal Update Form 1Form1 - Belvedere I - P51700077599.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Belvedere I Mar 2026 - Form 02 Signed.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Belvedere I Mar 2026 - Form 03 Signed.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A - Belvedere I - P51700077599.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 1Form1 - Belvedere I - P51700077599.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 June 2026 - P51700077599 D.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 June 2026 - P51700077599 D.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Belvedere I.pdf · uploaded 29 Sep 2026Source
Technical
- DocumentBelvedere Wing I.pdf · uploaded 10 Aug 2024Source
- DocumentBelvedere Wing I.pdf · uploaded 10 Aug 2024Source
- DocumentBelvedere Wing I.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N38 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N37 - converted.pdf · uploaded 10 Aug 2024Source
- DocumentPalava 2 - CC - Sheet N36 - converted (2).pdf · uploaded 10 Aug 2024Source
- Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- Other – TechnicalOrder 50.pdf · uploaded 10 Aug 2024Source
- DocumentBelvedere - Cluster 1501 Wing I - converted.pdf · uploaded 22 Nov 2025Source
- DocumentBelvedere - Cluster 1501 Wing I - converted.pdf · uploaded 25 Nov 2025Source
- DocumentBelvedere Wing I (1)-Compres.pdf · uploaded 16 Jul 2026Source
- Document20260217 - Sheet 46.pdf · uploaded 16 Jul 2026Source
- Document20260217 - Sheet 47.pdf · uploaded 16 Jul 2026Source
- Document20260217 - Sheet 48.pdf · uploaded 16 Jul 2026Source
- DocumentBelvedere Wing I (1)-Compres.pdf · uploaded 20 Jul 2026Source
- Document20260217 - Sheet 46.pdf · uploaded 20 Jul 2026Source
- Document20260217 - Sheet 47.pdf · uploaded 20 Jul 2026Source
- Document20260217 - Sheet 48.pdf · uploaded 20 Jul 2026Source
- DocumentLatest CC 17022026.pdf · uploaded 20 Jul 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 25/2A Part 25/2B Part
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —95 units in all
- Address
- 25/2A Part 25/2B Part, Hedutane, HedutanePIN 421203
- Village
- Hedutane, Kalyan taluka
- Land area for this project
- 1,459 sq m (15,705 sq ft)
- Permissible built-up area
- 11,232 sq m (1,20,899 sq ft)
- Sanctioned built-up area
- 11,232 sq m (1,20,899 sq ft)
- Recreational open space
- 145 sq m (1,561 sq ft)
- Designated bank account
- 229
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
25/2A Part 25/2B Part
Boundaries
- North
- 25 2A Part 25 2B Part
- South
- 25 1 Part
- East
- 29 Part
- West
- 25 4 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking95 units
95 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 95 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pradeep Kamble | — |
| Architect | Vilas Desai & Associate | — |
| Chartered accountant | Chirag Sarvaiya | — |
| Chartered accountant | Chirag Sarvaiya & Co | — |
| Engineer | Dadaso Gavali | — |
| Engineer | Kaivant Shah | — |
| Engineer | K C Shah Consultants | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Hedutane
- BelvedereRERA P51700078177
- Belvedere-B and CRERA P51700052950
- FioraRERA P51700052406
- BelvedereRERA P51700052237
- Casa BelvedereRERA P51700046311
- FioraRERA P51700046352
- Fiora FRERA P51700046315
- FioraRERA P51700033965
All 11 projects in Hedutane · Compare Belvedere I with another project