Vaishnavi Heights
Deedo IDDP-THN-2XP7Its promised completion date, Jan 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Chinchpada, Thane 421306 · by Vaishnavi Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jan 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 9 Jan 2020, completion promised 1 Jan 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700023882
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700023882 | 9 Jan 2020 | 1 Jan 2024 | 1 Jan 2024 | Vaishnavi Developers | Project page |
Documents66
1 document held by Deedo, 65 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card.pdf · uploaded 31 Dec 2019Source
Legal
Migrated
- 1 PAN CardPan Card.pdf · uploaded 31 Dec 2019Source
- 1 Copy of the legal title reporttitle certificate.pdf · uploaded 31 Dec 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 31 Dec 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 31 Dec 2019Source
Show all 66 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 1 Jan 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentlayout plan.pdf · uploaded 1 Jan 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentfloor plan.pdf · uploaded 1 Jan 2020Source
- 1 Details of encumbrancesNo Encumbrance.pdf · uploaded 3 Jan 2020Source
- 1 Declaration in FORM BFB.pdf · uploaded 3 Jan 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca_compressed.pdf · uploaded 7 Jan 2020Source
- 1 Proforma of Allotment letter1.pdf · uploaded 7 Jan 2020Source
- 2 Proforma of Allotment letter2.pdf · uploaded 7 Jan 2020Source
- 3 Proforma of Allotment letter3.pdf · uploaded 7 Jan 2020Source
- 4 Proforma of Allotment letter4.pdf · uploaded 7 Jan 2020Source
- 5 Proforma of Allotment letterALLOTMENT 01.pdf · uploaded 7 Jan 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2A_compressed.pdf · uploaded 1 Jul 2020Source
- 1 Details of Restarting of Construction work post lockdownCOVID-19.pdf · uploaded 1 Jul 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS FORM 2.pdf · uploaded 5 Jul 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)signed CA Certificate-Vaishnavi Developers-final.pdf · uploaded 7 Jul 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 8 Jul 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)NM RERA COMPLETION.pdf · uploaded 8 Jul 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)vaishanvi heights rera update.pdf · uploaded 15 Feb 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)vaishanvi heights rera update.pdf · uploaded 15 Feb 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 22 Feb 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)engg certificate.pdf · uploaded 22 Feb 2023Source
- 1 Other – Technicalpropriter rera update sir (1).pdf · uploaded 22 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)2019-20.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)2020-21.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)2021-22.pdf · uploaded 4 May 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society formation certificate.pdf · uploaded 12 Feb 2024Source
- 2 Details of encumbrancesvh propriter NO ENCUMBURANCE.pdf · uploaded 16 Feb 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentvaishnavi heights cc.pdf · uploaded 16 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect form 1.pdf · uploaded 7 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 19-20.pdf · uploaded 7 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 20-21.pdf · uploaded 7 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 21-22.pdf · uploaded 7 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 22-23.pdf · uploaded 7 Mar 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 12 20.pdf · uploaded 22 Mar 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 12 21.pdf · uploaded 22 Mar 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 03 23.pdf · uploaded 22 Mar 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 06 23.pdf · uploaded 22 Mar 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 09 23.pdf · uploaded 22 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 12 20.pdf · uploaded 27 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 12 21.pdf · uploaded 27 Mar 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 01 23.pdf · uploaded 27 Mar 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 06 23.pdf · uploaded 27 Mar 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 09 23.pdf · uploaded 27 Mar 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 01 20.pdf · uploaded 27 Mar 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 10 Jun 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 10 Jun 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 10 Jun 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 10 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 10 Jun 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 oct to dec 2020.pdf · uploaded 11 Jun 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (14).pdf · uploaded 11 Jun 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 23 Jul 2024Source
Technical
Technical (Architect)
- Documentform 1 09 23.pdf · uploaded 22 Mar 2024Source
Technical (Engineer)
- Documentform 2 01 20.pdf · uploaded 27 Mar 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT BEARING S NO 20 H NO 22
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK46 units in all
- Address
- Plot Bearing S No 20 H No 22, Chinchpada Road Near Balaji Chowk, KalyanPIN 421306
- Village
- Chinchpada, Ambarnath taluka
- Land area for this project
- 2,000 sq m (21,528 sq ft)
- Permissible built-up area
- 1,928 sq m (20,751 sq ft)
- Sanctioned built-up area
- 1,928 sq m (20,751 sq ft)
- Designated bank account
- 108
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT BEARING S NO 20 H NO 22
Boundaries
- North
- Vaishnavi Apartment
- South
- Open Land
- East
- Open Land
- West
- Existing Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking46 units
0 of 46 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 27.24 sq m · 293 sq ft | 6 | 0 |
| 1BHK | 27.77 sq m · 299 sq ft | 7 | 0 |
| 1BHK | 28.61 sq m · 308 sq ft | 1 | 0 |
| 1BHK | 30.48 sq m · 328 sq ft | 2 | 0 |
| 1BHK | 31.06 sq m · 334 sq ft | 3 | 0 |
| 1BHK | 31.11 sq m · 335 sq ft | 3 | 0 |
| 1BHK | 31.29 sq m · 337 sq ft | 1 | 0 |
| 1BHK | 31.43 sq m · 338 sq ft | 3 | 0 |
Show all 14 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.64 sq m · 341 sq ft | 6 | 0 |
| 2BHK | 41.94 sq m · 451 sq ft | 3 | 0 |
| 2BHK | 41.95 sq m · 452 sq ft | 3 | 0 |
| 2BHK | 42.03 sq m · 452 sq ft | 3 | 0 |
| 2BHK | 42.15 sq m · 454 sq ft | 4 | 0 |
| 2BHK | 45.06 sq m · 485 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | De Con Consultants | — |
| Chartered accountant | Nehali & Co | — |
| Engineer | Ana Consulting | — |
| Other | Hrishikant Bibhishan Dhas | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Chinchpada
- Vaishnavi HeavenRERA PR1330002502284
- Magan UltimaRERA PM1330002500880
- Shree Samarth ParadiseRERA P51700080081
- Kurm Casa VaishnaviRERA P51700078019
- Mountain ViewRERA P51700076812
- Mahadev HeightsRERA P51700055444
- Baliram Tare ResidencyRERA P51700047951
- Vaishnavi PrideRERA P51700046405
All 12 projects in Chinchpada · Compare Vaishnavi Heights with another project