Skip to content
Others · 2 buildings · 33 unitsRERA P51700055444

Mahadev Heights

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 33% of its units are booked.

Chinchpada, Thane 421306 · Promoter: Sonali Homes LLP

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked11 of 33 units · as the promoter reported to MahaRERA
Mahadev Heights project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 22 Mar 2024, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700055444
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005544422 Mar 202431 Dec 202930 Apr 2030Sonali Homes LLPProject page
Documents91

1 document held by Deedo, 90 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 6 Feb 2024Source

Legal

  • Legal Title reportLegal Title Report_0001.pdf · uploaded 8 Feb 2024Source
  • Legal Title reportThe Title Of Side Land_0001.pdf · uploaded 8 Feb 2024Source
  • Other – Legalचिंचपाडा_10_22_Satbara.pdf · uploaded 20 Feb 2024Source
  • Other – Legal339 8353_0001_compressed-compressed - converted (4).pdf · uploaded 20 Feb 2024Source
  • Other – LegalLLP Agreement_0001_compressed.pdf · uploaded 20 Feb 2024Source
  • Declaration Form BForm-B Developers Revised.pdf · uploaded 11 Mar 2024Source
Show all 91 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN.pdf · uploaded 6 Feb 2024Source
  • 1 Declaration about Commencement CertificateFormat D Declaration About Commencement Certificate_0001.pdf · uploaded 6 Feb 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form-1_0001.pdf · uploaded 6 Feb 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_0001.pdf · uploaded 6 Feb 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sonali Homes LLP_0001_compressed.pdf · uploaded 6 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Bharat Mhatre_0001.pdf · uploaded 6 Feb 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Ashish Joshi_0001.pdf · uploaded 6 Feb 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Sonali Mhatre_0001.pdf · uploaded 6 Feb 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Suraj Mhatre_0001.pdf · uploaded 6 Feb 2024Source
  • 1 Proforma of Allotment letterAllotment Letter_0001_0001_compressed.pdf · uploaded 6 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Details.pdf · uploaded 6 Feb 2024Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20240111_0002 (1)_rotated.pdf · uploaded 7 Feb 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentMYSCAN_20240111_0001_rotated (1).pdf · uploaded 7 Feb 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentMYSCAN_20240111_0002 (1)_rotated.pdf · uploaded 7 Feb 2024Source
  • 1 Other – TechnicalUndertaking.pdf · uploaded 7 Feb 2024Source
  • 1 Copy of the legal title reportLegal Title Report_0001.pdf · uploaded 8 Feb 2024Source
  • 2 Copy of the legal title reportThe Title Of Side Land_0001.pdf · uploaded 8 Feb 2024Source
  • 1 a Details of encumbrances concerned to Financedec legal.pdf · uploaded 8 Feb 2024Source
  • 1 b Details of encumbrances concerned to Legaldec legal.pdf · uploaded 8 Feb 2024Source
  • 2 Copy of Layout Approval (in case of layout)MYSCAN_20240111_0001.pdf · uploaded 8 Feb 2024Source
  • 1 CERSAI detailsDeclaration For No Cersai Report_0001_0001.pdf · uploaded 8 Feb 2024Source
  • 2 CERSAI detailsCERSAI_Search_Report_200296167295_For_Asset_Based_Search_08_02_2024_10_41_10_969.pdf · uploaded 8 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letterreport allotment letter.pdf · uploaded 8 Feb 2024Source
  • 1 Deviation Report with respect to model copy of Agreementreport on agreement for sale.pdf · uploaded 8 Feb 2024Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration For Financial Encumrbances_0001_0001.pdf · uploaded 20 Feb 2024Source
  • 2 b Details of encumbrances concerned to LegalDeclaration For Financial Encumrbances_0001_0001.pdf · uploaded 20 Feb 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_0001.pdf · uploaded 20 Feb 2024Source
  • 1 Other – Legalचिंचपाडा_10_22_Satbara.pdf · uploaded 20 Feb 2024Source
  • 2 Other – Legal339 8353_0001_compressed-compressed - converted (4).pdf · uploaded 20 Feb 2024Source
  • 3 Other – LegalLLP Agreement_0001_compressed.pdf · uploaded 20 Feb 2024Source
  • 1 Declaration in FORM BForm-B Developers Revised.pdf · uploaded 11 Mar 2024Source
  • 1 Proforma of Agreement for saleRERA Agreement-Sonali Homes-Revised.pdf · uploaded 11 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 30-06-2024_0001.pdf · uploaded 17 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 30-06-2024_0001.pdf · uploaded 17 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 FY 2023-24 Sign_compressed (1).pdf · uploaded 9 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 arch certificate.pdf · uploaded 2 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng certificate.pdf · uploaded 2 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 31-12-2024.pdf · uploaded 2 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 31-12-2024.pdf · uploaded 2 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 30-06-2024 Sign.pdf · uploaded 24 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 30-09-2024 Sign.pdf · uploaded 24 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03 Sonali Homes LLP_0001.pdf · uploaded 24 Jan 2025Source
  • 1 Disclosure of sold/ booked inventory300924.pdf · uploaded 17 Feb 2025Source
  • 2 Disclosure of sold/ booked inventory311224.pdf · uploaded 17 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 31-03-2025.pdf · uploaded 2 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 31-03-2025.pdf · uploaded 12 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03 Q4 Sign.pdf · uploaded 15 Apr 2025Source
  • 1 Disclosure of sold/ booked inventory20250417120609.pdf · uploaded 17 Apr 2025Source
  • Form 1Form1 31032025 Sonali Homes.pdf · uploaded 11 Jul 2025Source
  • Form 2Form2 31032025 Sonali Homes.pdf · uploaded 11 Jul 2025Source
  • Form 3Form3 31032025 Sonali homes.pdf · uploaded 11 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Form 31032025 Sonali Homes.pdf · uploaded 11 Jul 2025Source
  • Withdrawal Update Form 1Form-1 30-06-2025.pdf · uploaded 29 Jul 2025Source
  • Withdrawal Update Form 2Form-2 30-06-2025.pdf · uploaded 29 Jul 2025Source
  • Withdrawal Update Form 31Signed Form 3 Sonali homes LLP.pdf · uploaded 29 Jul 2025Source
  • Form 5 (FY 2024-2025)Form-5 FY 2024-25 Signed.pdf · uploaded 3 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Sept 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Sept 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3Signed Form 3.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3Form-3.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1Form-1 31-03-2026_compressed (1).pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form-2 31-03-2026_compressed (1).pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form-3 31-03-2026.pdf · uploaded 24 Apr 2026Source
  • Form 2A (FY 2025-2026)Form-2A FY 2025-26 Signed_compressed.pdf · uploaded 4 May 2026Source
  • Form 5 (FY 2025-2026)Form-5 FY 2025-26 Signed.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 SIGNED.pdf · uploaded 1 Aug 2026Source

Technical

  • DocumentMYSCAN_20240111_0002 (1)_rotated.pdf · uploaded 7 Feb 2024Source
  • DocumentMYSCAN_20240111_0001_rotated (1).pdf · uploaded 7 Feb 2024Source
  • DocumentMYSCAN_20240111_0002 (1)_rotated.pdf · uploaded 7 Feb 2024Source
  • Other – TechnicalUndertaking.pdf · uploaded 7 Feb 2024Source
  • DocumentMYSCAN_20240111_0001.pdf · uploaded 8 Feb 2024Source

Technical (Architect)

  • DocumentForm 1 arch certificate.pdf · uploaded 2 Dec 2024Source
  • DocumentForm-1 31-12-2024.pdf · uploaded 2 Jan 2025Source
  • DocumentForm-1 31-03-2025.pdf · uploaded 2 Apr 2025Source
  • DocumentForm 1.pdf · uploaded 1 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 Eng certificate.pdf · uploaded 2 Dec 2024Source
  • DocumentForm-2 31-12-2024.pdf · uploaded 2 Jan 2025Source
  • DocumentForm-2 31-03-2025.pdf · uploaded 12 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 1 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsHISSA NO 22, SURVEY NO 10

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK33 units in all
Address
Survey No 10, Hissa No 22, Chinchpada, Kalyan EastPIN 421306
Village
Chinchpada, Ambarnath taluka
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

HISSA NO 22SURVEY NO 10

Boundaries

North
Land
South
Property Of Chandrabhaga Bodke
East
Property Of Chandrabhaga Bodke
West
Property Pf Balaram Mhatre

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking33 units

11 of 33 units booked (33%), as the promoter reported to MahaRERA

1BHK · 25 units2BHK · 8 units
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK34.69 sq m · 373 sq ft20
A Wing1BHK38.24 sq m · 412 sq ft20
A Wing2BHK51.81 sq m · 558 sq ft10
B Wing1BHK35.94 sq m · 387 sq ft72
B Wing1BHK36.03 sq m · 388 sq ft75
B Wing1BHK36.37 sq m · 391 sq ft73
B Wing2BHK47.06 sq m · 507 sq ft71

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNikhil Borade—
ArchitectSaini And Associates—
Chartered accountantMayur K Jain And Co—
EngineerDev And Associates—
EngineerPranali Barku Joshi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology