Residential / Group Housing · 3 buildings · 324 unitsRERA P51700047616

Tulsi Aaradhana

Deedo IDDP-THN-KDFA

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 54% of its units are booked.

Badlapur, Thane 421503 · by Raj Group · 71% of its projects kept the RERA date

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales54% booked174 of 324 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 14 Nov 2022, completion promised 31 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700047616
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004761614 Nov 202231 Dec 202531 Dec 2025Raj GroupProject page
Documents109

1 document held by Deedo, 108 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 2 Aug 2022Source

Legal

  • Legal Title reportRera title ph-9_compressed.pdf · uploaded 18 Jun 2022Source
  • Legal Title reportSearch Conso_compressed.pdf · uploaded 18 Jun 2022Source
  • Declaration Form BFORM-B Tulsi Aaradhana_compressed.pdf · uploaded 18 Jun 2022Source
  • Other – LegalRevised AFS Tulsi Aaradhana.pdf · uploaded 4 Nov 2022Source

Migrated

  • 1 Copy of the legal title reportRera title ph-9_compressed.pdf · uploaded 18 Jun 2022Source
  • 2 Copy of the legal title reportSearch Conso_compressed.pdf · uploaded 18 Jun 2022Source
Show all 109 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesCertificate Tulsi Aaradhana.pdf · uploaded 18 Jun 2022Source
  • 1 Copy of Layout Approval (in case of layout)P-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 18 Jun 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentP-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 18 Jun 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentPhase-09 CC.pdf · uploaded 18 Jun 2022Source
  • 1 Declaration about Commencement CertificateForm-D Tulsi Aaradhana_compressed.pdf · uploaded 18 Jun 2022Source
  • 1 Declaration in FORM BFORM-B Tulsi Aaradhana_compressed.pdf · uploaded 18 Jun 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200240039253_For_Asset_Based_Search_18_06_2022_12_34_43_752.pdf · uploaded 18 Jun 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentP-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 5 Jul 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentPhase-09 CC.pdf · uploaded 5 Jul 2022Source
  • 1 PAN CardPan Card.pdf · uploaded 2 Aug 2022Source
  • 1 b Details of encumbrances concerned to LegalCertificate Tulsi Aaradhana.pdf · uploaded 2 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Bank.pdf · uploaded 2 Aug 2022Source
  • 1 Deviation Report with respect to Allotment letterDeclaration Allotment deviation.pdf · uploaded 2 Aug 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentP-09 Layout Plan 1 of 3.pdf · uploaded 24 Aug 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentP-09 Layout Plan 2 of 3.pdf · uploaded 24 Aug 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentP-09 Layout Plan 3 of 3.pdf · uploaded 24 Aug 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentPlinth Completion Certificate_compressed.pdf · uploaded 24 Aug 2022Source
  • 1 Proforma of Allotment letterAllotment Letter - Tulsi Aaradhana.pdf · uploaded 24 Aug 2022Source
  • 1 Proforma of Agreement for saleRevised AFS Tulsi Aaradhana.pdf · uploaded 24 Aug 2022Source
  • 4 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 19 Sep 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Sep 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report of RajGroup.pdf · uploaded 19 Sep 2022Source
  • 1 Other – LegalRevised AFS Tulsi Aaradhana.pdf · uploaded 4 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 PHASE-9 TULSI AARADHANA.pdf · uploaded 24 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 PHASE-9 TULSI AARADHANA.pdf · uploaded 27 Mar 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Tulsi Aaradhana.pdf · uploaded 27 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 PHASE-9 TULSI AARADHANA.pdf · uploaded 3 Aug 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 DATED 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-1 DATED 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-03-2023_compressed.pdf · uploaded 3 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM-2A 31-03-2023.pdf · uploaded 3 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 JUN -2023 (Aaradhana)_compressed.pdf · uploaded 16 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1- 30092023 Aaradhana_compressed.pdf · uploaded 1 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Tulsi Aaradhana June 23.pdf · uploaded 1 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Tulsi Aaradhana - Form 2-Sep23.pdf · uploaded 1 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3-Mar 23_Tulsi Aaradhna.pdf · uploaded 1 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 DEC-2023 Aaradhana.pdf · uploaded 15 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-Tulsi Aaradhana PH 9_Apr23 To Jun23-Compressed.pdf · uploaded 15 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-Tulsi Aaradhana PH 9_Jul23 To Sep23_Compressed.pdf · uploaded 15 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q3- Aaradhana.pdf · uploaded 25 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5- 31 MARCH 2023 Aaradhana.pdf · uploaded 25 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Tulsi Aananda-Q3_compressed.pdf · uploaded 29 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3-Tulsi Aaradhana-Q3_compressed.pdf · uploaded 29 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySigned Disclosure of Sold_Unsold Inventory Tulsi Aaradhana PH 9_compressed.pdf · uploaded 18 May 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 Q4 Tulsi Aaradhna_compressed.pdf · uploaded 18 May 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Aadradhna.pdf · uploaded 23 May 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Aaradhana.pdf · uploaded 23 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30062024_ Compressed.pdf · uploaded 14 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold-unsold inventory 30062024 (Aaradhana) Compressed.pdf · uploaded 14 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30062024_ Compressed.pdf · uploaded 14 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold-unsold inventory 30062024 (Aaradhana) Compressed.pdf · uploaded 14 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 22 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 22 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 23 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 23 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Tulsi Aaradhana.pdf · uploaded 9 Dec 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of sold and unsold inventory Aaradhana_11zon.pdf · uploaded 24 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A Aaradhana.pdf · uploaded 26 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Aaradhana Q3.pdf · uploaded 31 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM- 3 Aaradhana Q3.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold inventory Q3 Aaradhna.pdf · uploaded 31 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q3 Aaradhana.pdf · uploaded 7 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31_03_2025 Tulsi Aaradhana.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31_03_2025 Aaradhana.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31_03_2025 Aaradhana_11zon.pdf · uploaded 5 May 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold-unsold inventory 31_03_2025 (Aaradhana)_11zon.pdf · uploaded 6 May 2025Source
  • Form 1FORM-1 Q1 Aaradhana.pdf · uploaded 15 Jan 2026Source
  • Form 2FORM-2 Q1 Aaradhana.pdf · uploaded 15 Jan 2026Source
  • Form 3Form 3_Tulsi Aradhana_Q1_compressed.pdf · uploaded 15 Jan 2026Source
  • Disclosure of Sold and Booked InventoryTulsi Aradhana Q1 Disclosure of Sold_Unsold Unit.pdf · uploaded 15 Jan 2026Source
  • Form 1FORM-1 Q2-2025 Aaradhana.pdf · uploaded 15 Jan 2026Source
  • Form 2FORM-2 Q2- 2025 Aaradhana.pdf · uploaded 15 Jan 2026Source
  • Form 3Form 3_Tulsi Aradhana_Q2_compressed.pdf · uploaded 15 Jan 2026Source
  • Disclosure of Sold and Booked InventoryTulsi Aaradhana Q2 Disclosure of Sold_Unsold Unit.pdf · uploaded 15 Jan 2026Source
  • Form 1FORM 1.pdf · uploaded 3 Feb 2026Source
  • Form 2FORM 2.pdf · uploaded 3 Feb 2026Source
  • Form 3Form3_compressed.pdf · uploaded 3 Feb 2026Source
  • Disclosure of Sold and Booked InventoryRaj Group Tulsi Aaradhana Q3 Sold_Unsold Unit.pdf · uploaded 3 Feb 2026Source

Technical

  • DocumentP-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 18 Jun 2022Source
  • DocumentP-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 18 Jun 2022Source
  • DocumentP-09 Layout Plan 1 of 3_compressed_compressed.pdf · uploaded 5 Jul 2022Source
  • DocumentP-09 Layout Plan 1 of 3.pdf · uploaded 24 Aug 2022Source
  • DocumentP-09 Layout Plan 2 of 3.pdf · uploaded 24 Aug 2022Source
  • DocumentP-09 Layout Plan 3 of 3.pdf · uploaded 24 Aug 2022Source

Technical (Architect)

  • DocumentFORM 1 Aadradhna.pdf · uploaded 23 May 2024Source
  • DocumentFORM-1 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-1 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-1.pdf · uploaded 22 Nov 2024Source
  • DocumentFORM-1 Aaradhana Q3.pdf · uploaded 31 Jan 2025Source
  • DocumentFORM 1 31_03_2025 Tulsi Aaradhana.pdf · uploaded 2 May 2025Source

Technical (Engineer)

  • DocumentFORM 2 Aaradhana.pdf · uploaded 23 May 2024Source
  • DocumentFORM-2 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-2 30062024 Aaradhana.pdf · uploaded 14 Oct 2024Source
  • DocumentFORM-2.pdf · uploaded 23 Nov 2024Source
  • DocumentFORM-2.pdf · uploaded 23 Nov 2024Source
  • DocumentFORM 2 Q3 Aaradhana.pdf · uploaded 7 Feb 2025Source
  • DocumentFORM 2 31_03_2025 Aaradhana.pdf · uploaded 2 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S No41 H No5A, S No42 H No1A S No44 H NoC

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—324 units in all
Address
S No-41 H No-5A, S No-42 H No-1A S No-44 H No-C, Kharvai, BadlapurPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
6,980 sq m (75,132 sq ft)
Permissible built-up area
18,390 sq m (1,97,950 sq ft)
Sanctioned built-up area
18,390 sq m (1,97,950 sq ft)
Recreational open space
737 sq m (7,928 sq ft)
Designated bank account
21
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S No41 H No5AS No42 H No1A S No44 H NoC

Land as published on MahaRERA's project page

S No-41 H No-5A, S No-42 H No-1A S No-44 H No-C

Boundaries

North
S No-41-4 Land
South
S No-42-2 Land
East
Railway Open Land
West
S No-42-1B Land

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking324 units

324 units registered

— · 324 units
BuildingTypeCarpet areaUnits
Wing A——107
Wing B——115
Wing C——102

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates (Ar. S R Khambayat)—
ArchitectS R Khambayat Partner of RAJ ASSOCIATES—
Chartered accountantCA Ganapath Jain—
Chartered accountantCA Rajendra Chaplot—
EngineerER. Kamlesh R Patel—
EngineerSmit Velani Partner of Aadhar Engineering—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology