Promised date passed9 floors · 118 flatsRERA P51700008568

Wing A, The Chalets Avenue

Deedo IDDP-THN-W02R-A-2

108 flats have a sale on record, 8 are booked without a sale deed yet and 2 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.

Median saleNot on recordneeds 3 or more sales
Booked98%116 of 118 · Oct 2026
Completion30 Nov 2018as registered

Every flat, floor by floor

Tap a flat to see its record.

  • Sale registered
  • Booked, no deed yet
  • Unsold
010203040506070809101112
Fl 9
Fl 8
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
Fl G
1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK1 BHK

Other units on these floors (no stack in the number):

Fl G

Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.

SelectedSold

Flat 912

1 BHK · 259 sq ft · floor 9

Deeds
0
Last activity
None on record
Last sale
None registered
Units & parking in Wing A

MahaRERA's project page with unit types hasn't been imported for this registration.

Parking: Closed/Covered 0 · Open Space 0 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation100%
  • Basement (if any)n/a
  • Podiums (if any)n/a
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises87%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
As registered with MahaRERA
RERA registration
P51700008568 · registered 19 Aug 2017
Promised completion
30 Nov 2018
Sanctioned habitable floors
9
Deedo ID
DP-THN-W02R-A-2
Questions about Wing A

How many flats in Wing A are sold?

108 flats have a sale on record, 8 are booked without a sale deed yet and 2 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.

When is Wing A due for completion?

The MahaRERA registration promises 30 Nov 2018.

How many floors does Wing A have?

9 sanctioned habitable floors, as registered with MahaRERA.

Data through11 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology