Residential / Group Housing · 6 buildings · 237 unitsRERA P51700000644

Thanekar Parkland

Deedo IDDP-THN-VFBA

MahaRERA shows it completed; no MahaRERA orders on record; 38% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Ajay Madhukar Thanekar

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales38% booked89 of 237 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 19 Jul 2017, completion promised 31 Dec 2019.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700000644
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000064419 Jul 201731 Dec 201931 Dec 2019Ajay Madhukar ThanekarProject page
Documents65

2 documents held by Deedo, 63 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN - Ajay Thanekar.pdf · uploaded 26 Jun 2017Source

Legal

  • Legal Title reportTitled Report- Thanekar Parkland.PDF · uploaded 26 Jun 2017Source
  • Declaration Form BDeclaration Form B.pdf · uploaded 12 Jul 2017Source

Migrated

  • 1 PAN CardPAN - Ajay Thanekar.pdf · uploaded 26 Jun 2017Source
  • 1 Copy of the legal title reportTitled Report- Thanekar Parkland.PDF · uploaded 26 Jun 2017Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20170628_0001.PDF · uploaded 29 Jun 2017Source
Show all 65 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)MYSCAN_20170628_0002.PDF · uploaded 29 Jun 2017Source
  • 2 Building Plan Approval (IOD)MYSCAN_20170628_0003.PDF · uploaded 29 Jun 2017Source
  • 3 Building Plan Approval (IOD)MYSCAN_20170628_0004.PDF · uploaded 29 Jun 2017Source
  • 4 Building Plan Approval (IOD)MYSCAN_20170628_0005.PDF · uploaded 29 Jun 2017Source
  • 5 Building Plan Approval (IOD)MYSCAN_20170628_0006.PDF · uploaded 29 Jun 2017Source
  • 6 Building Plan Approval (IOD)MYSCAN_20170628_0007.PDF · uploaded 29 Jun 2017Source
  • 7 Building Plan Approval (IOD)MYSCAN_20170628_0008.PDF · uploaded 29 Jun 2017Source
  • 8 Building Plan Approval (IOD)MYSCAN_20170628_0009.PDF · uploaded 29 Jun 2017Source
  • 9 Building Plan Approval (IOD)MYSCAN_20170628_0010.PDF · uploaded 29 Jun 2017Source
  • 10 Building Plan Approval (IOD)MYSCAN_20170628_0011.PDF · uploaded 29 Jun 2017Source
  • 1 Details of encumbrancesNon Litigation Certificate.pdf · uploaded 11 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Cert - T Parkland.pdf · uploaded 12 Jul 2017Source
  • 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certificate of Architect.pdf · uploaded 13 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer.pdf · uploaded 13 Jul 2017Source
  • 1 Certificates of CA (Form 3)Certificate of CA.pdf · uploaded 13 Jul 2017Source
  • 1 Proforma of Allotment letterAllotment Letter and Sales Agreement.pdf · uploaded 13 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Parkland Nov 2017.pdf · uploaded 29 Dec 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate PArkland November 2017.pdf · uploaded 29 Dec 2017Source
  • 2 Certificates of CA (Form 3)CA Certificate Parkland new .pdf · uploaded 29 Dec 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Parkland Jan 2018.pdf · uploaded 6 Mar 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Parkland jan 2018.pdf · uploaded 6 Mar 2018Source
  • 3 Certificates of CA (Form 3)CA_Certificate_Parkland_Jan_2018_New.pdf · uploaded 6 Mar 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH CERTIFICATE PARKLAND.pdf · uploaded 2 Jun 2018Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate - Parkland.pdf · uploaded 2 Jun 2018Source
  • 4 Certificates of CA (Form 3)CA CERTIFICATE PARKLAND April 2018.pdf · uploaded 2 Jun 2018Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS INC.pdf · uploaded 12 Dec 2018Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 12 Dec 2018Source
  • 5 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 12 Dec 2018Source
  • 6 Certificates of CA (Form 3)THANEKAR PARKLAND CA CERTIFICATE DEC2018.pdf · uploaded 19 Feb 2019Source
  • 1 Certificates of CA (Form 5)PARKLAND FORM 5 MARCH 18.pdf · uploaded 19 Feb 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentC-Block Completion Certificate.PDF · uploaded 18 Jun 2019Source
  • 3 Commencement Certificates / NA Order for plotted developmentA AND B WING Completion Certificate.PDF · uploaded 18 Jun 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentA AND B WING Completion Certificate.PDF · uploaded 9 Aug 2019Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentC-Block Completion Certificate.PDF · uploaded 9 Aug 2019Source
  • 7 Certificates of CA (Form 3)FORM 3 THANEKAR PARKLAND MARCH 2019.pdf · uploaded 17 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)PARKLAND FORM 5 MARCH 19.pdf · uploaded 24 Jan 2020Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)UDIN Form 5 PARKLAND FORM 5 MARCH 18.pdf · uploaded 24 Jan 2020Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form 4 Thanekar Infrastructure - Parkland.pdf · uploaded 24 May 2021Source
  • 8 Certificates of CA (Form 3)FORM 3 13062019.pdf · uploaded 1 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5-Annual Audit-Thanekar Parkland.pdf · uploaded 7 Jun 2021Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Paradise.PDF · uploaded 11 Jun 2021View
  • 9 Certificates of CA (Form 3)FORM 3 30042020.pdf · uploaded 11 Jun 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Soceity Registration Certificat.PDF · uploaded 19 Feb 2022Source

Technical

  • DocumentMYSCAN_20170628_0001.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0002.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0003.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0004.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0005.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0006.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0007.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0008.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0009.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0010.PDF · uploaded 29 Jun 2017Source
  • DocumentMYSCAN_20170628_0011.PDF · uploaded 29 Jun 2017Source

Technical (Architect)

  • DocumentARCHITECTS INC.pdf · uploaded 12 Dec 2018Source

Technical (Engineer)

  • DocumentENGINEER CERTIFICATE.pdf · uploaded 12 Dec 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 58/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK237 units in all
Address
58/2PIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
6,100 sq m (65,660 sq ft)
Permissible built-up area
10,125 sq m (1,08,986 sq ft)
Sanctioned built-up area
10,125 sq m (1,08,986 sq ft)
Recreational open space
610 sq m (6,566 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

58/2

Land as published on MahaRERA's project page

58/2

Boundaries

North
12 Mtr Wide Road
South
KBMC Stadium Reservation
East
KBMC Stadium Reservatopm
West
S No58 H No 2 G Zone

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking237 units

89 of 237 units booked (38%), as the promoter reported to MahaRERA

1BHK · 141 units2BHK · 96 units
BuildingTypeCarpet areaUnitsBooked
A Block1BHK25.86 sq m · 278 sq ft10
A Block1BHK26.03 sq m · 280 sq ft11
A Block1BHK26.31 sq m · 283 sq ft77
A Block1BHK26.5 sq m · 285 sq ft75
A Block1BHK28.09 sq m · 302 sq ft11
A Block1BHK28.54 sq m · 307 sq ft74
A Block1BHK29.28 sq m · 315 sq ft11
A Block1BHK30.12 sq m · 324 sq ft104
Show all 53 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Block1BHK30.23 sq m · 325 sq ft10
A Block1BHK30.64 sq m · 330 sq ft70
A Block1BHK30.81 sq m · 332 sq ft11
A Block1BHK31.12 sq m · 335 sq ft43
A Block1BHK31.35 sq m · 337 sq ft76
A Block1BHK31.81 sq m · 342 sq ft11
A Block1BHK32.64 sq m · 351 sq ft71
B Block1BHK29.51 sq m · 318 sq ft10
B Block1BHK30.08 sq m · 324 sq ft11
B Block1BHK30.41 sq m · 327 sq ft70
B Block1BHK30.44 sq m · 328 sq ft10
B Block1BHK30.65 sq m · 330 sq ft70
B Block1BHK31.12 sq m · 335 sq ft74
B Block1BHK31.32 sq m · 337 sq ft70
B Block1BHK32.53 sq m · 350 sq ft10
B Block1BHK33.47 sq m · 360 sq ft72
B Block2BHK35.1 sq m · 378 sq ft11
B Block2BHK35.13 sq m · 378 sq ft10
B Block2BHK35.96 sq m · 387 sq ft75
B Block2BHK36.1 sq m · 389 sq ft74
B Block2BHK37.92 sq m · 408 sq ft10
B Block2BHK38.31 sq m · 412 sq ft10
B Block2BHK38.81 sq m · 418 sq ft76
B Block2BHK38.82 sq m · 418 sq ft74
B Block2BHK39.22 sq m · 422 sq ft20
B Block2BHK39.86 sq m · 429 sq ft1413
C Block1BHK29.51 sq m · 318 sq ft10
C Block1BHK30.08 sq m · 324 sq ft10
C Block1BHK30.41 sq m · 327 sq ft70
C Block1BHK30.44 sq m · 328 sq ft10
C Block1BHK30.65 sq m · 330 sq ft73
C Block1BHK31.12 sq m · 335 sq ft73
C Block1BHK31.32 sq m · 337 sq ft70
C Block1BHK32.53 sq m · 350 sq ft10
C Block1BHK33.47 sq m · 360 sq ft70
C Block2BHK35.1 sq m · 378 sq ft11
C Block2BHK35.13 sq m · 378 sq ft10
C Block2BHK35.96 sq m · 387 sq ft74
C Block2BHK36.1 sq m · 389 sq ft70
C Block2BHK37.92 sq m · 408 sq ft10
C Block2BHK38.31 sq m · 412 sq ft10
C Block2BHK38.81 sq m · 418 sq ft71
C Block2BHK38.82 sq m · 418 sq ft70
C Block2BHK39.22 sq m · 422 sq ft20
C Block2BHK39.86 sq m · 429 sq ft142

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Satish D Oak of ARCHITECTS Inc—
EngineerMr Atul V Kudtarkar of ATUL KUDTARKAR & ASSOCIATES—
OtherMr Niteshbhai T Patel of NITESH ENTERPRISES—
OtherMr Shantaram G Mali of SONALI CONSTRUCTION—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology