Ajay Madhukar Thanekar
Deedo IDDD-QFDVOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Thanekar ParklandP51700000644 | Badlapur (M Cl) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Thanekar ParadiseP51700001024 | Badlapur (M Cl) | Certificate Signed | 30 Jun 2021 | 30 Dec 2021 | +6 mo |
Ajay Madhukar Thanekar, in questions
Does Ajay Madhukar Thanekar finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ajay Madhukar Thanekar registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Ajay Madhukar Thanekar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.