Skip to content
Others · 1 building · 146 unitsRERA P51700001024

Thanekar Paradise

Deedo IDDP-THN-TYFR

MahaRERA shows it completed, after its date was pushed back 6 months; no MahaRERA orders on record; 18% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Ajay Madhukar Thanekar

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales18% booked26 of 146 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 6 months

  • This projectRegistered 25 Jul 2017, completion promised 30 Jun 2021, revised to 30 Dec 2021.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700001024
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000102425 Jul 201730 Jun 202130 Dec 2021Ajay Madhukar ThanekarProject page
Documents64

3 documents held by Deedo, 61 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN - Ajay Thanekar.pdf · uploaded 20 Jul 2017Source

Legal

  • Declaration Form BDeclaration Form - B - Paradise.pdf · uploaded 20 Jul 2017Source
  • Legal Title reportTitile report-paradise.PDF · uploaded 20 Jul 2017Source

Migrated

  • 1 PAN CardPAN - Ajay Thanekar.pdf · uploaded 20 Jul 2017Source
  • 1 Copy of the legal title reportTitile report-paradise.PDF · uploaded 20 Jul 2017Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesCertificate of non litigation.pdf · uploaded 20 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommt Certf - Thanekar Paradise.pdf · uploaded 20 Jul 2017Source
  • 1 Declaration in FORM BDeclaration Form - B - Paradise.pdf · uploaded 20 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certif of Architect - Paradise.PDF · uploaded 20 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer-Paradise.PDF · uploaded 20 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approval - Paradise.PDF · uploaded 21 Jul 2017Source
  • 1 Building Plan Approval (IOD)MYSCAN_20170721_0006.PDF · uploaded 21 Jul 2017Source
  • 2 Building Plan Approval (IOD)MYSCAN_20170721_0007.PDF · uploaded 21 Jul 2017Source
  • 3 Building Plan Approval (IOD)MYSCAN_20170721_0008.PDF · uploaded 21 Jul 2017Source
  • 4 Building Plan Approval (IOD)MYSCAN_20170721_0009.PDF · uploaded 21 Jul 2017Source
  • 5 Building Plan Approval (IOD)MYSCAN_20170721_0010.PDF · uploaded 21 Jul 2017Source
  • 1 Certificates of CA (Form 3)Certiificate of CA - Paradise.pdf · uploaded 21 Jul 2017Source
  • 1 Proforma of Allotment letterBLANK FLAT SALE AGREEMENT.pdf · uploaded 21 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Paradise Nov 2017.pdf · uploaded 28 Dec 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Paradise November 2017.pdf · uploaded 28 Dec 2017Source
  • 2 Certificates of CA (Form 3)CA Certificate Paradise November 2017.pdf · uploaded 28 Dec 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Paradise Jan 2018.pdf · uploaded 6 Mar 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Paradise - Jan 2018.pdf · uploaded 6 Mar 2018Source
  • 3 Certificates of CA (Form 3)CA_CERTIFICATE_-_PARADISE_JAN_2018_New.pdf · uploaded 6 Mar 2018Source
  • 6 Building Plan Approval (IOD)MYSCAN_20180208_01 NEW.pdf · uploaded 14 Mar 2018Source
  • 7 Building Plan Approval (IOD)MYSCAN_20180208_02 NEW.pdf · uploaded 14 Mar 2018Source
  • 8 Building Plan Approval (IOD)MYSCAN_20180208_03 NEW.pdf · uploaded 14 Mar 2018Source
  • 9 Building Plan Approval (IOD)MYSCAN_20180208_04 NEW.pdf · uploaded 14 Mar 2018Source
  • 10 Building Plan Approval (IOD)MYSCAN_20180208_05 NEW.pdf · uploaded 14 Mar 2018Source
  • 11 Building Plan Approval (IOD)MYSCAN_20180208_06 NEW.pdf · uploaded 14 Mar 2018Source
  • 4 Certificates of CA (Form 3)CA CERTIFICATE -PARADISE SEP 2018.pdf · uploaded 23 Feb 2019Source
  • 5 Certificates of CA (Form 3)CA CERTIFICATE -PARADISE DEC 2018.pdf · uploaded 23 Feb 2019Source
  • 1 Certificates of CA (Form 5)FORM 5 THANEKAR PARADISE -MARCH 2018.pdf · uploaded 23 Feb 2019Source
  • 2 Certificates of CA (Form 5)CA CERTIFICATE -PARADISE DEC 2018.pdf · uploaded 23 Feb 2019Source
  • 6 Certificates of CA (Form 3)Paradise CA Certificate June2019.pdf · uploaded 6 Aug 2019Source
  • 7 Certificates of CA (Form 3)CA Certificate _June 2019_Compressed.pdf · uploaded 22 Aug 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5.pdf · uploaded 23 Dec 2019Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Ajay Realtors - Paradise.pdf · uploaded 24 May 2021Source
  • 8 Certificates of CA (Form 3)FORM 3 30092019.pdf · uploaded 25 May 2021Source
  • 9 Certificates of CA (Form 3)FORM 3 31122019.pdf · uploaded 25 May 2021Source
  • 10 Certificates of CA (Form 3)FORM 3 31032020.pdf · uploaded 25 May 2021Source
  • 11 Certificates of CA (Form 3)FORM 3 30042020.pdf · uploaded 25 May 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5-Annual Audit-Thanekar Paradise 2020.pdf · uploaded 7 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5-Annual Audit-Thanekar Paradise 30-4-2020.pdf · uploaded 7 Jun 2021Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Paradise.PDF · uploaded 11 Jun 2021View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Certificate QA.pdf · uploaded 16 Jun 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.PDF · uploaded 19 Feb 2022Source

Technical

  • DocumentMYSCAN_20170721_0006.PDF · uploaded 21 Jul 2017Source
  • DocumentMYSCAN_20170721_0007.PDF · uploaded 21 Jul 2017Source
  • DocumentMYSCAN_20170721_0008.PDF · uploaded 21 Jul 2017Source
  • DocumentMYSCAN_20170721_0009.PDF · uploaded 21 Jul 2017Source
  • DocumentMYSCAN_20170721_0010.PDF · uploaded 21 Jul 2017Source
  • DocumentLayout Approval - Paradise.PDF · uploaded 21 Jul 2017Source
  • DocumentMYSCAN_20180208_01 NEW.pdf · uploaded 14 Mar 2018Source
  • DocumentMYSCAN_20180208_02 NEW.pdf · uploaded 14 Mar 2018Source
  • DocumentMYSCAN_20180208_03 NEW.pdf · uploaded 14 Mar 2018Source
  • DocumentMYSCAN_20180208_04 NEW.pdf · uploaded 14 Mar 2018Source
  • DocumentMYSCAN_20180208_05 NEW.pdf · uploaded 14 Mar 2018Source
  • DocumentMYSCAN_20180208_06 NEW.pdf · uploaded 14 Mar 2018Source

Technical (Architect)

  • DocumentArchitect Certificate Paradise Jan 2018.pdf · uploaded 6 Mar 2018Source

Technical (Engineer)

  • DocumentEngineer Certificate Paradise - Jan 2018.pdf · uploaded 6 Mar 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 81/1A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Shop146 units in all
Address
81/1aPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
4,400 sq m (47,361 sq ft)
Permissible built-up area
6,252 sq m (67,298 sq ft)
Sanctioned built-up area
6,252 sq m (67,298 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

81/1A

Land as published on MahaRERA's project page

81/1A

Boundaries

North
Dilip Surval Property S No 81 H No 1 Part
South
12 Mtr D P Road
East
Kalp Nisarg Project S No 81 H No 2
West
15 Mtr D P Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking146 units

26 of 146 units booked (18%), as the promoter reported to MahaRERA

1BHK · 69 units2BHK · 50 units3BHK · 4 unitsShop · 23 units
TypeCarpet areaUnitsBooked
1BHK28.87 sq m · 311 sq ft124
1BHK29.53 sq m · 318 sq ft121
1BHK32.75 sq m · 353 sq ft120
1BHK35.25 sq m · 379 sq ft121
1BHK37.69 sq m · 406 sq ft10
1BHK37.88 sq m · 408 sq ft91
1BHK38.55 sq m · 415 sq ft112
2BHK36.94 sq m · 398 sq ft102
Show all 35 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK38.36 sq m · 413 sq ft10
2BHK38.38 sq m · 413 sq ft113
2BHK39.09 sq m · 421 sq ft92
2BHK42.48 sq m · 457 sq ft102
2BHK42.64 sq m · 459 sq ft92
3BHK61.06 sq m · 657 sq ft11
3BHK65.24 sq m · 702 sq ft10
3BHK72.26 sq m · 778 sq ft10
3BHK73.14 sq m · 787 sq ft10
Shop6.2 sq m · 67 sq ft20
Shop11.21 sq m · 121 sq ft11
Shop12.02 sq m · 129 sq ft10
Shop12.2 sq m · 131 sq ft10
Shop13.75 sq m · 148 sq ft10
Shop13.76 sq m · 148 sq ft31
Shop14.15 sq m · 152 sq ft10
Shop15.26 sq m · 164 sq ft10
Shop15.44 sq m · 166 sq ft21
Shop15.68 sq m · 169 sq ft10
Shop16.28 sq m · 175 sq ft20
Shop17.73 sq m · 191 sq ft10
Shop18.26 sq m · 197 sq ft10
Shop20.26 sq m · 218 sq ft11
Shop21.38 sq m · 230 sq ft10
Shop22.3 sq m · 240 sq ft10
Shop26.77 sq m · 288 sq ft11
Shop27.45 sq m · 295 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Satish Oak of ARCHITECTS INC—
EngineerMr Atul Kudtarkar of ATUL KUDTARKAR AND ASSOCIATES—
OtherMr Mehul P Parsia of ANVEESHA ENTERPRISES—

Source: MahaRERA project page. Contact details are not shown.