Skip to content
Residential / Group Housing · 7 buildings · 293 unitsRERA P51700029932

Thanekar Civic

Deedo IDDP-THN-RYG7

MahaRERA shows it completed; no MahaRERA orders on record; 22% of its units are booked.

Badlapur (M Cl), Thane 421503 · by Shree Swami Samarth Enterprises

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales22% booked64 of 293 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 15 Jul 2021, completion promised 9 Apr 2024.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700029932
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002993215 Jul 20219 Apr 20249 Apr 2024Shree Swami Samarth EnterprisesProject page
Documents77

2 documents held by Deedo, 75 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardShree Swami Samarth PAN Card.pdf · uploaded 5 Jul 2021Source

Legal

  • Legal Title reportTitle Certifiacate- CIVIC.PDF · uploaded 5 Jul 2021Source
  • Legal Title reportSearch Report- Thanekar Civic.pdf · uploaded 5 Jul 2021Source
  • Declaration Form BFORM B with Notary_compressed.pdf · uploaded 7 Jul 2021Source

Migrated

  • 1 PAN CardShree Swami Samarth PAN Card.pdf · uploaded 5 Jul 2021Source
  • 1 Copy of the legal title reportTitle Certifiacate- CIVIC.PDF · uploaded 5 Jul 2021Source
Show all 77 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportSearch Report- Thanekar Civic.pdf · uploaded 5 Jul 2021Source
  • 1 Details of encumbrancesNo Encumbrances_ Shree Swami Samarth-New.pdf · uploaded 5 Jul 2021Source
  • 1 Copy of Layout Approval (in case of layout)HPSCANNER1451-converted.pdf · uploaded 5 Jul 2021Source
  • 2 Copy of Layout Approval (in case of layout)HPSCANNER1452-converted.pdf · uploaded 5 Jul 2021Source
  • 3 Copy of Layout Approval (in case of layout)HPSCANNER1453-converted.pdf · uploaded 5 Jul 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentCommencement Certificate - Shree Swami Samarth Enterprises- CIVIC.PDF · uploaded 5 Jul 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate - Shree Swami Samarth Enterprises- CIVIC.PDF · uploaded 5 Jul 2021Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 5 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Architect Certificate - CIVIC.PDF · uploaded 5 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineers Certificate- CIVIC.PDF · uploaded 5 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM-2A-QA_compressed.pdf · uploaded 5 Jul 2021Source
  • 1 Proforma of Allotment letterFLAT SALE AGREEMENT.pdf · uploaded 5 Jul 2021Source
  • 2 Proforma of Allotment letterRERA Allotment Letter.pdf · uploaded 5 Jul 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Signed_compressed.pdf · uploaded 6 Jul 2021Source
  • 1 Declaration in FORM BFORM B with Notary_compressed.pdf · uploaded 7 Jul 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 19 Jan 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2-c.pdf · uploaded 20 Jan 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.PDF · uploaded 17 Feb 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certifiacte.PDF · uploaded 17 Feb 2022Source
  • 1 Disclosure of sold/ booked inventoryMERGED SOLD AND UNSOLD.pdf · uploaded 17 Feb 2022Source
  • 2 Disclosure of sold/ booked inventoryCOMPRESSED SOLD AND BOOKED.pdf · uploaded 1 Mar 2022View
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1 (Civic).PDF · uploaded 29 Apr 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate From 2 (Civic).PDF · uploaded 29 Apr 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-new signed.pdf · uploaded 30 May 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Form-1.PDF · uploaded 19 Aug 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form-2.PDF · uploaded 19 Aug 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 19 Aug 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 4 Nov 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5.pdf · uploaded 4 Nov 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 12 Nov 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 12 Nov 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 NEW.pdf · uploaded 18 Nov 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 NEW.pdf · uploaded 1 Dec 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Scanned Compressed.pdf · uploaded 1 Dec 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Jan 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2.PDF · uploaded 21 Jan 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Revised.pdf · uploaded 25 Jan 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-signed.pdf · uploaded 25 Jan 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (Form-1)-SSSE.PDF · uploaded 2 Jun 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.PDF · uploaded 2 Jun 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3- Signed_compressed.pdf · uploaded 2 Jun 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (SSSE).PDF · uploaded 15 Jul 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate (Form-2).PDF · uploaded 12 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-signed.pdf · uploaded 12 Aug 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 (SSSE).PDF · uploaded 18 Aug 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1 SSE_compressed.pdf · uploaded 30 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form- 5.PDF · uploaded 3 Nov 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1 SSE_compressed.pdf · uploaded 18 Nov 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 (SSSE).PDF · uploaded 18 Nov 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 18 Nov 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1.pdf · uploaded 19 Feb 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1_compressed.pdf · uploaded 19 Feb 2024Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)From - 2_compressed.pdf · uploaded 19 Feb 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_11zon.pdf · uploaded 19 Feb 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)From - 1_compressed.pdf · uploaded 6 May 2024Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2.pdf · uploaded 6 May 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3 - converted.pdf · uploaded 6 May 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate (T-Civic).PDF · uploaded 6 May 2024Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentHPSCANNER1211_compressed (1).pdf · uploaded 6 May 2024Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentHPSCANNER1213_compressed.pdf · uploaded 6 May 2024Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentHPSCANNER1214 (1)_compressed.pdf · uploaded 6 May 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 6 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 Shree Swami Smarth Ent.pdf · uploaded 23 Oct 2024Source

Technical

  • DocumentHPSCANNER1451-converted.pdf · uploaded 5 Jul 2021Source
  • DocumentHPSCANNER1452-converted.pdf · uploaded 5 Jul 2021Source
  • DocumentHPSCANNER1453-converted.pdf · uploaded 5 Jul 2021Source
  • DocumentCommencement Certificate - Shree Swami Samarth Enterprises- CIVIC.PDF · uploaded 5 Jul 2021Source

Technical (Architect)

  • DocumentFrom - 1_compressed.pdf · uploaded 6 May 2024Source

Technical (Engineer)

  • DocumentForm - 2.pdf · uploaded 6 May 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel H NO 2, S NO 133

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK293 units in all
Address
S NO 133, H NO 2, Vadavali Gaon, Chikhloli, BadlapurPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
5,640 sq m (60,708 sq ft)
Permissible built-up area
19,260 sq m (2,07,313 sq ft)
Sanctioned built-up area
17,885 sq m (1,92,512 sq ft)
Recreational open space
564 sq m (6,071 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

H NO 2S NO 133

Land as published on MahaRERA's project page

S NO 133, H NO 2

Boundaries

North
Part of Land Bearing S No 133
South
9 MTR W-12 MT-W Road
East
Part of Land Bearing S No 133
West
Part of Land Bearing H NO133-1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking293 units

64 of 293 units booked (22%), as the promoter reported to MahaRERA

1BHK · 126 units1RK · 37 units2BHK · 130 units
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK29.37 sq m · 316 sq ft5217
A Wing1RK23.17 sq m · 249 sq ft241
A Wing2BHK45.06 sq m · 485 sq ft130
A Wing2BHK47.83 sq m · 515 sq ft131
A Wing2BHK48.34 sq m · 520 sq ft134
B Wing1BHK29.37 sq m · 316 sq ft132
B Wing1BHK29.91 sq m · 322 sq ft118
B Wing1BHK34.22 sq m · 368 sq ft264
Show all 14 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Wing1RK23.17 sq m · 249 sq ft130
B Wing2BHK45.09 sq m · 485 sq ft266
B Wing2BHK46.09 sq m · 496 sq ft132
C wing1BHK29.37 sq m · 316 sq ft244
C wing2BHK45.09 sq m · 485 sq ft264
C wing2BHK46.7 sq m · 503 sq ft2611

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—
Chartered accountantAnkit Paras Jain & Co—
EngineerAtul Kudtarkar & Associates—
EngineerRavindra Vaze—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Badlapur (M Cl)

All 432 projects in Badlapur (M Cl) · Compare Thanekar Civic with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology