Skip to content
Others · 1 building · 40 unitsRERA P51700078920

Parivar Sadan Chs Ltd

Deedo IDDP-THN-52V9

Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 0% of its units are booked.

Badlapur, Thane 421503 · by Kaivalya And Associates

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 40 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • This projectRegistered 20 Jan 2025, completion promised 31 Mar 2027, revised to 31 Jul 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700078920
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007892020 Jan 202531 Mar 202731 Jul 2027Kaivalya And AssociatesProject page
Documents66

1 document held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan Card.pdf · uploaded 9 Nov 2024Source

Legal

  • Declaration Form Bpradeep pawar affidavit.pdf · uploaded 9 Nov 2024Source
  • Declaration Form Bsachin gorle Affidavit.pdf · uploaded 9 Nov 2024Source
  • Legal Title reportlegal title report.pdf · uploaded 9 Nov 2024Source
  • Other – LegalRedevelopment agreement.pdf · uploaded 28 Dec 2024Source
  • Other – LegalLETTER OF UNDERTAKING.pdf · uploaded 28 Dec 2024Source

Migrated

  • 1 PAN CardFirm Pan Card.pdf · uploaded 9 Nov 2024Source
Show all 66 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportlegal title report.pdf · uploaded 9 Nov 2024Source
  • 2 a Details of encumbrances concerned to FinanceLegal encumbrance.pdf · uploaded 9 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan-1-compressed.pdf · uploaded 9 Nov 2024Source
  • 2 Copy of Layout Approval (in case of layout)plan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • 3 Copy of Layout Approval (in case of layout)plan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • 1 Declaration in FORM Bsachin gorle Affidavit.pdf · uploaded 9 Nov 2024Source
  • 2 Declaration in FORM Bpradeep pawar affidavit.pdf · uploaded 9 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 9 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate.pdf · uploaded 9 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 9 Nov 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentplan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan-1-compressed.pdf · uploaded 9 Nov 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentplan-2-compressed.pdf · uploaded 9 Nov 2024Source
  • 1 Declaration about Commencement Certificatedeclaration of cc.pdf · uploaded 9 Nov 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200313606884_For_Asset_Based_Search_14_07_2024_11_45_27_466.pdf · uploaded 9 Nov 2024Source
  • 2 CERSAI detailsundertaking.pdf · uploaded 9 Nov 2024Source
  • 1 Deviation Report with respect to Allotment lettersale and allotment letter.pdf · uploaded 9 Nov 2024Source
  • 2 b Details of encumbrances concerned to LegalLegal encumbrance.pdf · uploaded 9 Nov 2024Source
  • 1 Deviation Report with respect to model copy of Agreementsale and allotment letter.pdf · uploaded 9 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectSecured and Unsecured Loan.pdf · uploaded 9 Nov 2024Source
  • 1 Proforma of Allotment letterALLOTMENT.pdf · uploaded 27 Dec 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)BANK FORMAT A.pdf · uploaded 27 Dec 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SALE (4).pdf · uploaded 27 Dec 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizationssachin gorle.pdf · uploaded 27 Dec 2024Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsharshal ghoropade.pdf · uploaded 27 Dec 2024Source
  • 3 Disclosure of Interest in Other Real Estate Organizationsbharat thakare.pdf · uploaded 27 Dec 2024Source
  • 1 Other – LegalLETTER OF UNDERTAKING.pdf · uploaded 28 Dec 2024Source
  • 2 Other – LegalRedevelopment agreement.pdf · uploaded 28 Dec 2024Source
  • 1 a Details of encumbrances concerned to FinanceKaivalya and Associates Finance New.pdf · uploaded 6 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New (1).pdf · uploaded 6 Jan 2025Source
  • 1 b Details of encumbrances concerned to LegalKaivalya and Associates Finance New.pdf · uploaded 6 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)BANK LETTER FORM B.pdf · uploaded 6 Jan 2025Source
  • Form 1Form 1 Mar25 Kaivalya Ass.pdf · uploaded 16 May 2026Source
  • Form 2Form 2 Mar25 Kaivalya Ass.pdf · uploaded 16 May 2026Source
  • Form 3Form 3 Mar25 Kaivalya Ass.pdf · uploaded 16 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Mar25 Kaivalya Ass.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 1Form 1 June25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 1Form 1 Sept25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 1Form 1 Dec25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 2Form 2 June25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 2Form 2 Sept25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 2Form 2 Dec25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 3Form 3 June25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 3Form 3 Sept25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 3Form 3 Dec25 Kaivalya Ass.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 1Form 1 Mar26 Kaivalya Ass.pdf · uploaded 19 May 2026Source
  • Withdrawal Update Form 2Form 2 Mar26 Kaivalya Ass.pdf · uploaded 19 May 2026Source
  • Withdrawal Update Form 3Form 3 Mar26 Kaivalya Ass.pdf · uploaded 19 May 2026Source
  • Form 2A (FY 2024-2025)Form 2A FY2024-25 Kaivalya Ass.pdf · uploaded 21 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A FY2025-26 Kaivalya Ass.pdf · uploaded 22 May 2026Source

Technical

  • Documentplan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • Documentplan-2-compressed.pdf · uploaded 9 Nov 2024Source
  • DocumentPlan-1-compressed.pdf · uploaded 9 Nov 2024Source
  • Documentplan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • Documentplan -3-compressed.pdf · uploaded 9 Nov 2024Source
  • DocumentPlan-1-compressed.pdf · uploaded 9 Nov 2024Source

Technical (Architect)

  • DocumentForm 1 Mar26 Kaivalya Ass.pdf · uploaded 18 May 2026Source

Technical (Engineer)

  • DocumentForm 2 Mar26 Kaivalya Ass.pdf · uploaded 18 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2, H NO 2/8 PLOT NO 2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1BHKAlloted, 1BHKALLOTED, 2BHK, 2BHKAlloted, 2BHKALLOTED, Office space, SHOP NO 01 Alloted, SHOP NO 02 alloted, SHOP NO 03 alloted, SHOP NO. 04 alloted, SHOP NO 05 alloted, SHOP NO 06 alloted, SHOP NO 07 alloted40 units in all
Address
Plot No 1 & 2, S No 20 H No 2/7, Plot No 1 & S. No 20, H No 2/8 Plot No 2, Katrap, BadlapurPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
635 sq m (6,840 sq ft)
Permissible built-up area
1,798 sq m (19,359 sq ft)
Sanctioned built-up area
1,798 sq m (19,359 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
148
Developed in phases
No

Survey, CTS, gat or plot numbers

2H NO 2/8 PLOT NO 2PLOT NO 1S. NO 20S NO 20 H NO 2/7

Land as published on MahaRERA's project page

PLOT NO 1 & 2, S NO 20 H NO 2/7, PLOT NO 1 & S. NO 20, H NO 2/8 PLOT NO 2

Boundaries

North
6 Meter Road
South
Govind Nilay Chsl
East
Jay Heights Chsl
West
9 Meter Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

0 of 40 units booked (0%), as the promoter reported to MahaRERA

1BHK · 11 units1BHKAlloted · 1 unit1BHKALLOTED · 1 unit2BHK · 3 units2BHKAlloted · 10 units2BHKALLOTED · 3 unitsOffice space · 4 unitsSHOP NO 01 Alloted · 1 unitSHOP NO 02 alloted · 1 unitSHOP NO 03 alloted · 1 unitSHOP NO. 04 alloted · 1 unitSHOP NO 05 alloted · 1 unitSHOP NO 06 alloted · 1 unitSHOP NO 07 alloted · 1 unit
TypeCarpet areaUnitsBooked
1BHK33.06 sq m · 356 sq ft50
1BHK33.75 sq m · 363 sq ft10
1BHK35.72 sq m · 384 sq ft50
1BHKAlloted35.72 sq m · 384 sq ft10
1BHKALLOTED33.06 sq m · 356 sq ft10
2BHK40.45 sq m · 435 sq ft10
2BHK43.44 sq m · 468 sq ft20
2BHKAlloted40.45 sq m · 435 sq ft40
Show all 21 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHKAlloted43.16 sq m · 465 sq ft60
2BHKALLOTED43.44 sq m · 468 sq ft30
Office space30.78 sq m · 331 sq ft10
Office space39.4 sq m · 424 sq ft10
Office space60.72 sq m · 654 sq ft10
Office space77.69 sq m · 836 sq ft10
SHOP NO 01 Alloted8.93 sq m · 96 sq ft10
SHOP NO 02 alloted12.49 sq m · 134 sq ft10
SHOP NO 03 alloted21.86 sq m · 235 sq ft10
SHOP NO. 04 alloted18.98 sq m · 204 sq ft10
SHOP NO 05 alloted8.33 sq m · 90 sq ft10
SHOP NO 06 alloted8.14 sq m · 88 sq ft10
SHOP NO 07 alloted13.88 sq m · 149 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—
Chartered accountantca amrrita jagnaani—
EngineerAtul Kudatarkar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Badlapur

All 152 projects in Badlapur · Compare Parivar Sadan Chs Ltd with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology