Extended 18 mo9 floorsRERA P51700027239
Main building, Balaji Darshan
Deedo IDDP-THN-CVBR-BDMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked5%4 of 88 · MahaRERA
Completion30 Sep 202431 Mar 2023 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 28.7 m² (309 sq.ft) | 1 | 0 |
| 1BHK | 28.9 m² (311 sq.ft) | 1 | 0 |
| 1BHK | 29.1 m² (314 sq.ft) | 8 | 0 |
| 1BHK | 29.2 m² (315 sq.ft) | 9 | 0 |
| 1BHK | 29.3 m² (315 sq.ft) | 1 | 0 |
| 1BHK | 29.3 m² (316 sq.ft) | 1 | 0 |
| 1BHK | 29.4 m² (317 sq.ft) | 9 | 1 |
| 1BHK | 29.8 m² (320 sq.ft) | 1 | 0 |
| 1BHK | 30 m² (322 sq.ft) | 4 | 0 |
| 1BHK | 30 m² (323 sq.ft) | 5 | 0 |
| 1BHK | 30.6 m² (329 sq.ft) | 4 | 0 |
| 1BHK | 30.9 m² (333 sq.ft) | 5 | 0 |
| 2BHK | 44.5 m² (479 sq.ft) | 4 | 0 |
| 2BHK | 44.6 m² (480 sq.ft) | 4 | 0 |
| 2BHK | 45.5 m² (489 sq.ft) | 5 | 0 |
| 2BHK | 46.3 m² (498 sq.ft) | 5 | 0 |
| 2BHK | 50.7 m² (545 sq.ft) | 4 | 0 |
| 2BHK | 51.2 m² (551 sq.ft) | 5 | 1 |
| Office space | 29.8 m² (321 sq.ft) | 1 | 0 |
| Office space | 30.7 m² (330 sq.ft) | 1 | 0 |
| Office space | 34.4 m² (370 sq.ft) | 1 | 0 |
| Office space | 37.3 m² (401 sq.ft) | 1 | 0 |
| Shop | 11.2 m² (121 sq.ft) | 1 | 1 |
| Shop | 15.9 m² (171 sq.ft) | 1 | 1 |
| Shop | 18.4 m² (198 sq.ft) | 1 | 0 |
| Shop | 23.1 m² (249 sq.ft) | 1 | 0 |
| Shop | 24 m² (258 sq.ft) | 1 | 0 |
| Shop | 25.6 m² (276 sq.ft) | 1 | 0 |
| Shop | 26.9 m² (289 sq.ft) | 1 | 0 |
| Shop | 28 m² (301 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700027239 · registered 25 Nov 2020
- Promised completion
- 31 Mar 2023
- Revised completion
- 30 Sep 2024
- Sanctioned habitable floors
- 9
- Building
- BALAJI DARSHAN
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-CVBR-BD
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Mar 2023, revised to 30 Sep 2024.
How many floors does Main building have?
9 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology