Dattatray Residency
Deedo IDDP-THN-GMAYCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 3% of its units are booked.
Badlapur, Thane 421503 · by Shri Krishna Vastu
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 6 Mar 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Wing A13 floors · 128 units4% booked
- Wing B2 floors · 20 units0% booked
- Wing C2 floors · 20 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700049960
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700049960 | 6 Mar 2023 | 31 Dec 2027 | 30 Apr 2028 | Shri Krishna Vastu | Project page |
Documents143
1 document held by Deedo, 142 filings listed on MahaRERA's project page
Finance
- PAN CardPancard Firm.pdf · uploaded 29 Nov 2022Source
Legal
Show all 143 documentsShow fewer documents
Migrated
- 3 Copy of Layout Approval (in case of layout)KBMC Plan Pass 4_1.pdf · uploaded 29 Nov 2022Source
- 4 Copy of Layout Approval (in case of layout)KBMC Plan Pass 5_1.pdf · uploaded 29 Nov 2022Source
- 5 Copy of Layout Approval (in case of layout)KBMC Plan Pass 6_1.pdf · uploaded 29 Nov 2022Source
- 6 Copy of Layout Approval (in case of layout)KBMC Plan Pass 7_1.pdf · uploaded 29 Nov 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentKBMC Plan Pass 1_1.pdf · uploaded 29 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_1.pdf · uploaded 29 Nov 2022Source
- 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 29 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARchitect Certificate Shri Krishna Vastu.pdf · uploaded 29 Nov 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate_1.pdf · uploaded 29 Nov 2022Source
- 1 Declaration in FORM BForm B_Developer.pdf · uploaded 16 Jan 2023Source
- 1 Proforma of Allotment letterAllotment Letter Draft New.pdf · uploaded 16 Jan 2023Source
- 1 a Details of encumbrances concerned to FinanceDeclaration For Non Encumbrances.pdf · uploaded 23 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalDeclaration For Non Encumbrances.pdf · uploaded 23 Jan 2023Source
- 1 CERSAI detailsCersai Report.pdf · uploaded 23 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Sanjesh Patkar.pdf · uploaded 23 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A sanika patkar.pdf · uploaded 23 Jan 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (Anil Tiwari) Rera Shri krishna Vastu.pdf · uploaded 23 Jan 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (Sunil Tiwari) Rera Shri krishna Vastu.pdf · uploaded 23 Jan 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Harsh Shukla.pdf · uploaded 23 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDeclaration Deviation report allotment letter.pdf · uploaded 23 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeclaration Deviation report agreement.pdf · uploaded 23 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri Krishna Vastu_Signed-compressed.pdf · uploaded 25 Jan 2023Source
- 1 Copy of the legal title reportTitle Certificate New Format.pdf · uploaded 3 Feb 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Separate Bank Ac.pdf · uploaded 9 Feb 2023Source
- 1 Proforma of Agreement for saleAgreement for Sale Draft New.pdf · uploaded 27 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri krishna vastu_001.pdf · uploaded 18 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 S P Dev jun 23_001.pdf · uploaded 18 Nov 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri krishna vastu jun 23_001.pdf · uploaded 18 Nov 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri krishna vastu_002.pdf · uploaded 18 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri krishna vastu jun 23_001.pdf · uploaded 18 Nov 2023Source
- 1 Disclosure of sold/ booked inventorydisclosure of sold inventory Shri krishna vastu_001.pdf · uploaded 18 Nov 2023Source
- 2 Disclosure of sold/ booked inventoryDisclosure unsold shri krishna vastu jun 23_001.pdf · uploaded 18 Nov 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri krishna vastu_001.pdf · uploaded 18 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri Krishna Vastu Jun 23_001.pdf · uploaded 18 Nov 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri Krishna Vastu.pdf · uploaded 19 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu.pdf · uploaded 19 Jan 2024Source
- 3 Disclosure of sold/ booked inventoryDisclosure of Sold or Unsold Inventory Shri Krishna Vastu.pdf · uploaded 19 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Shri krishna vastu FY 22-23.pdf · uploaded 4 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri Krishna Vastu March 24.pdf · uploaded 30 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu March 24.pdf · uploaded 30 Apr 2024Source
- 4 Disclosure of sold/ booked inventoryshri Krishna Vastu Disclosure of Sold or Unsold Inventory.pdf · uploaded 30 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri Krishna Vastu March 24.pdf · uploaded 30 Apr 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri krishna vastu_003.pdf · uploaded 8 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu_004.pdf · uploaded 8 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri krishna Vastu Jun 24.pdf · uploaded 8 Oct 2024Source
- 1 Disclosure of sold/ booked inventorysold and unsold inventory shri krishna vastu.pdf · uploaded 8 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri krishna vastu_003.pdf · uploaded 8 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shri krishna Vastu Jun 24.pdf · uploaded 8 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu_004.pdf · uploaded 8 Oct 2024Source
- 2 Disclosure of sold/ booked inventorysold and unsold inventory shri krishna vastu.pdf · uploaded 8 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri Krishna Vastu Sep 24.pdf · uploaded 22 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Shri Krishna Vastu Sep 24.pdf · uploaded 22 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu Sep 24.pdf · uploaded 22 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold and booked inve Shri Krishna Vastu.pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shri Krishna Vastu Dec 24.pdf · uploaded 12 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shri Krishna Vastu Dec 24.pdf · uploaded 12 Mar 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold or Unsold Inventory SKV Dec 24.pdf · uploaded 12 Mar 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold or Unsold Inventory SKV Dec 24.pdf · uploaded 12 Mar 2025Source
- Withdrawal Update Form 1Form 1 SKV Jun 25.pdf · uploaded 29 Jul 2025Source
- Withdrawal Update Form 2Form 2 SKV Jun 25.pdf · uploaded 29 Jul 2025Source
- Withdrawal Update Form 3Form 3 Jun 25 SKV.pdf · uploaded 29 Jul 2025Source
- Form 1Form 1 june 2023.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 june 2023.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 june 2023.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold inventory june 2023.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 dec 2023.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 dec 2023.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 dec 2023.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Invenntory December 2023.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 march 2024.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 march 2024.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 march 2024.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory March 2024.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 june 2024.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 June 2024.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 june 2024.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory June 2024.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 Sept 2024.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 sept 2024.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 sept 2024.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory Sept 2024.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 dec 2024.pdf · uploaded 23 Sep 2025Source
- Form 2Form 2 Dec 2024.pdf · uploaded 23 Sep 2025Source
- Form 3Form 3 december 2024.pdf · uploaded 23 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory Dec 2024.pdf · uploaded 23 Sep 2025Source
- Form 1Form 1 Shri krishna vastu_001.pdf · uploaded 24 Sep 2025Source
- Form 2Form 2 Shri krishna vastu_002.pdf · uploaded 24 Sep 2025Source
- Form 3Form 3 Shri krishna vastu_001.pdf · uploaded 24 Sep 2025Source
- Disclosure of Sold and Booked Inventorydisclosure of sold inventory Shri krishna vastu_001.pdf · uploaded 24 Sep 2025Source
- Form 1Form 1 SKV Mar 25.pdf · uploaded 24 Sep 2025Source
- Form 2Form 2 SKV Mar 25.pdf · uploaded 24 Sep 2025Source
- Form 3Form 3 Shri Krishna Vastu March 2025.pdf · uploaded 24 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold unsold inventory shri krishna vastu mar 2025.pdf · uploaded 24 Sep 2025Source
- Form 1Form 1 june 2023.pdf · uploaded 8 Oct 2025Source
- Form 2Form 2 june 2023.pdf · uploaded 8 Oct 2025Source
- Form 3Form 3 june 2023.pdf · uploaded 8 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold inventory june 2023.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 1form 1 SKV Sep 25.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 2Form 2 SKV Sep 25.pdf · uploaded 25 Oct 2025Source
- Withdrawal Update Form 3FORM 3 SKV SEPT2025.pdf · uploaded 25 Oct 2025Source
- Form 5 (FY 2024-2025)Signed Form 5 Shri krishna vastu.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Form 1 SKV Dec 25.pdf · uploaded 29 Jan 2026Source
- Withdrawal Update Form 2Form 2 SKV Dec 25.pdf · uploaded 29 Jan 2026Source
- Withdrawal Update Form 3Form 3 of Shri Krishna Vastu December 2025_Signed.pdf · uploaded 29 Jan 2026Source
- Withdrawal Update Form 1Form 1 Mar 26 SKV.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 2Form 2 Mar 2026 SKV.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 3Signed Form 3 SKV Mar 2026_0001.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 1Signed Form 1 June 2026 Shri Krishna Vastu.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2Signed Form 2 June 2026 Shri Krishna Vastu.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3Signed Form 3 of Shri Krishna Vastu June 26.pdf · uploaded 17 Jul 2026Source
- Form 5 (FY 2022-2023)Form 5 Shri krishna vastu FY 22-23.pdf · uploaded 22 Jul 2026Source
- Form 5 (FY 2023-2024)Form 5 FY 2023-24.pdf · uploaded 22 Jul 2026Source
- Form 2A (FY 2022-2023)Form 2a SKV Mar 2023.pdf · uploaded 16 Sep 2026Source
- Form 2A (FY 2023-2024)Form 2a SKV Mar 2024.pdf · uploaded 16 Sep 2026Source
- Form 2A (FY 2024-2025)Form 2a SKV Mar 2025.pdf · uploaded 16 Sep 2026Source
- Form 2A (FY 2025-2026)Form 2a SKV Mar 2026.pdf · uploaded 16 Sep 2026Source
Technical
- DocumentKBMC Plan Pass 2_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 3_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 4_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 5_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 6_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 7_1.pdf · uploaded 29 Nov 2022Source
- DocumentKBMC Plan Pass 1_1.pdf · uploaded 29 Nov 2022Source
Technical (Architect)
- DocumentForm 1 Shri krishna vastu_003.pdf · uploaded 8 Oct 2024Source
- DocumentForm 1 Shri krishna vastu_003.pdf · uploaded 8 Oct 2024Source
- DocumentForm 1 Shri Krishna Vastu Sep 24.pdf · uploaded 22 Jan 2025Source
- DocumentForm 1 Shri Krishna Vastu Dec 24.pdf · uploaded 12 Mar 2025Source
- DocumentSigned Form 1 June 2026 Shri Krishna Vastu.pdf · uploaded 17 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 Shri Krishna Vastu_004.pdf · uploaded 8 Oct 2024Source
- DocumentForm 2 Shri Krishna Vastu_004.pdf · uploaded 8 Oct 2024Source
- DocumentForm 2 Shri Krishna Vastu Sep 24.pdf · uploaded 22 Jan 2025Source
- DocumentForm 2 Shri Krishna Vastu Dec 24.pdf · uploaded 12 Mar 2025Source
- DocumentSigned Form 2 June 2026 Shri Krishna Vastu.pdf · uploaded 17 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO4/3/A, S NO 4/3/B/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK168 units in all
- Address
- S No4/3/A, S No 4/3/B/1, S No 4/3/B/2, Badlapur, BadlapurPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.15394, 73.24654
- Land area for this project
- 6,580 sq m (70,826 sq ft)
- Permissible built-up area
- 7,525 sq m (80,995 sq ft)
- Sanctioned built-up area
- 7,525 sq m (80,995 sq ft)
- Recreational open space
- 632 sq m (6,801 sq ft)
- Designated bank account
- 82
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO4/3/A,S NO 4/3/B/1, S NO 4/3/B/2
Boundaries
- North
- S No 4 H No 5 S No 4 H No2
- South
- S No 3
- East
- S No 5 H No 1
- West
- S No 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking168 units
5 of 168 units booked (3%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | 1BHK | 29.44 sq m · 317 sq ft | 102 | 3 |
| Wing A | 1RK | 27.56 sq m · 297 sq ft | 26 | 2 |
| Wing B | 1BHK | 29.44 sq m · 317 sq ft | 16 | 0 |
| Wing B | 2BHK | 38.37 sq m · 413 sq ft | 4 | 0 |
| Wing C | 1BHK | 29.44 sq m · 317 sq ft | 16 | 0 |
| Wing C | 1RK | 27.56 sq m · 297 sq ft | 4 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Acotech Consultants Pvt Ltd | — |
| Chartered accountant | Aska & Co | — |
| Chartered accountant | Monisha Kuperkar | — |
| Chartered accountant | Nitish Deo | — |
| Engineer | Atul Kudtarkar & Associates Pvt Ltd | — |
| Engineer | Utkarsha Ravindra Mukadam | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Badlapur
- KalpataruRERA PR1330002602159
- City Pride NxRERA PM1330002601687
- Sai UniverseRERA PR1330002601334
- James Residency Phase 3RERA P51700081009
- Vishnu KrupaRERA PM1330002500811
- Matrukrupa Co-operative Housing Society LtdRERA P51700080588
- Ram EmpireRERA P51700080024
- Patels MeadowsRERA P51700079829
All 152 projects in Badlapur · Compare Dattatray Residency with another project