Mihir Chsl
Deedo IDDP-THN-2Z82Completion was pushed back 10 months to Mar 2025, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.
Ambarnath, Maharashtra 421503 · by Harshal Ramdas Navghare
Buying a flat here?
See every deed registered on it.
Completion was pushed back 10 months to Mar 2025, and that date has passed too
- This projectRegistered 26 May 2022, completion promised 31 May 2024, revised to 31 Mar 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700045607
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700045607 | 26 May 2022 | 31 May 2024 | 31 Mar 2025 | Harshal Ramdas Navghare | Project page |
Documents46
2 documents held by Deedo, 44 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card harshal.pdf · uploaded 9 May 2022Source
Legal
Show all 46 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportSearch Report.pdf · uploaded 9 May 2022Source
- 1 Details of encumbrancesNO ENCRUMBANCES CERTIFICATE.pdf · uploaded 9 May 2022Source
- 1 Copy of Layout Approval (in case of layout)approved plan copy.pdf · uploaded 9 May 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentapproved plan copy.pdf · uploaded 9 May 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 9 May 2022Source
- 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 9 May 2022Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 9 May 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate mihir chsl.pdf · uploaded 9 May 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Mihir CHSL.pdf · uploaded 9 May 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200235703389_For_Asset_Based_Search_23_04_2022_10_50_03_942.pdf · uploaded 9 May 2022Source
- 2 CERSAI detailsCERSAI TRANSACTION ID.pdf · uploaded 9 May 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 9 May 2022Source
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 May 2022Source
- 2 Proforma of Allotment letterRERA Draft afreement.pdf · uploaded 9 May 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAR 23.pdf · uploaded 14 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUN 23.pdf · uploaded 14 Jun 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEPT 23.pdf · uploaded 14 Jun 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 23.pdf · uploaded 14 Jun 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAR 24.pdf · uploaded 14 Jun 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MARCH 23.pdf · uploaded 14 Jun 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUN 2023.pdf · uploaded 14 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 2023.pdf · uploaded 14 Jun 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 2023.pdf · uploaded 14 Jun 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAR 2024.pdf · uploaded 14 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A MAR 24.pdf · uploaded 14 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 CA 22-23.pdf · uploaded 14 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 mihir june 2024.pdf · uploaded 9 Dec 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 mihir sept 2024.pdf · uploaded 9 Dec 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)june form 2.pdf · uploaded 9 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)sept form 2.pdf · uploaded 9 Dec 2024Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 8 at Ambarnath
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK, Shop29 units in all
- Address
- 8, Old Katrap Road, Badlapur EastPIN 421503
- Land area for this project
- 1,446 sq m (15,562 sq ft)
- Permissible built-up area
- 883 sq m (9,506 sq ft)
- Sanctioned built-up area
- 883 sq m (9,506 sq ft)
- Recreational open space
- 563 sq m (6,056 sq ft)
- Designated bank account
- 41
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
8
Boundaries
- North
- Adj Plot No 15 And 16
- South
- Adj Plot No 8 And 18
- East
- Layout Road
- West
- Layout Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking29 units
0 of 29 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 233.72 sq m · 2,516 sq ft | 8 | 0 |
| 1RK | 88.88 sq m · 957 sq ft | 4 | 0 |
| 2BHK | 467.8 sq m · 5,035 sq ft | 12 | 0 |
| Shop | 92.72 sq m · 998 sq ft | 5 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ravindra Ghormode | — |
| Chartered accountant | P C Parvadiya And Associates | — |
| Engineer | Suntech Engineers & Consultants | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Ambarnath
- Sai Sonali GrandRERA PR1330002602653
- Shree Swanand ApartmentRERA PR1330002602633
- Vishnu Puram (Rugi Aurelia)RERA PM1330002602632
- Tridal Co. Op.hsg. Soc. Ltd.RERA PM1330002602595
- Jewel AurraRERA PR1330002602533
- Maa ShardaRERA PR1330002602477
- Mangal Chhaya Co Operative Hsg Soc LtdRERA PM1330002602480
- Shree Smaran HeightsRERA PR1330002602461
All 1,602 projects in Ambarnath · Compare Mihir Chsl with another project