Residential / Group Housing · 1 building · 29 unitsRERA P51700045607

Mihir Chsl

Deedo IDDP-THN-2Z82

Completion was pushed back 10 months to Mar 2025, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Ambarnath, Maharashtra 421503 · by Harshal Ramdas Navghare

Delivery2 yrs 6 mo latePromised May 2024 · revised Mar 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 29 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 10 months to Mar 2025, and that date has passed too

  • This projectRegistered 26 May 2022, completion promised 31 May 2024, revised to 31 Mar 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700045607
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004560726 May 202231 May 202431 Mar 2025Harshal Ramdas NavghareProject page
Documents46

2 documents held by Deedo, 44 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardpan card harshal.pdf · uploaded 9 May 2022Source

Legal

  • Legal Title reporttitle certificate rera.pdf · uploaded 9 May 2022Source
  • Legal Title reportSearch Report.pdf · uploaded 9 May 2022Source
  • Declaration Form BFORM B.pdf · uploaded 9 May 2022Source

Migrated

  • 1 PAN Cardpan card harshal.pdf · uploaded 9 May 2022Source
  • 1 Copy of the legal title reporttitle certificate rera.pdf · uploaded 9 May 2022Source
Show all 46 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportSearch Report.pdf · uploaded 9 May 2022Source
  • 1 Details of encumbrancesNO ENCRUMBANCES CERTIFICATE.pdf · uploaded 9 May 2022Source
  • 1 Copy of Layout Approval (in case of layout)approved plan copy.pdf · uploaded 9 May 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentapproved plan copy.pdf · uploaded 9 May 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 9 May 2022Source
  • 1 Declaration about Commencement CertificateCC DECLARATION.pdf · uploaded 9 May 2022Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 9 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate mihir chsl.pdf · uploaded 9 May 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Mihir CHSL.pdf · uploaded 9 May 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200235703389_For_Asset_Based_Search_23_04_2022_10_50_03_942.pdf · uploaded 9 May 2022Source
  • 2 CERSAI detailsCERSAI TRANSACTION ID.pdf · uploaded 9 May 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 9 May 2022Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 May 2022Source
  • 2 Proforma of Allotment letterRERA Draft afreement.pdf · uploaded 9 May 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAR 23.pdf · uploaded 14 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUN 23.pdf · uploaded 14 Jun 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEPT 23.pdf · uploaded 14 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 23.pdf · uploaded 14 Jun 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAR 24.pdf · uploaded 14 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MARCH 23.pdf · uploaded 14 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUN 2023.pdf · uploaded 14 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 2023.pdf · uploaded 14 Jun 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 2023.pdf · uploaded 14 Jun 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAR 2024.pdf · uploaded 14 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A MAR 24.pdf · uploaded 14 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 CA 22-23.pdf · uploaded 14 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 mihir june 2024.pdf · uploaded 9 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 mihir sept 2024.pdf · uploaded 9 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)june form 2.pdf · uploaded 9 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)sept form 2.pdf · uploaded 9 Dec 2024Source

Technical

  • Documentapproved plan copy.pdf · uploaded 9 May 2022Source
  • Documentapproved plan copy.pdf · uploaded 9 May 2022Source

Technical (Architect)

  • DocumentFORM 1 MAR 24.pdf · uploaded 14 Jun 2024Source
  • Documentform 1 mihir june 2024.pdf · uploaded 9 Dec 2024Source
  • Documentform 1 mihir sept 2024.pdf · uploaded 9 Dec 2024Source

Technical (Engineer)

  • DocumentFORM 2 MAR 2024.pdf · uploaded 14 Jun 2024Source
  • Documentjune form 2.pdf · uploaded 9 Dec 2024Source
  • Documentsept form 2.pdf · uploaded 9 Dec 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 8 at Ambarnath

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, Shop29 units in all
Address
8, Old Katrap Road, Badlapur EastPIN 421503
Land area for this project
1,446 sq m (15,562 sq ft)
Permissible built-up area
883 sq m (9,506 sq ft)
Sanctioned built-up area
883 sq m (9,506 sq ft)
Recreational open space
563 sq m (6,056 sq ft)
Designated bank account
41
Developed in phases
No

Survey, CTS, gat or plot numbers

8 at Ambarnath

Land as published on MahaRERA's project page

8

Boundaries

North
Adj Plot No 15 And 16
South
Adj Plot No 8 And 18
East
Layout Road
West
Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking29 units

0 of 29 units booked (0%), as the promoter reported to MahaRERA

1BHK · 8 units1RK · 4 units2BHK · 12 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK233.72 sq m · 2,516 sq ft80
1RK88.88 sq m · 957 sq ft40
2BHK467.8 sq m · 5,035 sq ft120
Shop92.72 sq m · 998 sq ft50

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRavindra Ghormode—
Chartered accountantP C Parvadiya And Associates—
EngineerSuntech Engineers & Consultants—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ambarnath

All 1,602 projects in Ambarnath · Compare Mihir Chsl with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology