Harshal Ramdas Navghare

Deedo IDDD-2D5E

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 67 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay67 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
nakshatraP51700005959KudsavareCertificate Signed31 May 201931 Dec 2027+103 mo
Mihir ChslP51700045607AmbarnathCertificate Signed31 May 202431 Mar 2025+30 mo*

Harshal Ramdas Navghare, in questions

Does Harshal Ramdas Navghare finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 67 mo late. Across Maharashtra, 73% kept their date.

How many projects has Harshal Ramdas Navghare registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Harshal Ramdas Navghare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology