7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects198
Registrations200some projects hold several
Completion still due8095 past their date
Median extension4 months37% of registrations extended
Regulatory cases4on 4 projects

7 in 10 registrations run late here

200 MahaRERA registrations in Karad and the places within it

31 not yet due49 extended, not yet due95 past even the latest date25 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Karad

198 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Harmony ApartmentK P AssociatesDue Dec 2026——
Vishal EliteVishal Shivajirao JagtapDue Apr 2030, extended 4 mo——
Ekdant ResidencyEkdant DevelopersDue Dec 2028, extended 4 mo——
Siddhivinayak HeightsSiddhivinayak InfraDue Oct 2027, extended 4 mo——
Rangsarja EmpireJagtap BuildersDue Apr 2029, extended 4 mo——
Vardhan GovindVardhan PropertiesDue Apr 2031, extended 4 mo——
Devgiri Row BungalowsPerfect Builders And DevelopersCompleted——
Kst Central ParkKst ConstructionsDue Apr 2031, extended 4 mo——
Rau Gold CoastShreem Multicon Private LimitedDue Apr 2028, extended 4 mo——
D S HeritageD S DevelopersDue Apr 2028, extended 4 mo——
Vrundavan City Phase 3Kalyani AssociatesDue Jun 2028, extended 4 mo——
Aruved CrownShubhangi Nilesh PatilDue Apr 2028, extended 4 mo——
Smaark oneDevashree Garden LLPDue May 2028, extended 4 mo——
Deshmukhs Royal CasalMohini Bhalchandra DeshmukhDue Dec 2026, extended 4 mo——
Satyajeet ParadiseSatyajeet ParadiseDue Apr 2028, extended 4 mo——
Shriram City Wing BVijaykumar Ramesh DhumalDue Apr 2028, extended 4 mo——
Sai ResidencyShri Sai DevelopersCompleted, extended 4 mo——
Gurudarshan Phase IIGurudatta Builders And DevelopersDue Feb 2028, extended 4 mo—6%
Uttam ResidencyNilam Ashokrao PatilDue Apr 2031, extended 4 mo——
Padmavati HeightsAvinash Pandurang Kamble11 mo late——
Pooja Royal BShital Tanaji RamugadeCompleted—9%
Silver SpringsJanardhan Pandurang JadhavDue Jul 2027, extended 4 mo——
Janaki PrestigeSarada Landmark Private LimitedDue Sep 2027, extended 4 mo——
Shivsamarth ApartmentSai Construction & Santaji Vinayak PatilDue May 2029——
Aanand ViharrDubal EmpireDue Apr 2028, extended 4 mo——
Karad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Kalyani Associates3 projects
  2. Sarada Landmark Private Limited3 projects
  3. Shubhashree Infrastructure3 projects
  4. Ajantadevelopers2 projects
  5. Anuraj Construction2 projects
  6. Aruved Builders & Developers2 projects
  7. D S Developers2 projects
  8. Gurudatta Builders And Developers2 projects
  9. Kanyaratna Infra2 projects
  10. Kst Constructions2 projects

Karad, in questions

How many projects in Karad run late?

7 in 10 MahaRERA registrations (144 of 200): their completion date was extended or has passed, data through 10 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Karad by Deedo. Medians on fewer than 3 deeds are not shown.

Data through10 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology