Deedo IDDL-SAN-MIRAJ9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects664
Registrations668some projects hold several
Completion still due105537 past their date
Median extension4 months24% of registrations extended
Regulatory cases7on 7 projects
9 in 10 registrations run late here
668 MahaRERA registrations in Miraj and the places within it
23 not yet due82 extended, not yet due537 past even the latest date26 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Miraj
664 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Saicharan HeightsAshtang Developers | Due Oct 2027, extended 4 mo | — | — |
| Galaxy SkySky Galaxy Constructions | 6 mo late | — | 20% |
| Shiv AspireVian Unity | 7 mo late | — | 24% |
| Bhosale EmpireBhosale Developers | Completed | — | 23% |
| Mayur Convention CenterShivgayatri Buildcon Private Limited | Due Apr 2028, extended 4 mo | — | — |
| Megh Malhar ResidencyMalhar Buildcon | Due Mar 2027 | — | — |
| Kamal RanjiniGokhale And Associates | Due Sep 2027, extended 4 mo | — | — |
| Shalinee HeightsM S Builders And Developers | Completed | — | 29% |
| Unity HarmonyUnity Contractors | Due Apr 2027, extended 4 mo | — | — |
| Agrawal ExoticaMr Agrawal Nilesh Nemichand (HUF) | Completed | — | — |
| R City MallYogshivrutu Land Developers Private Limited | Completed | — | — |
| Varad ChintamaniSrushti Developers | 11 mo late | — | 45% |
| Samarth RegencyNikhil Datta Thakur | 8 mo late | — | — |
| Galaxy TowerShivdatta Builders & Contractors | 1 mo late | — | 25% |
| Sidharth ApartmentNirmiti Developers | Completed | — | — |
| shashwat thirthSachin Sumatilal Bedmutha HUF | 2 yrs 8 mo late | — | 64% |
| Siyaram Meena ApartmentSitaram Giridharilal Meena | Completed | — | — |
| Royal HeightsShivrajya Construction | 11 mo late | — | 17% |
| Girnar ParkNIlesh Dnyaneshwar Khot | Due Dec 2026 | — | — |
| Brij ArcadeBrij Arcade | 11 mo late | — | 10% |
| Sky PalaceAkshay Nuclear LLP | Due Jun 2027 | — | — |
| Kp TowerRavindra Shankar Khilare | Completed | — | 8% |
| Raj GalaxyRashid Rajesaheb Hattiwale | Completed | — | — |
| Sai Sonai SahanivasVishwa Malhar Construction | Due Apr 2027, extended 4 mo | — | 7% |
| Shri Capital Apartment 3Shrisamarth Developers | 11 mo late | — | — |
Nearby: other talukas in Sangli
Most active promoters
- Creationproperties7 projects
- Deepak Vasantrao Suryawanshi7 projects
- Uttam Nagesh Arage7 projects
- Anandkumar Baban Rajmane6 projects
- Pranav Builders6 projects
- Tatyasaheb Sambhaji Khot6 projects
- Abhijit Vijaykumar Borgave5 projects
- Lagoo Builders And Consultants Pvt Ltd5 projects
- Pradeep Shridhar Phadke5 projects
- Pune Housing and Area Development Board Pune5 projects
Miraj, in questions
How many projects in Miraj run late?
9 in 10 MahaRERA registrations (619 of 668): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Miraj by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology