Residential / Group Housing · 1 building · 144 unitsRERA P52000045608

Balaji Tulips

Deedo IDDP-RAI-V03M

It is due for completion in Nov 2026, with no extension on record; no MahaRERA orders on record; 45% of its units are booked.

Rees, Raigarh 410222 · by Balaji Homes · 75% of its projects kept the RERA date

DeliveryDue Nov 2026No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales45% booked65 of 144 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Nov 2026, with no extension on record

  • This projectRegistered 26 May 2022, completion promised 30 Nov 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000045608
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200004560826 May 202230 Nov 202630 Nov 2026Balaji HomesProject page
Documents101

1 document held by Deedo, 100 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card BH-min.pdf · uploaded 7 May 2022Source

Legal

  • Declaration Form BForm B Declaration.pdf · uploaded 7 May 2022Source
  • Legal Title reportcertificate of Tittle (1).pdf · uploaded 24 May 2022Source
  • Legal Title reportLegal Title Report.pdf · uploaded 24 May 2022Source

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-compressed.pdf · uploaded 6 May 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_compressed.pdf · uploaded 6 May 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed part 2.pdf · uploaded 6 May 2022Source
Show all 101 documentsShow fewer documents

Migrated

  • 1 Proforma of Allotment letterAllotment Letter for Balaji Tulips pdf.pdf · uploaded 6 May 2022Source
  • 1 PAN Cardpan card BH-min.pdf · uploaded 7 May 2022Source
  • 1 Details of encumbrancesEncrumbenses.pdf · uploaded 7 May 2022Source
  • 1 Copy of Layout Approval (in case of layout)1 Building Plan Approval pg 1 Layout Plan.pdf · uploaded 7 May 2022Source
  • 1 Building Plan Approval / NA Order for plotted development1-8.pdf · uploaded 7 May 2022Source
  • 2 Building Plan Approval / NA Order for plotted development2-8.pdf · uploaded 7 May 2022Source
  • 3 Building Plan Approval / NA Order for plotted development3-8.pdf · uploaded 7 May 2022Source
  • 4 Building Plan Approval / NA Order for plotted development4-8.pdf · uploaded 7 May 2022Source
  • 5 Building Plan Approval / NA Order for plotted development5-8.pdf · uploaded 7 May 2022Source
  • 6 Building Plan Approval / NA Order for plotted development6-8.pdf · uploaded 7 May 2022Source
  • 7 Building Plan Approval / NA Order for plotted development7-8.pdf · uploaded 7 May 2022Source
  • 8 Building Plan Approval / NA Order for plotted development8-8.pdf · uploaded 7 May 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Balaji Tulips Page 1 - 2-min.pdf · uploaded 7 May 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Balaji Tulips Page 3-4-min.pdf · uploaded 7 May 2022Source
  • 1 Declaration about Commencement Certificate2 (1).pdf · uploaded 7 May 2022Source
  • 1 Declaration in FORM BForm B Declaration.pdf · uploaded 7 May 2022Source
  • 1 Disclosure of sold/ booked inventoryDiscloure of Sold Inventory.pdf · uploaded 7 May 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200237987053_For_Asset_Based_Search_23_05_2022_20_30_36_276.pdf · uploaded 23 May 2022Source
  • 1 Copy of the legal title reportcertificate of Tittle (1).pdf · uploaded 24 May 2022Source
  • 2 Copy of the legal title reportLegal Title Report.pdf · uploaded 24 May 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Balaji Tulips.pdf · uploaded 15 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 B Tulips.pdf · uploaded 21 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 B Tulips.pdf · uploaded 23 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 19 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)BALAJI HOMES FORM - 3 20-04-24.pdf · uploaded 20 Apr 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1Tulips.pdf · uploaded 26 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Tulips.pdf · uploaded 26 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 B Tulips.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 BALAJI TULIPS.pdf · uploaded 22 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Tulips 30th June 2024_compressed.pdf · uploaded 22 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Tulips 30th June 2024.pdf · uploaded 22 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Balaji Tulips 31st Dec 2024_compressed.pdf · uploaded 22 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 BALAJI TULIPS.pdf · uploaded 22 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentTULIP REVISED CC.pdf · uploaded 6 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted development01 (2)-compressed.pdf · uploaded 6 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted development02 (2)-compressed.pdf · uploaded 6 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted development03 (1)-compressed.pdf · uploaded 6 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted development04 (1)-compressed.pdf · uploaded 6 Mar 2025Source
  • 5 Building Plan Approval / NA Order for plotted development05 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • 6 Building Plan Approval / NA Order for plotted development06 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • 7 Building Plan Approval / NA Order for plotted development07 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • 8 Building Plan Approval / NA Order for plotted development8 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • 1 Details of encumbrancesEncumbrances Tulip.pdf · uploaded 7 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectEncumbrances Tulip.pdf · uploaded 7 May 2025Source
  • Form 1Form 1 Sep 2025 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 1Form 1 Sep 2025 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 2Form 2 Sep 2025 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 2Form 2 Sep 2025 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 3Form 3 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 3Form 3 Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Balaji Tulips.pdf · uploaded 20 Nov 2025Source
  • Form 2A (FY 2024-2025)Form 2A 2024-25.pdf · uploaded 20 Nov 2025Source
  • Form 5 (FY 2022-2023)Form 5 2022-23.pdf · uploaded 20 Nov 2025Source
  • Form 5 (FY 2023-2024)Form 5 2023-24.pdf · uploaded 20 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5 2024-25.pdf · uploaded 20 Nov 2025Source
  • Form 2A (FY 2022-2023)Form 2A 2022-23.pdf · uploaded 21 Nov 2025Source
  • Form 2A (FY 2023-2024)Form 2A 2023-24.pdf · uploaded 21 Nov 2025Source
  • Withdrawal Update Form 1Form 1 B Tulips 31122025.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 2Form 2 B Tulips.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 3Form 3 Dec-25 Tulips revised (1).pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 1Form 1 balaji tulips as on march 2026.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 2Form 2 balaji tulips as on march 2026.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 3Form 3 balaji tulips as on march 2026.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 1Form 1 Balaji Tulips June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Balaji Tulips June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Balaji Tulips June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1Form 1 Balaji Tulips June 2026.pdf · uploaded 1 Sep 2026Source
  • Withdrawal Update Form 2Form 2 Balaji Tulips June 2026.pdf · uploaded 1 Sep 2026Source
  • Withdrawal Update Form 3Form 3 Balaji Tulips June 2026.pdf · uploaded 1 Sep 2026Source

Technical

  • Document1 Building Plan Approval pg 1 Layout Plan.pdf · uploaded 7 May 2022Source
  • Document2-8.pdf · uploaded 7 May 2022Source
  • Document3-8.pdf · uploaded 7 May 2022Source
  • Document4-8.pdf · uploaded 7 May 2022Source
  • Document5-8.pdf · uploaded 7 May 2022Source
  • Document6-8.pdf · uploaded 7 May 2022Source
  • Document7-8.pdf · uploaded 7 May 2022Source
  • Document8-8.pdf · uploaded 7 May 2022Source
  • Document1-8.pdf · uploaded 7 May 2022Source
  • Document01 (2)-compressed.pdf · uploaded 6 Mar 2025Source
  • Document02 (2)-compressed.pdf · uploaded 6 Mar 2025Source
  • Document03 (1)-compressed.pdf · uploaded 6 Mar 2025Source
  • Document04 (1)-compressed.pdf · uploaded 6 Mar 2025Source
  • Document05 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • Document06 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • Document07 (1)_compressed.pdf · uploaded 6 Mar 2025Source
  • Document8 (1)_compressed.pdf · uploaded 6 Mar 2025Source

Technical (Architect)

  • DocumentForm 1Tulips.pdf · uploaded 26 Oct 2024Source
  • DocumentForm 1 BALAJI TULIPS.pdf · uploaded 22 Feb 2025Source
  • DocumentForm 1 Balaji Tulips June 2026.pdf · uploaded 30 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Tulips.pdf · uploaded 26 Oct 2024Source
  • DocumentForm 2 BALAJI TULIPS.pdf · uploaded 22 Feb 2025Source
  • DocumentForm 2 Balaji Tulips June 2026.pdf · uploaded 30 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 172/6

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop144 units in all
Address
172/6, Dand Apta Road, MohopadaPIN 410222
Village
Rees, Khalapur taluka
Land area for this project
4,450 sq m (47,899 sq ft)
Permissible built-up area
12,705 sq m (1,36,755 sq ft)
Sanctioned built-up area
8,604 sq m (92,613 sq ft)
Recreational open space
446 sq m (4,801 sq ft)
Designated bank account
89
Developed in phases
No

Survey, CTS, gat or plot numbers

172/6

Land as published on MahaRERA's project page

172/6

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking144 units

65 of 144 units booked (45%), as the promoter reported to MahaRERA

1BHK · 77 units2BHK · 52 unitsShop · 15 units
TypeCarpet areaUnitsBooked
1BHK32.45 sq m · 349 sq ft83
1BHK32.87 sq m · 354 sq ft61
1BHK32.91 sq m · 354 sq ft11
1BHK33.23 sq m · 358 sq ft166
1BHK33.29 sq m · 358 sq ft114
1BHK33.38 sq m · 359 sq ft198
1BHK33.47 sq m · 360 sq ft162
2BHK38.34 sq m · 413 sq ft10
Show all 17 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK38.7 sq m · 417 sq ft1814
2BHK52.58 sq m · 566 sq ft3320
Shop8.51 sq m · 92 sq ft22
Shop11.42 sq m · 123 sq ft32
Shop11.88 sq m · 128 sq ft21
Shop13.7 sq m · 147 sq ft20
Shop15 sq m · 161 sq ft20
Shop15.39 sq m · 166 sq ft20
Shop16.09 sq m · 173 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSatish Manohar—
Chartered accountantRashmikesh Panigrahi—
Chartered accountantSachin Prabhakar Saraf—
EngineerSandesh Bagkar—
EngineerYatish Tare—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Rees

All 28 projects in Rees · Compare Balaji Tulips with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology