Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 80 mo late.

Projects45 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay80 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Balaji SplendourP52000002182AdaiCertificate Signed30 Jun 201830 Jun 2018On date
Balaji OrchidsP52000015351ReesCertificate Signed30 Dec 202130 Dec 2021On date
Balaji SplendourP52000016889AdaiCertificate Signed31 Mar 202030 Mar 2022+80 mo*
Balaji CornerP52000027101UlaweCertificate Signed30 Oct 202230 Oct 2022On date
Balaji TulipsP52000045608ReesCertificate Signed30 Nov 202630 Nov 2026On date

Balaji Homes, in questions

Does Balaji Homes finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 80 mo late. Across Maharashtra, 73% kept their date.

How many projects has Balaji Homes registered with MahaRERA?

4 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.

Does Balaji Homes have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology