Residential / Group Housing · 2 buildings · 128 unitsRERA P52000077349

Aashray Nisarg

Deedo IDDP-RAI-4BW5

Completion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 2% of its units are booked.

Rees, Raigarh 410222 · by Aashray Homes

DeliveryExtended 4 moPromised Jun 2028 · now due Oct 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales2% booked3 of 128 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2028

  • This projectRegistered 9 Aug 2024, completion promised 30 Jun 2028, revised to 30 Oct 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000077349
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000773499 Aug 202430 Jun 202830 Oct 2028Aashray HomesProject page
Documents99

1 document held by Deedo, 98 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 5 Jul 2024Source
  • OthersCERSAI DECLARATION.pdf · uploaded 28 Mar 2026Source
  • OthersENCUMBRANCES FINANCE.pdf · uploaded 28 Mar 2026Source
  • OthersDISCLOSURE OF LOAN.pdf · uploaded 31 Mar 2026Source
  • OthersCERSAI 1.pdf · uploaded 31 Mar 2026Source
  • OthersCERSAI 2.pdf · uploaded 31 Mar 2026Source

Legal

  • Other – LegalSALE DEED.pdf · uploaded 5 Jul 2024Source
Show all 99 documentsShow fewer documents

Legal

  • Declaration Form BFORM B-AFFIDAVIT.pdf · uploaded 5 Jul 2024Source
  • Legal Title reportTITLE.pdf · uploaded 15 Jul 2024Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 5 Jul 2024Source
  • 1 a Details of encumbrances concerned to FinanceNO ENCUMBRANCES LEGAL.pdf · uploaded 5 Jul 2024Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCES LEGAL.pdf · uploaded 5 Jul 2024Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN 1.pdf · uploaded 5 Jul 2024Source
  • 2 Copy of Layout Approval (in case of layout)Layout Plan 2.pdf · uploaded 5 Jul 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 1.pdf · uploaded 5 Jul 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 2.pdf · uploaded 5 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 3.pdf · uploaded 5 Jul 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentBLDG PLAN 4.pdf · uploaded 5 Jul 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 5 Jul 2024Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE AASHRAY.pdf · uploaded 5 Jul 2024Source
  • 1 Declaration in FORM BFORM B-AFFIDAVIT.pdf · uploaded 5 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 5 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 5 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 5 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST AMIT.pdf · uploaded 5 Jul 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST KISAN.pdf · uploaded 5 Jul 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST NIKUNJ.pdf · uploaded 5 Jul 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST PANKAJ.pdf · uploaded 5 Jul 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST PARESH.pdf · uploaded 5 Jul 2024Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST RAHUL.pdf · uploaded 5 Jul 2024Source
  • 7 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST RAJESH .pdf · uploaded 5 Jul 2024Source
  • 8 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST SUNIL.pdf · uploaded 5 Jul 2024Source
  • 9 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST VITHAL.pdf · uploaded 5 Jul 2024Source
  • 1 Proforma of Agreement for saleDRAFT AFS.pdf · uploaded 5 Jul 2024Source
  • 1 Proforma of Allotment letterDRAFT ALLOTTMENT.pdf · uploaded 5 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT ALLOTMENT.pdf · uploaded 5 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT AGREEMENT FOR SALE.pdf · uploaded 5 Jul 2024Source
  • 1 Other – LegalSALE DEED.pdf · uploaded 5 Jul 2024Source
  • 1 Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 5 Jul 2024Source
  • 1 Copy of the legal title reportTITLE.pdf · uploaded 15 Jul 2024Source
  • 2 a Details of encumbrances concerned to FinanceNO ENCUM FINANCE.pdf · uploaded 15 Jul 2024Source
  • 2 b Details of encumbrances concerned to LegalNO ENCUM FINANCE.pdf · uploaded 15 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC CONFIRMATION EMAIL.pdf · uploaded 15 Jul 2024Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 15 Jul 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDETAILS OF SEC UNSEC LOAN.pdf · uploaded 15 Jul 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A PROMOTER LETTERHEAD 1.pdf · uploaded 15 Jul 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B BANK LETTER.pdf · uploaded 15 Jul 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC CONFIRMATION EMAIL.pdf · uploaded 21 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEPT 24.pdf · uploaded 18 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 24.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SEPT 24.pdf · uploaded 18 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 DEC 24.pdf · uploaded 18 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 24.pdf · uploaded 18 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 24.pdf · uploaded 18 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD SEPT 24.pdf · uploaded 18 Feb 2025Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD DEC 24.pdf · uploaded 18 Feb 2025Source
  • Form 1FORM 1 SEPT 24.pdf · uploaded 16 Jun 2025Source
  • Form 2FORM 2 SEPT 24.pdf · uploaded 16 Jun 2025Source
  • Form 3FORM 3 SEPT 24.pdf · uploaded 16 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD SEPT 24.pdf · uploaded 16 Jun 2025Source
  • Form 1FORM 1 DEC 24.pdf · uploaded 16 Jun 2025Source
  • Form 2FORM 2 DEC 24.pdf · uploaded 16 Jun 2025Source
  • Form 3FORM 3 DEC 24.pdf · uploaded 16 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD DEC 24.pdf · uploaded 16 Jun 2025Source
  • Form 1FORM 1 MAR 25.pdf · uploaded 16 Jun 2025Source
  • Form 2FORM 2 MAR 25.pdf · uploaded 16 Jun 2025Source
  • Form 3FORM 3 MAR 25.pdf · uploaded 16 Jun 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD MAR 25.pdf · uploaded 16 Jun 2025Source
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 JUN 25.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 SEPT 25.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 2FORM 2 SEPT 25.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 3FORM 3 SEPT 25.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 25.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 26.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 26.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 26.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 1FORM 1 JUNE 26.pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 JUNE 26.pdf · uploaded 1 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 26.pdf · uploaded 1 Aug 2026Source

Technical

  • DocumentLAYOUT PLAN 1.pdf · uploaded 5 Jul 2024Source
  • DocumentLayout Plan 2.pdf · uploaded 5 Jul 2024Source
  • DocumentBLDG PLAN 1.pdf · uploaded 5 Jul 2024Source
  • DocumentBLDG PLAN 2.pdf · uploaded 5 Jul 2024Source
  • DocumentBLDG PLAN 3.pdf · uploaded 5 Jul 2024Source
  • DocumentBLDG PLAN 4.pdf · uploaded 5 Jul 2024Source
  • Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 5 Jul 2024Source
  • OthersFORM 1.pdf · uploaded 28 Mar 2026Source
  • OthersFORM 2.pdf · uploaded 28 Mar 2026Source

Technical (Architect)

  • DocumentFORM 1 SEPT 24.pdf · uploaded 18 Feb 2025Source
  • DocumentFORM 1 DEC 24.pdf · uploaded 18 Feb 2025Source
  • DocumentFORM 1 JUNE 26.pdf · uploaded 1 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2 SEPT 24.pdf · uploaded 18 Feb 2025Source
  • DocumentFORM 2 DEC 24.pdf · uploaded 18 Feb 2025Source
  • DocumentFORM 2 JUNE 26.pdf · uploaded 1 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 20/3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1.5BHK, 1BHK, 2BHK, Shop128 units in all
Address
Survey No 20/3, Survey No 20/3, ReesPIN 410222
Village
Rees, Khalapur taluka
Land area for this project
2,580 sq m (27,771 sq ft)
Permissible built-up area
6,267 sq m (67,453 sq ft)
Sanctioned built-up area
6,267 sq m (67,453 sq ft)
Designated bank account
51
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO 20/3

Land as published on MahaRERA's project page

SURVEY NO 20/3

Boundaries

North
Road
South
Structure
East
Survey No 20 4
West
H N 1 5

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking128 units

3 of 128 units booked (2%), as the promoter reported to MahaRERA

1.5BHK · 28 units1BHK · 78 units2BHK · 10 unitsShop · 12 units
BuildingTypeCarpet areaUnitsBooked
A Wing1.5BHK41.56 sq m · 447 sq ft140
A Wing1BHK26.3 sq m · 283 sq ft70
A Wing1BHK29.03 sq m · 312 sq ft140
A Wing1BHK29.74 sq m · 320 sq ft60
A Wing1BHK31.83 sq m · 343 sq ft50
A Wing1BHK32.97 sq m · 355 sq ft10
A Wing1BHK33.79 sq m · 364 sq ft60
A Wing2BHK47.38 sq m · 510 sq ft41
Show all 27 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Wing2BHK47.51 sq m · 511 sq ft40
A Wing2BHK48.78 sq m · 525 sq ft10
A Wing2BHK48.93 sq m · 527 sq ft11
A WingShop19.43 sq m · 209 sq ft10
A WingShop20.04 sq m · 216 sq ft10
A WingShop22 sq m · 237 sq ft10
A WingShop24.23 sq m · 261 sq ft10
A WingShop25.51 sq m · 275 sq ft10
A WingShop25.93 sq m · 279 sq ft10
A WingShop26.53 sq m · 286 sq ft10
A WingShop26.95 sq m · 290 sq ft30
A WingShop29.6 sq m · 319 sq ft10
A WingShop36.26 sq m · 390 sq ft10
B Wing1.5BHK41.56 sq m · 447 sq ft140
B Wing1BHK29.03 sq m · 312 sq ft141
B Wing1BHK29.74 sq m · 320 sq ft60
B Wing1BHK30.59 sq m · 329 sq ft60
B Wing1BHK34.54 sq m · 372 sq ft70
B Wing1BHK34.82 sq m · 375 sq ft60

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr P K Madhav—
Chartered accountantL K Dedhia & Co—
EngineerKb Consultants—

Source: MahaRERA project page. Contact details are not shown.