RERA projects in Poyanje
5 projects under 6 MahaRERA registrations, registered 2018–2026. 33% have a completion date extended beyond the one promised.
Locality
5RERA projects
6Registrationssome projects hold several
2Completion still due4 past their completion date
20 monthsMedian extension beyond promised date33% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 2 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Poyanje
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| ParkcityRaigad Friends LLP | PR1270002502598 | 4 Mar 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Pushp VasundharaHari Om Builders and Developers | P52000079381 | 3 Mar 2025 | 1 Jun 2027 | — | Not yet due | 0 |
| Eden Garden Phase -IILaxmikantan R Venkatraman | P52000028297 | 18 Feb 2021 | 30 Mar 2022 | — | Promised date passed | 0 |
| Sundar ResidencyLaxmikantan Ramakrishnan Venkatraman | P52000016733, P52000029402 | 12 Jun 2018 | 16 May 2023 | 16 May 2023 | Promised date passed | 0 |
| Eden GardenLaxmikantan R Venkatraman | P52000015065 | 23 Jan 2018 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other localities in Panvel
Most active promoters
By projects registered here, as named on MahaRERA.
- Laxmikantan R Venkatraman2 projects
- Hari Om Builders and Developers1 project
- Laxmikantan Ramakrishnan Venkatraman1 project
- Raigad Friends LLP1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology