Plot 1 Sector 36 Taloja
Deedo IDDP-RAI-7PMPMahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 100% of its units are booked.
Pendhar, Raigarh 410208 · by Cidco Of Maharashtra Ltd · 17% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year
- This projectRegistered 4 Sep 2019, completion promised 30 May 2023, revised to 29 May 2024.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
15 buildings
Open a building to see every flat, floor by floor.
- Building (P52000022182)Size not on record100% booked
- EWS 115 floors
- EWS 215 floors
- EWS 315 floors
- EWS 415 floors
- EWS 515 floors
- EWS 615 floors
- LIG 123 floors
- LIG 223 floors
- LIG 323 floors
- LIG 423 floors
- LIG 522 floors
Show all 15 buildingsShow fewer buildings
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000022182
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000022182 | 4 Sep 2019 | 30 May 2023 | 29 May 2024 | CIDCO of Maharashtra Ltd. | Project page |
Documents42
3 documents held by Deedo, 39 filings listed on MahaRERA's project page
Show all 42 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN - P-1 - S-36-1.pdf · uploaded 23 Aug 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - EWS - R - 6-1.pdf · uploaded 23 Aug 2019Source
- 2 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - EWS - R - 8-1.pdf · uploaded 23 Aug 2019Source
- 3 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - LIG - C-R - 12-1.pdf · uploaded 23 Aug 2019Source
- 4 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - LIG - R - 6-1-111.pdf · uploaded 23 Aug 2019Source
- 5 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - LIG - R - 6-11.pdf · uploaded 23 Aug 2019Source
- 6 Building Plan Approval / NA Order for plotted developmentFLOOR PLAN - LIG - R - 12-1.pdf · uploaded 23 Aug 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCC-1.pdf · uploaded 23 Aug 2019Source
- 1 Declaration in FORM BAffidavit cum Declaration - CE(NM)-1.pdf · uploaded 23 Aug 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Project Cost Certificate-1.pdf · uploaded 23 Aug 2019Source
- 1 Proforma of Allotment letterAGREEMENT FOR SALE Rera Plot 1 Sector 36-converted.pdf · uploaded 23 Aug 2019Source
- 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 23 Aug 2019Source
- 1 PAN CardPAN CARD CIDCO.pdf · uploaded 17 Jun 2021Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate Plot No 1 Sector 36 Taloja p.pdf · uploaded 25 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2019_20__P_36_1.pdf · uploaded 29 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2020_21__P_36_1.pdf · uploaded 29 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2021_22__P_36_1.pdf · uploaded 29 May 2023Source
- 1 Disclosure of sold/ booked inventoryMahaRERA inventory details plot 01 sector 36 taloja.pdf · uploaded 29 May 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Sector 36 plot No 1 2022-2023.pdf · uploaded 12 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Sector 36 plot No 1 2020-2021.pdf · uploaded 12 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Sector 36 plot No 1 2021-2022.pdf · uploaded 12 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Sector 36 plot No 1 2022-2023.pdf · uploaded 12 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P 1 sec 36 Form 2A 2022 23.pdf · uploaded 17 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 2023-24 Plot No 1 Sector 36 Taloja.pdf · uploaded 7 May 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC-PLOT-1 SEC-36 TALOJA CIDCO.pdf · uploaded 7 May 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion certificate plot 1 , sect 36, taloja.pdf · uploaded 15 May 2024Source
- 48 Architect’s Certificate on Completion of Project (Form 4)36-1 FORM-4.pdf · uploaded 28 May 2024Source
Technical
- DocumentLAYOUT PLAN - P-1 - S-36-1.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - EWS - R - 6-1.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - EWS - R - 8-1.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - LIG - C-R - 12-1.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - LIG - R - 6-1-111.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - LIG - R - 6-11.pdf · uploaded 23 Aug 2019Source
- DocumentFLOOR PLAN - LIG - R - 12-1.pdf · uploaded 23 Aug 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Address
- 1, Proposed 30 m wide road, Pendhar VillagePIN 410208
- Village
- Pendhar, Panvel taluka
- Land area for this project
- 37,193 sq m (4,00,344 sq ft)
- Permissible built-up area
- 75,898 sq m (8,16,957 sq ft)
- Sanctioned built-up area
- 75,898 sq m (8,16,957 sq ft)
- Recreational open space
- 5,683 sq m (61,171 sq ft)
- Designated bank account
- 220
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
1
Boundaries
- North
- Proposed 30 m wide road
- South
- Plot No 2 Sector 36
- East
- 24 m wide road
- West
- Proposed 30 m wide road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mr Tushar Prakash Tikhe | — |
| Chartered accountant | Chandrashekhar Biwalkar CAO | — |
| Engineer | S K Chotalia | — |
| Other | B G Shirke CTPL | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Pendhar
- Bat-Ha ResidencyRERA P52000079868
- Shree Shankar PalaceRERA P52000056096
- Hd PrideRERA P52000055238
- Rishikesh HeightsRERA P52000026899
- Plot 1 Sector 34 TalojaRERA P52000022174
- Plo t 2 Sector 36 TalojaRERA P52000022173
- Plot 6, Sector 34, TalojaRERA P52000022171
- Satyam ImperiaRERA P52000021355
All 15 projects in Pendhar · Compare Plot 1 Sector 36 Taloja with another project