Pendhar, Raigarh
Deedo IDDL-RAI-PENDHAR10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects15
Registrations15
Completion still due213 past their date
Median extension12 months60% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
15 MahaRERA registrations in Pendhar
2 extended, not yet due13 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Pendhar
15 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Bat-Ha ResidencyAnanda Buildstones LLP | Due Apr 2028, extended 4 mo | — | — |
| Shree Shankar PalaceManoj Omprakash Jaiswal | Completed | — | — |
| Hd PrideHd Builders & Developers | Due Jul 2027, extended 4 mo | — | 43% |
| Rishikesh HeightsRishikesh Enterprises | Completed | — | 84% |
| Plot 1 Sector 34 TalojaCIDCO of Maharashtra Ltd. | Completed, extended 1 yr | — | — |
Nearby: other villages in Panvel
Most active promoters
- Cidco Of Maharashtra Ltd4 projects
- City And Industrial Development Corporation Of Maharashtra Limited3 projects
- Aakar Developers1 project
- Ananda Buildstones LLP1 project
- Hd Builders & Developers1 project
- Manoj Omprakash Jaiswal1 project
- Rajesh Dharamvir Gulati1 project
- Rd Homes1 project
- Rishikesh Enterprises1 project
- Santosh Ramchandra Karavkar1 project
Pendhar, in questions
How many projects in Pendhar run late?
10 in 10 MahaRERA registrations (15 of 15): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Pendhar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology