Cidco Of Maharashtra Ltd
Deedo IDDD-NF9BOf 6 registrations whose promised date has arrived, 1 kept it (17%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
5 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Plot 1 Sector 10 GHANSOLIP51700017366 | Ghansoli | Certificate Signed | 30 Jun 2021 | 30 Sep 2022 | +15 mo |
| Plot 2 Sector Sector 10 GHANSOLIP51700017421 | Ghansoli | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | On date |
| Plot 6, Sector 34, TalojaP52000022171 | Pendhar | Certificate Signed | 30 May 2023 | 29 May 2024 | +12 mo |
| Plo t 2 Sector 36 TalojaP52000022173 | Pendhar | Certificate Signed | 30 May 2023 | 29 May 2024 | +12 mo |
| Plot 1 Sector 34 TalojaP52000022174 | Pendhar | Certificate Signed | 30 May 2023 | 29 May 2024 | +12 mo |
| Plot 1 Sector 36 TalojaP52000022182 | Pendhar | Certificate Signed | 30 May 2023 | 29 May 2024 | +12 mo |
Cidco Of Maharashtra Ltd, in questions
Does Cidco Of Maharashtra Ltd finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 1 kept it (17%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Cidco Of Maharashtra Ltd registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 6 completed on MahaRERA.
Does Cidco Of Maharashtra Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.