9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects10
Registrations14some projects hold several
Completion still due95 past their date
Median extension4 months71% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

14 MahaRERA registrations in Palaspe

2 not yet due7 extended, not yet due5 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Palaspe

10 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
La Mer OneLa Mer Homes LLPDue Jul 2031, extended 4 mo——
Blue HeavenVaradvinayak DevelopersDue Apr 2027, extended 4 mo——
Arihant Aspire Phase IIIArihant Abode LimitedDue Apr 2032, extended 4 mo—56%
Sai Greens C WingRekha Subhash JagdaleDue Dec 2026——
Krishna EnclaveS P Construction1 yr 5 mo late—50%
All 10 projects →
Palaspe market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Arihant Abode Limited2 projects
  2. Rekha Subhash Jagdale2 projects
  3. La Mer Homes LLP1 project
  4. La Mer Homes LLP1 project
  5. Maitree Builders1 project
  6. Phoenix Developers1 project
  7. S P Construction1 project
  8. Varadvinayak Developers1 project
  9. Vision Realtors1 project

Palaspe, in questions

How many projects in Palaspe run late?

9 in 10 MahaRERA registrations (12 of 14): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Palaspe by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology