RERA projects in Owe

7 projects under 7 MahaRERA registrations, registered 2017–2025. 57% have a completion date extended beyond the one promised.

7RERA projects
7Registrations
1Completion still due6 past their completion date
6 monthsMedian extension beyond promised date57% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20192
20200
20210
20220
20230
20240
20251

Projects in Owe

7 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sai PrernaParadise Infracon Private LimitedP520000794426 Mar 202530 Dec 2030—Not yet due0
Sai IconParadise Infra-con Pvt LtdP520000231564 Dec 201930 Dec 202414 May 2025Extended 5 mo0
Sai AaradhyaOm Sai ConstructionP520000215729 Jul 201928 Dec 202430 Jun 2025Extended 6 mo0
Sai SymphonyParadise Infracon Private LimitedP520000170444 Jul 201830 Dec 202331 Mar 2025Extended 15 mo1
Siddhi BelezzaSiddhitapaswi BuildtechP5200001055813 Nov 201731 Dec 2017—Promised date passed0
Keshav WindsWindfield Stocks And Securities Pvt LtdP5200000820918 Aug 201730 Apr 201831 Oct 2018Extended 6 mo0
Krishh CelestiaKrishh DevelopersP5200000616414 Aug 201731 Dec 2018—Promised date passed0

Other localities in Panvel

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Paradise Infracon Private Limited2 projects
  2. Krishh Developers1 project
  3. Om Sai Construction1 project
  4. Paradise Infra-con Pvt Ltd1 project
  5. Siddhitapaswi Buildtech1 project
  6. Windfield Stocks And Securities Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology