Navade, Raigarh

Deedo IDDL-RAI-NAVADE

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects15
Registrations15
Completion still due312 past their date
Median extension8 months27% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

15 MahaRERA registrations in Navade

2 not yet due1 extended, not yet due12 past even the latest date

Extended registrations moved their completion date by a median of 8 months.

Projects in Navade

15 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shree NiketanGns GlobalDue Apr 2028, extended 4 mo——
Maitri ResidencyShree Ganesh Builders And DevelopersDue Dec 2026——
Sai Vishwa ResidencyWalmik Raghunath KhairnarDue Dec 2026—16%
Maya ResidencyMajidunnisha Akram ManiharCompleted, extended 3 mo—79%
Shiv Shankar CornerSuresh Shivshankar SharmaCompleted—52%
All 15 projects →
Navade market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Suresh Shivshankar Sharma2 projects
  2. Walmik Raghunath Khairnar2 projects
  3. Arss Ravechi Ratna Developers1 project
  4. Dev Homes1 project
  5. Euro Reality1 project
  6. Girish Krushna Khutarkar1 project
  7. Gns Global1 project
  8. K K Group Builders And Developers1 project
  9. Majidunnisha Akram Manihar1 project
  10. Nilesh Naik1 project

Navade, in questions

How many projects in Navade run late?

9 in 10 MahaRERA registrations (13 of 15): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Navade by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology