RERA projects in Morbe
2 projects under 2 MahaRERA registrations, registered 2017–2017. 100% have a completion date extended beyond the one promised.
2RERA projects
2Registrations
0Completion still due2 past their completion date
33 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
Projects in Morbe
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sahakar Dwarka 2Megha Enterprises | P52000005452 | 11 Aug 2017 | 30 Jun 2021 | 31 Dec 2025 | Extended 54 mo | 0 |
| Sahakar Dwarka ISanket Homes | P52000002292 | 31 Jul 2017 | 30 Jun 2018 | 30 Jun 2019 | Extended 12 mo | 0 |
Other localities in Panvel
- Ulawe678 projects
- Vadghar (Ct)421 projects
- Panvel301 projects
- Wahal299 projects
- Karanjade250 projects
- Taloje Panchnad151 projects
- Dapoli142 projects
- Kharghar137 projects
- Kamothe86 projects
- New Panvel74 projects
- Kalamboli58 projects
- Taloje Majkur43 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Megha Enterprises1 project
- Sanket Homes1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology