Skip to content

Mahodar, Raigarh

Deedo IDDL-RAI-MAHODAR

7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1
Registrations3some projects hold several
Completion still due21 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists

7 in 10 registrations run late here

3 MahaRERA registrations in Mahodar

1 not yet due1 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Mahodar

1 project registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Arihant AmishaArihant Aashiyana Private LimitedCompleted, extended 4 mo—68%
Mahodar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Arihant Aashiyana Private Limited1 project
  2. Arihant Aashiyana Private Limited1 project

Mahodar, in questions

How many projects in Mahodar run late?

7 in 10 MahaRERA registrations (2 of 3): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Mahodar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology