9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects14
Registrations16some projects hold several
Completion still due97 past their date
Median extension8 months63% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

16 MahaRERA registrations in Karade Kh.

2 not yet due7 extended, not yet due7 past even the latest date

Extended registrations moved their completion date by a median of 8 months.

Projects in Karade Kh.

14 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Vista Harmony Phase 2Divine GroupDue Apr 2031, extended 4 mo——
Dhoondiraj Hotels Pvt LtdPavan Mahatma DevalkarDue Apr 2027, extended 4 mo—60%
Vista HarmonyDivine GroupDue Dec 2026——
Kricon PalaciaKricon Homes LLPDue Jun 2028—26%
Cj GreensC J EstatesDue Apr 2027, extended 4 mo—14%
All 14 projects →
Karade Kh. market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Megaplex Properties Llp2 projects
  2. C J Estates1 project
  3. Deep Sagar Enterprises1 project
  4. Divine Group1 project
  5. Divine Group1 project
  6. Emperia Realty1 project
  7. Heera Siddhi Homes Llp1 project
  8. Kricon Homes LLP1 project
  9. Pavan Mahatma Devalkar1 project
  10. Qualcon Ecostar Realty Llp1 project

Karade Kh., in questions

How many projects in Karade Kh. run late?

9 in 10 MahaRERA registrations (14 of 16): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Karade Kh. by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology