7 projects under 7 MahaRERA registrations, registered 2017–2023. 29% have a completion date extended beyond the one promised.

7RERA projects
7Registrations
1Completion still due6 past their completion date
35 monthsMedian extension beyond promised date29% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20180
20192
20202
20210
20220
20231

Projects in Derawali

7 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Tejas NeelkamalTejas Sangram PatilP5200005056721 Apr 202331 Dec 2027—Not yet due0
Nirmal Residency -IIAnil Vishnu BhoirP5200002770031 Dec 202030 Jun 202230 Apr 2026Extended 46 mo0
Nirmal PoojaNeelkamal Builders Private LimitedP5200002683828 Oct 202030 May 2024—Promised date passed0
Venkat ResidencyJagdeshappa Hanumanthappa GoudarP520000197325 Mar 201930 Dec 2023—Promised date passed0
Nirmal GaneshNeelkamal Builders Private LimitedP5200001925014 Jan 201930 Dec 2022—Promised date passed0
Shakti ResidencyShiv Shakti DevelopersP5200001097331 Aug 201730 Oct 201830 Oct 2020Extended 24 mo0
Balaji Residencyom sai homes creatorsP520000032965 Aug 201730 Dec 2020—Promised date passed0

Other localities in Panvel

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Neelkamal Builders Private Limited2 projects
  2. Anil Vishnu Bhoir1 project
  3. Jagdeshappa Hanumanthappa Goudar1 project
  4. om sai homes creators1 project
  5. Shiv Shakti Developers1 project
  6. Tejas Sangram Patil1 project