10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects2
Registrations2
Completion still due20 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

2 MahaRERA registrations in Bhanvaj

2 extended, not yet due

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhanvaj

2 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Adinath HeightsAdhinath Builders And DevelopersDue Apr 2029, extended 4 mo——
Suprabha HarmonySuprabha Developers Private LimitedDue Apr 2028, extended 4 mo——
Bhanvaj market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Adhinath Builders And Developers1 project
  2. Suprabha Developers Private Limited1 project

Bhanvaj, in questions

How many projects in Bhanvaj run late?

10 in 10 MahaRERA registrations (2 of 2): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhanvaj by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology