Residential / Group Housing · 1 building · 87 unitsRERA PR1260002501334

Prathamaa

Deedo IDDP-PUN-7E62

It is due for completion in Dec 2028, with no extension on record; no MahaRERA orders on record; 15% of its units are booked.

Yawalewadi, Pune 411048 · Property rates in Yawalewadi · by Yashodhan Associates · 40% of its projects kept the RERA date

DeliveryDue Dec 2028No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales15% booked13 of 87 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2028, with no extension on record

  • This projectRegistered 27 Oct 2025, completion promised 31 Dec 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1260002501334
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR126000250133427 Oct 202531 Dec 202831 Dec 2028Yashodhan AssociatesProject page
Documents37

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCO PAN.pdf · uploaded 3 Oct 2025Source

Legal

  • Others7 12.pdf · uploaded 3 Oct 2025Source
  • Declaration Form Bform b prathama.pdf · uploaded 3 Oct 2025Source
  • Declaration Form B7 12.pdf · uploaded 3 Oct 2025Source
  • Declaration Form BS NO2 YEOLEWADI SALE DEED.pdf · uploaded 3 Oct 2025Source
  • OthersAnnexture A DIS INT N.pdf · uploaded 4 Oct 2025Source
  • Othersdis int namita mam.pdf · uploaded 13 Oct 2025Source
Show all 37 documentsShow fewer documents

Legal

  • Declaration Form BLEGAL TITLE PRATHMA.pdf · uploaded 17 Oct 2025Source

Migrated

  • Withdrawal Update Form 1Withdrawal Update Form 1 · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 1Withdrawal Update Form 1 · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 2form 2 dec 25.pdf · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 2form 2 dec 25.pdf · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 3form 3 dec 25 prathamaa1.pdf · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 3form 3 dec 25 prathamaa1.pdf · uploaded 9 Jan 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 2form 2 dec 25.pdf · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 3form 3 dec 25 prathamaa1.pdf · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 1PRATHAMAAA FORM 1.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2form 2 prathamaa.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1Prathma Form 1 June-26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2form 2 prathama jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3form 3 for prathma jun 26.pdf · uploaded 20 Jul 2026Source
  • Form 2A (FY 2025-2026)2A PRATHAMA 25-26.pdf · uploaded 13 Aug 2026Source
  • Form 5 (FY 2025-2026)form 5 prathamaa 25-26.pdf · uploaded 13 Aug 2026Source

Technical

  • DocumentPlan-01.pdf · uploaded 3 Oct 2025Source
  • DocumentPlan-02.pdf · uploaded 3 Oct 2025Source
  • DocumentPlan-03.pdf · uploaded 3 Oct 2025Source
  • OthersFORM 2.pdf · uploaded 4 Oct 2025Source
  • OthersFORM-1_page-0001.pdf · uploaded 6 Oct 2025Source
  • DocumentAXX-A DIS CUM UNDERTAKING_page-0001.pdf · uploaded 7 Oct 2025Source
  • DocumentPLAN 01.pdf · uploaded 10 Jan 2026Source
  • DocumentPLAN 3.pdf · uploaded 10 Jan 2026Source
  • Document2 PLAN_compressed.pdf · uploaded 10 Jan 2026Source

Technical (Architect)

  • DocumentPrathma Form 1 June-26.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • Documentform 2 prathama jun 26.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 2/3/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—87 units in all
Address
YewalewadiPIN 411048
Village
Yawalewadi, Haveli taluka
Land area for this project
2,800 sq m (30,139 sq ft)
Permissible built-up area
7,059 sq m (75,982 sq ft)
Sanctioned built-up area
7,058 sq m (75,972 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
226
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 2/3/1

Land as published on MahaRERA's project page

SURVEY NO 2/3/1

Boundaries

North
15 mtr DP Road
South
Laxman Dandekar S No 2 (P)
East
9 mtr DP ROAD
West
Yashwant Nande S No 2 (P)

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking87 units

87 units registered

— · 87 units
TypeCarpet areaUnits
——87

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantSanjay Somani—
EngineerArjun Kanoji—

Source: MahaRERA project page. Contact details are not shown.