Yashodhan Associates
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
60%Kept RERA date3 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Dwarika NagariP52100002029 | Kondhwa Bk | 2017 | Not reported | 31 Dec 2019 | — | On date |
| Devayani ResidencyP52100002412 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Mahaveer DarshanP52100004901 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2024 | 31 Dec 2024 | On date |
| Mahaveer ResidencyP52100004257 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2017 | 31 Dec 2018 | +12 months |
| Mahaveer DelightP52100007439 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Yashodhan JubilationPM1260002501062 | Yawalewadi | 2025 | Not reported | 31 Mar 2028 | — | On date |
| PrathamaaPR1260002501334 | Yawalewadi | 2025 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Devayani Residency (P52100002412).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology