Laxmi Avenue
Deedo IDDP-PUN-XD4BMahaRERA shows it completed; no MahaRERA orders on record; 73% of its units are booked.
Wakad, Pune 411057 · Property rates in Wakad · by Laxman Saibana Mehetre
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 13 Feb 2020, completion promised 30 Jun 2024.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Building - A Residential17 floors · 90 units98% booked
- Building - B Commercial19 floors · 38 units13% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100024445
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100024445 | 13 Feb 2020 | 30 Jun 2024 | 30 Jun 2024 | Laxman Saibana Mehetre | Project page |
Documents116
1 document held by Deedo, 115 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD_LAXMAN MEHETRE.pdf · uploaded 30 Jan 2020Source
Legal
Migrated
- 1 PAN CardPANCARD_LAXMAN MEHETRE.pdf · uploaded 30 Jan 2020Source
- 1 Details of encumbrancesENCUMBRANCE CERTIFICATE_LAXMI AVENUE.pdf · uploaded 30 Jan 2020Source
- 1 Copy of Layout Approval (in case of layout)SANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
Show all 116 documentsShow fewer documents
Migrated
- 2 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 02.pdf · uploaded 30 Jan 2020Source
- 3 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 03.pdf · uploaded 30 Jan 2020Source
- 4 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 04.pdf · uploaded 30 Jan 2020Source
- 5 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 05.pdf · uploaded 30 Jan 2020Source
- 6 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 06.pdf · uploaded 30 Jan 2020Source
- 7 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 07.pdf · uploaded 30 Jan 2020Source
- 8 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 08.pdf · uploaded 30 Jan 2020Source
- 9 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 09.pdf · uploaded 30 Jan 2020Source
- 10 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
- 11 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 02.pdf · uploaded 30 Jan 2020Source
- 12 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 03.pdf · uploaded 30 Jan 2020Source
- 13 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 04.pdf · uploaded 30 Jan 2020Source
- 14 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 05.pdf · uploaded 30 Jan 2020Source
- 15 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 06.pdf · uploaded 30 Jan 2020Source
- 16 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 07.pdf · uploaded 30 Jan 2020Source
- 17 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 08.pdf · uploaded 30 Jan 2020Source
- 18 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 09.pdf · uploaded 30 Jan 2020Source
- 19 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 10.pdf · uploaded 30 Jan 2020Source
- 20 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 11.pdf · uploaded 30 Jan 2020Source
- 21 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 12.pdf · uploaded 30 Jan 2020Source
- 22 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 13.pdf · uploaded 30 Jan 2020Source
- 23 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 14.pdf · uploaded 30 Jan 2020Source
- 24 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 15.pdf · uploaded 30 Jan 2020Source
- 25 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 16.pdf · uploaded 30 Jan 2020Source
- 26 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN DRAWING - 17.pdf · uploaded 30 Jan 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE_LAXMI AVENUE.pdf · uploaded 30 Jan 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentREVISED COMMENCEMENT CERTIFICATE.pdf · uploaded 30 Jan 2020Source
- 1 Declaration in FORM BFORM-B - DECLARATION_LAXMI AVENUE.pdf · uploaded 30 Jan 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)L_S_Mehetre_Laxmi Avenue_Form-1.pdf · uploaded 30 Jan 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE_FORM NO-2_LAXMI AVENUE.pdf · uploaded 30 Jan 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE_FORM NO-3.pdf · uploaded 30 Jan 2020Source
- 1 Copy of the legal title reportSEARCH AND TITLE REPORT.pdf · uploaded 31 Jan 2020Source
- 1 Proforma of Allotment letterSAMPLE DRAFT LAXMI AVENUE.pdf · uploaded 1 Feb 2020Source
- 2 Proforma of Allotment letterALLOTMENT LETTER LAXMI AVENUE PROJECT.pdf · uploaded 7 Feb 2020Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - FORM - 1.pdf · uploaded 12 Sep 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE - FORM - 2.pdf · uploaded 12 Sep 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE - FORM - 3.pdf · uploaded 12 Sep 2020Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTICATE_Form 1.pdf · uploaded 31 Mar 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering Certificate.pdf · uploaded 31 Mar 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 31 Mar 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate FORM 1.pdf · uploaded 17 Jul 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 17 Jul 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 17 Jul 2021Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form_1.pdf · uploaded 26 Oct 2021Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 26 Oct 2021Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2021-21 Laxmi Avenue.pdf · uploaded 22 Feb 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate.pdf · uploaded 29 Apr 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 29 Apr 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 29 Apr 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Archotects Certificate.pdf · uploaded 21 Jul 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 21 Jul 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 21 Jul 2022Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 22 Oct 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineer Certificate.pdf · uploaded 22 Oct 2022Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 22 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 22 Oct 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentComplection Certificate Laxmi Avenue.pdf · uploaded 22 Oct 2022Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Architect Certificate.pdf · uploaded 19 Jan 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 19 Jan 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_CA Certificate.pdf · uploaded 19 Jan 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 21-22 Laxmi Avenue.pdf · uploaded 19 Jan 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Architect Certificate.pdf · uploaded 22 Apr 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 22 Apr 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3A CA Certificate.pdf · uploaded 22 Apr 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Laxmi Avenue A Building Society Registration Certificate (2).pdf · uploaded 22 Apr 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Jul 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 29 Jul 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 29 Jul 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 11 Nov 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Enginner Certificate.pdf · uploaded 11 Nov 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 A CA Certificate.pdf · uploaded 11 Nov 2023Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate Laxmi Avenue Commercial Building.pdf · uploaded 11 Nov 2023Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineer Certificate.pdf · uploaded 23 Feb 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 23 Feb 2024Source
- 1 Status of Conveyanceconveyance deed Laxmi Avenue A Building.pdf · uploaded 23 Feb 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Laxmi Avenue.pdf · uploaded 5 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Laxmi Avenue.pdf · uploaded 5 Mar 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Laxmi Avenue_Wakad_Form4.pdf · uploaded 2 Dec 2024Source
Technical
- DocumentSANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 02.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 03.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 04.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 05.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 06.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 07.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 08.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 09.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 01.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 02.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 03.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 04.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 05.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 06.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 07.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 08.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 09.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 10.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 11.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 12.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 13.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 14.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 15.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 16.pdf · uploaded 30 Jan 2020Source
- DocumentSANCTION PLAN DRAWING - 17.pdf · uploaded 30 Jan 2020Source
Technical (Architect)
- DocumentForm 1 Architect Certificate.pdf · uploaded 11 Nov 2023Source
Technical (Engineer)
- DocumentFORM 2 Engineer Certificate.pdf · uploaded 23 Feb 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 167/5, 167/6
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop, Office space128 units in all
- Address
- 167/5, 167/6, 167/7, Shankar Kalate Nagar Road, Near Pristine Prolife Phase IIIPIN 411057
- Village
- Wakad, Mulshi taluka
- Location
- 18.59605, 73.75925
- Land area for this project
- 5,900 sq m (63,507 sq ft)
- Permissible built-up area
- 10,517 sq m (1,13,208 sq ft)
- Sanctioned built-up area
- 10,517 sq m (1,13,208 sq ft)
- Recreational open space
- 500 sq m (5,382 sq ft)
- Designated bank account
- 212
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
167/5, 167/6, 167/7
Boundaries
- North
- By Land Bearing Survey No 167-2 P
- South
- By Land Bearing Survey No 167-9 P
- East
- By Land Bearing Survey No 168-2 168-3 And 168-4 P
- West
- By Land Bearing Survey No 167 P
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking128 units
93 of 128 units booked (73%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building - A Residential | 1BHK | 50.67 sq m · 545 sq ft | 5 | 5 |
| Building - A Residential | 1BHK | 50.83 sq m · 547 sq ft | 5 | 5 |
| Building - A Residential | 1BHK | 50.97 sq m · 549 sq ft | 10 | 10 |
| Building - A Residential | 2BHK | 71.42 sq m · 769 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 71.56 sq m · 770 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 71.83 sq m · 773 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 71.95 sq m · 774 sq ft | 6 | 6 |
| Building - A Residential | 2BHK | 72.17 sq m · 777 sq ft | 1 | 1 |
Show all 53 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building - A Residential | 2BHK | 72.27 sq m · 778 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 72.29 sq m · 778 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 72.86 sq m · 784 sq ft | 1 | 1 |
| Building - A Residential | 2BHK | 73.1 sq m · 787 sq ft | 1 | 1 |
| Building - A Residential | 2BHK | 73.27 sq m · 789 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 73.38 sq m · 790 sq ft | 6 | 6 |
| Building - A Residential | 2BHK | 74.23 sq m · 799 sq ft | 1 | 1 |
| Building - A Residential | 2BHK | 77.11 sq m · 830 sq ft | 1 | 1 |
| Building - A Residential | 2BHK | 77.12 sq m · 830 sq ft | 4 | 4 |
| Building - A Residential | 2BHK | 77.55 sq m · 835 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 77.81 sq m · 838 sq ft | 5 | 5 |
| Building - A Residential | 2BHK | 78.42 sq m · 844 sq ft | 5 | 5 |
| Building - A Residential | Shop | 22.91 sq m · 247 sq ft | 1 | 1 |
| Building - A Residential | Shop | 27.09 sq m · 292 sq ft | 1 | 0 |
| Building - A Residential | Shop | 28.4 sq m · 306 sq ft | 1 | 0 |
| Building - A Residential | Shop | 32.48 sq m · 350 sq ft | 1 | 1 |
| Building - B Commercial | Office space | 95.99 sq m · 1,033 sq ft | 3 | 0 |
| Building - B Commercial | Office space | 106.07 sq m · 1,142 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 109.39 sq m · 1,177 sq ft | 1 | 1 |
| Building - B Commercial | Office space | 112.99 sq m · 1,216 sq ft | 2 | 0 |
| Building - B Commercial | Office space | 112.99 sq m · 1,216 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 118.67 sq m · 1,277 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 122.09 sq m · 1,314 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 125.38 sq m · 1,350 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 125.4 sq m · 1,350 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 126.38 sq m · 1,360 sq ft | 1 | 1 |
| Building - B Commercial | Office space | 133.53 sq m · 1,437 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 134.48 sq m · 1,448 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 134.68 sq m · 1,450 sq ft | 2 | 0 |
| Building - B Commercial | Office space | 135.67 sq m · 1,460 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 138.77 sq m · 1,494 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 148.06 sq m · 1,594 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 148.28 sq m · 1,596 sq ft | 3 | 1 |
| Building - B Commercial | Office space | 149.23 sq m · 1,606 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 156.71 sq m · 1,687 sq ft | 2 | 1 |
| Building - B Commercial | Office space | 158.35 sq m · 1,704 sq ft | 1 | 1 |
| Building - B Commercial | Office space | 161.68 sq m · 1,740 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 161.68 sq m · 1,740 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 164.81 sq m · 1,774 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 170.95 sq m · 1,840 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 170.99 sq m · 1,841 sq ft | 2 | 0 |
| Building - B Commercial | Office space | 184.53 sq m · 1,986 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 197.05 sq m · 2,121 sq ft | 2 | 0 |
| Building - B Commercial | Office space | 223.02 sq m · 2,401 sq ft | 1 | 0 |
| Building - B Commercial | Office space | 236.22 sq m · 2,543 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Solespace | — |
| Chartered accountant | Madhukar T Thorat | — |
| Engineer | Sanjay Raosaheb Bangar | — |
| Other | G A Bhilare Consultants Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Wakad
- Maaisa GenesisRERA PR1260002602651
- PEBBLES BUSINESS BAY IT BuildingRERA PC1260002602561
- Wakad New ProjectRERA PR1260002602193
- Truspace Prima AltioraRERA PR1260002602057
- Arham PalazzoRERA PM1260002602013
- Austin AurusRERA PM1260002601438
- Jaijinendra NilayRERA PM1260002601417
- The Vantage A, B, C & DRERA PR1260002601066
All 314 projects in Wakad · Compare Laxmi Avenue with another project