Individual promoter · first RERA registration 2017

Laxman Saibana Mehetre

Deedo IDDD-XJXS

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 43 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay43 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Laxmi HorizonP52100000397PunawaleCertificate Signed30 Sep 201930 Apr 2023+43 mo
Laxmi AvenueP52100024445WakadCertificate Signed30 Jun 202430 Jun 2024On date

Laxman Saibana Mehetre, in questions

Does Laxman Saibana Mehetre finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 43 mo late. Across Maharashtra, 73% kept their date.

How many projects has Laxman Saibana Mehetre registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Laxman Saibana Mehetre have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology