Laxman Saibana Mehetre
Individual promoter · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+22 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Laxmi HorizonP52100000397 | Punawale | 2017 | Not reported | 30 Sep 2019 | 30 Apr 2023 | +43 months |
| Laxmi AvenueP52100024445 | Wakad | 2020 | Not reported | 30 Jun 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 43 months, for Laxmi Horizon (P52100000397).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
