Laxman Saibana Mehetre
Deedo IDDD-XJXSOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 43 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Laxmi HorizonP52100000397 | Punawale | Certificate Signed | 30 Sep 2019 | 30 Apr 2023 | +43 mo |
| Laxmi AvenueP52100024445 | Wakad | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
Laxman Saibana Mehetre, in questions
Does Laxman Saibana Mehetre finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 43 mo late. Across Maharashtra, 73% kept their date.
How many projects has Laxman Saibana Mehetre registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Laxman Saibana Mehetre have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.