Suryam 89
Deedo IDDP-PUN-R89DCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.
Wagholi, Pune 412207 · Property rates in Wagholi · by Uptitan Infra Pvt Ltd
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 1 Aug 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100080890
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100080890 | 1 Aug 2025 | 31 Dec 2028 | 30 Apr 2029 | Uptitan Infra PVT LTD | Project page |
Documents168
1 document held by Deedo, 167 filings listed on MahaRERA's project page
Finance
- PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
Show all 168 documentsShow fewer documents
Finance
- Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
Legal
- Declaration Form BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- Declaration Form BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- Declaration Form BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- Declaration Form BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- Legal Title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- Legal Title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- Legal Title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- Legal Title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- Legal Title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- Legal Title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- Legal Title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- Legal Title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
Migrated
- 1 PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- 1 a Details of encumbrances concerned to FinanceLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Declaration in FORM BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Ankit .pdf · uploaded 25 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Sachin .pdf · uploaded 25 Apr 2025Source
- 1 PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- 1 a Details of encumbrances concerned to FinanceLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Declaration in FORM BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Ankit .pdf · uploaded 25 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Sachin .pdf · uploaded 25 Apr 2025Source
- 1 PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- 1 a Details of encumbrances concerned to FinanceLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Declaration in FORM BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Ankit .pdf · uploaded 25 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Sachin .pdf · uploaded 25 Apr 2025Source
- 1 PAN CardUptitan Infra PAN.pdf · uploaded 25 Apr 2025Source
- 1 a Details of encumbrances concerned to FinanceLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Declaration in FORM BUptitan From B Owner .pdf · uploaded 25 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalLegal And Finance Uptitan.pdf · uploaded 25 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Ankit .pdf · uploaded 25 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsUptitan Annexure A Other Real Estate Sachin .pdf · uploaded 25 Apr 2025Source
- 1 Proforma of Allotment letterUptitan Allotment Letter.pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterUptitan Declaration Deviation Allotment .pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementUptitan Deviation Agreement Declaration .pdf · uploaded 26 Apr 2025Source
- 1 Proforma of Allotment letterUptitan Allotment Letter.pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterUptitan Declaration Deviation Allotment .pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementUptitan Deviation Agreement Declaration .pdf · uploaded 26 Apr 2025Source
- 1 Proforma of Allotment letterUptitan Allotment Letter.pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterUptitan Declaration Deviation Allotment .pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementUptitan Deviation Agreement Declaration .pdf · uploaded 26 Apr 2025Source
- 1 Proforma of Allotment letterUptitan Allotment Letter.pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterUptitan Declaration Deviation Allotment .pdf · uploaded 26 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementUptitan Deviation Agreement Declaration .pdf · uploaded 26 Apr 2025Source
- 1 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 29 Apr 2025Source
- 1 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 29 Apr 2025Source
- 1 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 29 Apr 2025Source
- 1 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 29 Apr 2025Source
- 1 Copy of the legal title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- 1 Copy of Layout Approval (in case of layout)Plan Wagholi.pdf · uploaded 3 May 2025Source
- 1 Copy of the legal title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- 1 Copy of Layout Approval (in case of layout)Plan Wagholi.pdf · uploaded 3 May 2025Source
- 1 Copy of the legal title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- 1 Copy of Layout Approval (in case of layout)Plan Wagholi.pdf · uploaded 3 May 2025Source
- 1 Copy of the legal title reportRERA Search Report.pdf · uploaded 3 May 2025Source
- 1 Copy of Layout Approval (in case of layout)Plan Wagholi.pdf · uploaded 3 May 2025Source
- 2 Copy of the legal title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- 2 a Details of encumbrances concerned to FinanceDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 CERSAI detailsUndertaking Maha RERA.pdf · uploaded 21 Jun 2025Source
- 2 b Details of encumbrances concerned to LegalDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure For Secured unsecured.pdf · uploaded 21 Jun 2025Source
- 2 Copy of the legal title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- 2 a Details of encumbrances concerned to FinanceDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 CERSAI detailsUndertaking Maha RERA.pdf · uploaded 21 Jun 2025Source
- 2 b Details of encumbrances concerned to LegalDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure For Secured unsecured.pdf · uploaded 21 Jun 2025Source
- 2 Copy of the legal title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- 2 a Details of encumbrances concerned to FinanceDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 CERSAI detailsUndertaking Maha RERA.pdf · uploaded 21 Jun 2025Source
- 2 b Details of encumbrances concerned to LegalDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure For Secured unsecured.pdf · uploaded 21 Jun 2025Source
- 2 Copy of the legal title reportFormat A Search Report.pdf · uploaded 21 Jun 2025Source
- 2 a Details of encumbrances concerned to FinanceDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 CERSAI detailsUndertaking Maha RERA.pdf · uploaded 21 Jun 2025Source
- 2 b Details of encumbrances concerned to LegalDeclaration Finance and Encumbrance.PDF · uploaded 21 Jun 2025Source
- 1 Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure For Secured unsecured.pdf · uploaded 21 Jun 2025Source
- 2 Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 7 Jul 2025Source
- 2 Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 7 Jul 2025Source
- 2 Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 7 Jul 2025Source
- 2 Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- 2 Proforma of Agreement for saleAgreement for Sale Uptitan for Rera.pdf · uploaded 7 Jul 2025Source
- 1 Declaration about Commencement CertificateFormat D Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about Commencement CertificateFormat D Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about Commencement CertificateFormat D Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about Commencement CertificateFormat D Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Uptitan.pdf · uploaded 11 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPTTITAN.pdf · uploaded 26 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPTTITAN.pdf · uploaded 26 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPTTITAN.pdf · uploaded 26 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)UPTTITAN.pdf · uploaded 26 Jul 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentUptitan Infra Updated CC 18-07-2025.pdf · uploaded 29 Jul 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentUptitan Infra CC 18-02-2025.pdf · uploaded 29 Jul 2025Source
- 1 Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Suryam 89.pdf · uploaded 29 Jul 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentUptitan Infra Updated CC 18-07-2025.pdf · uploaded 29 Jul 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentUptitan Infra CC 18-02-2025.pdf · uploaded 29 Jul 2025Source
- 1 Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Suryam 89.pdf · uploaded 29 Jul 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentUptitan Infra Updated CC 18-07-2025.pdf · uploaded 29 Jul 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentUptitan Infra CC 18-02-2025.pdf · uploaded 29 Jul 2025Source
- 1 Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Suryam 89.pdf · uploaded 29 Jul 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentUptitan Infra Updated CC 18-07-2025.pdf · uploaded 29 Jul 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentUptitan Infra CC 18-02-2025.pdf · uploaded 29 Jul 2025Source
- 1 Other – FinanceDeclaration .pdf · uploaded 29 Jul 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Suryam 89.pdf · uploaded 29 Jul 2025Source
- Withdrawal Update Form 1Form 1 Architect Certificate Uptitan infra.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 2From 2 Uptitan infra.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 3Form 3-Q2-25-26.pdf · uploaded 30 Oct 2025Source
Technical
- DocumentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentSanction Plan 2 Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentPlan Wagholi.pdf · uploaded 3 May 2025Source
- DocumentPlan Wagholi.pdf · uploaded 3 May 2025Source
- DocumentPlan Wagholi.pdf · uploaded 3 May 2025Source
- DocumentPlan Wagholi.pdf · uploaded 3 May 2025Source
- Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- Other – TechnicalANNEXURE A Declaration.pdf · uploaded 21 Jun 2025Source
- Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
- Other – TechnicalDeclaration POA POA.pdf · uploaded 7 Jul 2025Source
Technical (Architect)
- DocumentForm 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1 RERA Architect's application Wagholi.pdf · uploaded 25 Apr 2025Source
- DocumentForm 1 Architect Certificate Uptitan infra.pdf · uploaded 30 Oct 2025Source
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Gat No 849 to 854 Plot No 89
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1RK, 2BHK, LO Rehab 2 BHK, LO Rehab2 BHK20 units in all
- Address
- Gat No 849 to 854 Plot No 89, JSPM Road, Radheshwari SocietyPIN 412207
- Village
- Wagholi, Haveli taluka
- Location
- 18.58795, 74.01142
- Land area for this project
- 996 sq m (10,721 sq ft)
- Permissible built-up area
- 2,385 sq m (25,673 sq ft)
- Sanctioned built-up area
- 1,751 sq m (18,848 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gat No 849 to 854 Plot No 89
Boundaries
- North
- 9 Mtr Road
- South
- Plot No 90
- East
- 9 Mtr Road
- West
- Compound Wall
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
0 of 20 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 40.51 sq m · 436 sq ft | 1 | 0 |
| 1RK | 42.77 sq m · 460 sq ft | 1 | 0 |
| 2BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| 2BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| 2BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| 2BHK | 78.69 sq m · 847 sq ft | 1 | 0 |
| 2BHK | 78.69 sq m · 847 sq ft | 1 | 0 |
| 2BHK | 78.69 sq m · 847 sq ft | 1 | 0 |
Show all 20 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 93.58 sq m · 1,007 sq ft | 1 | 0 |
| 2BHK | 93.58 sq m · 1,007 sq ft | 1 | 0 |
| 2BHK | 93.58 sq m · 1,007 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 70.06 sq m · 754 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 70.06 sq m · 754 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 70.06 sq m · 754 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 72 sq m · 775 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 72 sq m · 775 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| LO Rehab 2 BHK | 76.32 sq m · 822 sq ft | 1 | 0 |
| LO Rehab2 BHK | 72 sq m · 775 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | PI Consultants Ingawale | — |
| Chartered accountant | Agrawal Oswal & Associates | — |
| Engineer | Eknath Ramchandra Yenpure | — |
| Engineer | Eknath Yenpure | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Wagholi
- Never Before Manjari Phase 1RERA PR1260002602570
- Ganga PavitraRERA PM1261012602430
- Rohan Yuva Bldg B & CRERA PC1260002602439
- The ElementRERA PM1260002602060
- Serene SpacesRERA PR1260002601339
- Omicron Tech ParkRERA PC1260002601259
- RTC Emerald SuitesRERA PR1260002601179
- T5E ApexRERA PR1260002601183
All 340 projects in Wagholi · Compare Suryam 89 with another project