Company or firm · first RERA registration 2025

Uptitan Infra Pvt Ltd

Deedo IDDD-S73B

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Suryam 89P52100080890WagholiCertificate Signed31 Dec 202830 Apr 2029+4 mo

Uptitan Infra Pvt Ltd, in questions

Does Uptitan Infra Pvt Ltd finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Uptitan Infra Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Uptitan Infra Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.