Deedo IDDL-PUN-VARALE-2

7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects3
Registrations3
Completion still due12 past their date
Median extension3 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists

7 in 10 registrations run late here

3 MahaRERA registrations in Varale

1 not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 3 months.

Projects in Varale

3 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
VighnahartaSharayu DevelopersDue Apr 2028——
Roshan One Wing CRahul Bhagwandas SanklaCompleted, extended 3 mo—47%
Roshan One Wing BRahul Bhagwandas SanklaCompleted—31%
Varale market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Rahul Bhagwandas Sankla2 projects
  2. Sharayu Developers1 project

Varale, in questions

How many projects in Varale run late?

7 in 10 MahaRERA registrations (2 of 3): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Varale by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology