Akshara Serenity
Deedo IDDP-PUN-PHXZIt is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 10% of its units are booked.
Tathwade, Pune 411057 · Property rates in Tathwade · by Garve Developers and Promoters
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2026, with no extension on record
- P52100046870Registered 14 Sep 2022, completion promised 1 Oct 2026.
- P52100051358Registered 8 Jun 2023, completion promised 31 Dec 2026.
1 extension certificate on record.
2 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- A Building7 floors · 28 units29% booked
- B Bldg5 floors · 28 units0% booked
- C Bldg5 floors · 21 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations2
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100046870 | 14 Sep 2022 | 1 Oct 2026 | 1 Oct 2026 | Garve Developers and Promoters | Project page |
| P52100051358 | 8 Jun 2023 | 31 Dec 2026 | 31 Dec 2026 | Garve Developers and Promoters | Project page |
Documents304
3 documents held by Deedo, 301 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
Show all 304 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardP52100046870 · GDP PAN CARD.pdf · uploaded 5 Aug 2022Source
- 1 Copy of the legal title reportP52100046870 · Format A (4)_compressed.pdf · uploaded 5 Aug 2022Source
- 1 a Details of encumbrances concerned to FinanceP52100046870 · ENCUMBRUNCES DECLARATION.pdf · uploaded 5 Aug 2022Source
- 1 b Details of encumbrances concerned to LegalP52100046870 · ENCUMBRUNCES DECLARATION.pdf · uploaded 5 Aug 2022Source
- 1 Copy of Layout Approval (in case of layout)P52100046870 · Layout Plan (2)_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100046870 · SANCTION PLAN A-6_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100046870 · CC_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Declaration about Commencement CertificateP52100046870 · FORMAT D COMMENCEMENT.pdf · uploaded 5 Aug 2022Source
- 1 Declaration in FORM BP52100046870 · Form B- Promoter_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · Tathwade Rera Letter_compressed.pdf · uploaded 5 Aug 2022Source
- 1 CERSAI detailsP52100046870 · CERSAI_Search_Report_200244066638_For_Asset_Based_Search_05_08_2022_15_17_15_726.pdf · uploaded 5 Aug 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · Final Form 3- Akshara Serenity_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Proforma of Allotment letterP52100046870 · Annexure I- Model copy of Allotment letter_compressed.pdf · uploaded 5 Aug 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100046870 · Format I- Declaration of Bank details.pdf · uploaded 5 Aug 2022Source
- 1 Deviation Report with respect to Allotment letterP52100046870 · Garve Developers- Deviation report of Allotment letter.pdf · uploaded 5 Aug 2022Source
- 2 Proforma of Allotment letterP52100046870 · Agreement uploaded 31 8 22.pdf · uploaded 9 Aug 2022Source
- 2 Copy of the legal title reportP52100046870 · Search title report (1)_compressed-Highlited.pdf · uploaded 18 Aug 2022Source
- 1 Deviation Report with respect to model copy of AgreementP52100046870 · Deviation Report - Agreement New.pdf · uploaded 3 Sep 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · Akshara Serenity A Building .pdf · uploaded 2 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · 3RD slab work completed 20-01-23.pdf · uploaded 2 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Akshara Serenity A Building .pdf · uploaded 2 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · Chandrakant Kale-5_compressed.pdf · uploaded 2 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryP52100046870 · sold inventory (1).pdf · uploaded 7 Feb 2023Source
- 1 PAN CardP52100051358 · 1 PAN Card.pdf · uploaded 22 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · Ca Certificate Form3.pdf · uploaded 31 Mar 2023Source
- 1 Copy of the legal title reportP52100051358 · Legal Title Report Format A.pdf · uploaded 10 Apr 2023Source
- 1 a Details of encumbrances concerned to FinanceP52100051358 · Encumbrance.pdf · uploaded 10 Apr 2023Source
- 1 b Details of encumbrances concerned to LegalP52100051358 · Encumbrance.pdf · uploaded 10 Apr 2023Source
- 1 Copy of Layout Approval (in case of layout)P52100051358 · Layout Main.pdf · uploaded 10 Apr 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100051358 · Layout Plan B.pdf · uploaded 10 Apr 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100051358 · Layout Plan C.pdf · uploaded 10 Apr 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100051358 · commensment certificate.pdf · uploaded 10 Apr 2023Source
- 1 Declaration about Commencement CertificateP52100051358 · Declaration of commencement.pdf · uploaded 10 Apr 2023Source
- 1 Declaration in FORM BP52100051358 · Form B Landowner.pdf · uploaded 10 Apr 2023Source
- 2 Declaration in FORM BP52100051358 · Form B- Promoter.pdf · uploaded 10 Apr 2023Source
- 1 CERSAI detailsP52100051358 · CERSAI_Search_Report_200265723407_For_Asset_Based_Search_10_04_2023_14_02_15_611 (1).pdf · uploaded 10 Apr 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP52100051358 · Annuexure A Subhum garve.pdf · uploaded 10 Apr 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsP52100051358 · Annuxure A- Akshay Sir.pdf · uploaded 10 Apr 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsP52100051358 · Annuxure A- Gaurav Mule.pdf · uploaded 10 Apr 2023Source
- 1 Proforma of Agreement for saleP52100051358 · Agreement for Sale.pdf · uploaded 10 Apr 2023Source
- 1 Proforma of Allotment letterP52100051358 · Model Allotment Letter_compressed.pdf · uploaded 10 Apr 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100051358 · Bank Account Declaration.pdf · uploaded 10 Apr 2023Source
- 1 Deviation Report with respect to Allotment letterP52100051358 · Deviation Report of Model Copy of allotment.pdf · uploaded 10 Apr 2023Source
- 1 Deviation Report with respect to model copy of AgreementP52100051358 · Deviation Of Agreement_compressed.pdf · uploaded 13 Apr 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · GARVE A BLDG.pdf · uploaded 22 Jun 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Akshara Serenity A f2.pdf · uploaded 22 Jun 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · AKSHARA SERENITY (A) f3_compressed.pdf · uploaded 30 Jun 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · AKSHARA SERENITY (A) f3_compressed.pdf · uploaded 30 Jun 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · AKSHARA SERENITY (A) f3_compressed.pdf · uploaded 30 Jun 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · Architect’s Certificate Sept.pdf · uploaded 12 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Engineer’s Certificate Oct.pdf · uploaded 12 Oct 2023Source
- 2 Disclosure of sold/ booked inventoryP52100046870 · Sold booked Mar.pdf · uploaded 12 Oct 2023Source
- 3 Disclosure of sold/ booked inventoryP52100046870 · Sold Booked June.pdf · uploaded 12 Oct 2023Source
- 4 Disclosure of sold/ booked inventoryP52100046870 · Sold booked Oct.pdf · uploaded 12 Oct 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · CA Certificate OCT.pdf · uploaded 12 Oct 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · CA Certificate OCT.pdf · uploaded 12 Oct 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · GARVE A BLDG.pdf · uploaded 21 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · akshara Serenity qu October 23.pdf · uploaded 21 Oct 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · AKSHARA SERENITY (A) f3_compressed.pdf · uploaded 21 Oct 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · A WING FORM 3_11zon.pdf · uploaded 27 Oct 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · Form 1.pdf · uploaded 6 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Form 2.pdf · uploaded 6 Jan 2024Source
- 5 Disclosure of sold/ booked inventoryP52100046870 · sold unsold.pdf · uploaded 6 Jan 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · Form 3_11zon (2).pdf · uploaded 6 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100051358 · Form 1.pdf · uploaded 11 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100051358 · Form 2.pdf · uploaded 11 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryP52100051358 · Sold unsold.pdf · uploaded 11 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · Form 3.pdf · uploaded 11 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100046870 · Akshara Serenity.pdf · uploaded 11 Mar 2024Source
- 2 Copy of Layout Approval (in case of layout)P52100051358 · 1 (6)_1_11zon.pdf · uploaded 15 Mar 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100051358 · 2 (4)_3_11zon.pdf · uploaded 15 Mar 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100051358 · 3 (1)_2_11zon.pdf · uploaded 15 Mar 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP52100051358 · 4 (1).pdf · uploaded 15 Mar 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP52100051358 · Com_4_11zon.pdf · uploaded 15 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Form2 march 2024.pdf · uploaded 23 Apr 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Form2 march 2024.pdf · uploaded 23 Apr 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · AKSHAR SERENITY CA Certificate_11zon.pdf · uploaded 23 Apr 2024Source
- 6 Disclosure of sold/ booked inventoryP52100046870 · Sold Unsold.pdf · uploaded 29 Apr 2024Source
- 2 Copy of Layout Approval (in case of layout)P52100046870 · Layout.pdf · uploaded 2 May 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100046870 · Floor plan_11zon.pdf · uploaded 2 May 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100046870 · Floor plan 2_11zon.pdf · uploaded 2 May 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP52100046870 · Floor plan 3_11zon.pdf · uploaded 2 May 2024Source
- 2 Declaration about Commencement CertificateP52100046870 · Commencemnt certificate_11zon.pdf · uploaded 2 May 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100051358 · signed F2.pdf · uploaded 29 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100051358 · signed f2a.pdf · uploaded 29 Jul 2024Source
- 2 Disclosure of sold/ booked inventoryP52100051358 · signed sold unsold.pdf · uploaded 29 Jul 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · signed F3_.pdf · uploaded 29 Jul 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP52100046870 · Com_compressed.pdf · uploaded 30 Jul 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100051358 · signed F2.pdf · uploaded 31 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryP52100051358 · signed sold unsold.pdf · uploaded 31 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · signed F3_.pdf · uploaded 31 Jul 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100046870 · Complition Certificate.pdf · uploaded 13 Dec 2024Source
- 1 Copy of Layout Approval (in case of layout)P52100051358 · LAYOUT_compressed.pdf · uploaded 24 Dec 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100051358 · CC_compressed (3).pdf · uploaded 24 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100051358 · 2_compressed.pdf · uploaded 24 Dec 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentP52100051358 · 3_compressed.pdf · uploaded 24 Dec 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP52100051358 · 4_compressed (1).pdf · uploaded 24 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100051358 · form 1.pdf · uploaded 13 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100051358 · F2 akshara serinity.pdf · uploaded 13 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100046870 · GetUserDocumentFileContent (49).pdf · uploaded 13 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · F3 (1)_compressed (1).pdf · uploaded 3 Mar 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · FORM-3(FY 24-25-Q2) (1)_compressed (1).pdf · uploaded 3 Mar 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · FORM-3 (FY 24-25-Q3) (4)_compressed.pdf · uploaded 3 Mar 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · serenity Dec 2024.pdf · uploaded 3 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Serenity june 2024 (1).pdf · uploaded 3 Mar 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · Serenity sep 2024 (1).pdf · uploaded 3 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · serenity f2 (1).pdf · uploaded 5 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · f2 serenityyyy (1).pdf · uploaded 5 May 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · f222 (1).pdf · uploaded 5 May 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · f222222 (1).pdf · uploaded 5 May 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100046870 · f33 (1).pdf · uploaded 5 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · FORM-3(FY 2024-25-Q3) (2)_compressed.pdf · uploaded 7 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · FORM-3(FY 2024-25-Q2) (2)_compressed.pdf · uploaded 7 May 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · FORM-3(FY 2024-25-Q3) (2)_compressed (1).pdf · uploaded 7 May 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · FORM-3(FY 2024-25-Q2) (2)_compressed (1).pdf · uploaded 7 May 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100051358 · form 3 b (1).pdf · uploaded 7 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f24 (1).pdf · uploaded 7 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · form 34 (1).pdf · uploaded 7 May 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f333 (1).pdf · uploaded 7 May 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f34 (1).pdf · uploaded 7 May 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f24 (1).pdf · uploaded 7 May 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f34 (1).pdf · uploaded 7 May 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f333 (1).pdf · uploaded 7 May 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100046870 · f3 sere (1).pdf · uploaded 7 May 2025Source
- Form 1P52100051358 · form 1 june 23.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · form 2 june 23.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · form 3 june 23.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-9.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · 1.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · 2.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · 3.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-1.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · from 1 dec 23.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · form 2 dec 23.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · form 3 dec 23.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · dec 23 sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-2.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · B,C Bldng March 2024.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · form 2 marc 24.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · form 3 mar 24.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · march 24 sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-3.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · 1.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · form 2 june 24 b& c.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · form 3 june 24 B.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · june 24 sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-4.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · 1.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · 2.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · 3.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-5.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · 1.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · 2.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · 3.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-6.pdf · uploaded 9 Jun 2025Source
- Form 1P52100051358 · 1.pdf · uploaded 9 Jun 2025Source
- Form 2P52100051358 · 2.pdf · uploaded 9 Jun 2025Source
- Form 3P52100051358 · 3.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · sold.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100051358 · Akshara Serenity B&C-7.pdf · uploaded 9 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · 3.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · s.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · declra.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · Form1 Serenity A June 2024.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · f2 jun 24 a.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · f3 june 24.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · s.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · declration.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · 3.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold mar 24.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · declrat.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · 3.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold dec 23.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · declration.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · 3.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold sep 23.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · declration.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · f 1 june 23 A.pdf · uploaded 12 Jun 2025Source
- Form 2P52100046870 · f 2 june 23 a.pdf · uploaded 12 Jun 2025Source
- Form 3P52100046870 · f3 june 23.pdf · uploaded 12 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold june 23.pdf · uploaded 12 Jun 2025Source
- Self-declaration of Quarterly ProgressP52100046870 · decl.pdf · uploaded 12 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 29 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 29 Jun 2025Source
- Form 3P52100046870 · 3.pdf · uploaded 29 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold sept 22.pdf · uploaded 29 Jun 2025Source
- Form 1P52100046870 · form 1 dec 22 a.pdf · uploaded 29 Jun 2025Source
- Form 2P52100046870 · form 2 dec 22 A.pdf · uploaded 29 Jun 2025Source
- Form 3P52100046870 · f3 dec 22.pdf · uploaded 29 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · s.pdf · uploaded 29 Jun 2025Source
- Form 1P52100046870 · 1.pdf · uploaded 29 Jun 2025Source
- Form 2P52100046870 · 2.pdf · uploaded 29 Jun 2025Source
- Disclosure of Sold and Booked InventoryP52100046870 · sold mar 23.pdf · uploaded 29 Jun 2025Source
- Form 3P52100046870 · AKSHARA SERENITY (A)-MARCH-23.pdf · uploaded 29 Jun 2025Source
- Form 1P52100051358 · F1-FINAL.pdf · uploaded 19 Jul 2025Source
- Form 2P52100051358 · F2-FINAL.pdf · uploaded 19 Jul 2025Source
- Form 3P52100051358 · F3-FINAL.pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventoryP52100051358 · SU-FINAL.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2023-2024)P52100051358 · F5-SERENITY B C-23-24.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2024-2025)P52100051358 · F5-SERENITY B C -24-25_compressed.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1P52100051358 · F1-FINAL.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 2P52100051358 · FORM-2.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 3P52100051358 · F3-FINAL.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1P52100051358 · F1-DEC-25.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 2P52100051358 · F2-DEC-25.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 3P52100051358 · F3-DEC-25.pdf · uploaded 29 May 2026Source
- Form 2A (FY 2023-2024)P52100051358 · Form 2A -FY 22-23.pdf · uploaded 29 May 2026Source
- Form 2A (FY 2024-2025)P52100051358 · Form 2A-FY 24-25.pdf · uploaded 29 May 2026Source
- Form 2A (FY 2025-2026)P52100051358 · Form 2A-FY 25-26.pdf · uploaded 29 May 2026Source
- Form 2A (FY 2022-2023)P52100046870 · Form 2A (FY 22-23).pdf · uploaded 29 May 2026Source
- Form 2A (FY 2023-2024)P52100046870 · Form 2A(FY 23-24).pdf · uploaded 29 May 2026Source
- Form 2A (FY 2024-2025)P52100046870 · Form 2A (FY 24-25).pdf · uploaded 29 May 2026Source
- Form 5 (FY 2022-2023)P52100046870 · F5-22-23.pdf · uploaded 29 May 2026Source
- Form 5 (FY 2023-2024)P52100046870 · F5-SERENITY A-23-24.pdf · uploaded 29 May 2026Source
- Form 5 (FY 2024-2025)P52100046870 · F5-SERENITY A-24-25.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 1P52100051358 · F1-MARCH-26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2P52100051358 · F2-MARCH-26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3P52100051358 · F3-Q4.pdf · uploaded 30 May 2026Source
- Form 1P52100046870 · F1-DEC-24.pdf · uploaded 18 Jun 2026Source
- Form 2P52100046870 · F2-DEC-24.pdf · uploaded 18 Jun 2026Source
- Form 3P52100046870 · F3-Q3.pdf · uploaded 18 Jun 2026Source
- Disclosure of Sold and Booked InventoryP52100046870 · SU-DEC-24.pdf · uploaded 18 Jun 2026Source
- Form 1P52100046870 · F1-MARCH-25.pdf · uploaded 18 Jun 2026Source
- Form 2P52100046870 · F2-MARCH-25.pdf · uploaded 18 Jun 2026Source
- Form 3P52100046870 · F3-MARCH-25-SERENITY A.pdf · uploaded 18 Jun 2026Source
- Disclosure of Sold and Booked InventoryP52100046870 · SU-MARCH-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1P52100046870 · F1-JUNE-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1P52100046870 · F1-SEPT-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1P52100046870 · F1-DEC-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 1P52100046870 · F1-MARCH-26.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 2P52100046870 · FORM-2-JUNE-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 2P52100046870 · FORM-2-SEPT-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 2P52100046870 · FORM-2-DEC-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 2P52100046870 · FORM-2-MARCH-26.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 3P52100046870 · F3-JUNE-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 3P52100046870 · F3-SEPT-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 3P52100046870 · F3-DEC-25.pdf · uploaded 18 Jun 2026Source
- Withdrawal Update Form 3P52100046870 · F3-MARCH-26 (SERENITY A).pdf · uploaded 18 Jun 2026Source
- Form 2A (FY 2025-2026)P52100046870 · Form 2A-(FY 25-26).pdf · uploaded 18 Jun 2026Source
- Form 5 (FY 2025-2026)P52100046870 · F5-FY 25-26.pdf · uploaded 18 Jun 2026Source
- Form 5 (FY 2025-2026)P52100051358 · bc wing.pdf · uploaded 19 Jun 2026Source
- Withdrawal Update Form 1P52100051358 · F1.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 2P52100051358 · F2.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 3P52100051358 · F3.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 1P52100046870 · F1-JUNE-26.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 2P52100046870 · F3-JUNE-26.pdf · uploaded 27 Jul 2026Source
- Withdrawal Update Form 3P52100046870 · F3-JUNE-26.pdf · uploaded 27 Jul 2026Source
- Occupational CertificateP52100046870 · OC.pdf · uploaded 28 Jul 2026Source
- Occupational CertificateP52100046870 · FORM-4 (A).pdf · uploaded 28 Jul 2026Source
- Occupational CertificateP52100046870 · OC MAIL 10-12-25.pdf · uploaded 28 Jul 2026Source
Technical
- DocumentP52100046870 · Layout Plan (2)_compressed.pdf · uploaded 5 Aug 2022Source
- DocumentP52100046870 · SANCTION PLAN A-6_compressed.pdf · uploaded 5 Aug 2022Source
- DocumentP52100051358 · Layout Main.pdf · uploaded 10 Apr 2023Source
- DocumentP52100051358 · Layout Plan B.pdf · uploaded 10 Apr 2023Source
- DocumentP52100051358 · Layout Plan C.pdf · uploaded 10 Apr 2023Source
- DocumentP52100051358 · 1 (6)_1_11zon.pdf · uploaded 15 Mar 2024Source
- DocumentP52100051358 · 2 (4)_3_11zon.pdf · uploaded 15 Mar 2024Source
- DocumentP52100051358 · 3 (1)_2_11zon.pdf · uploaded 15 Mar 2024Source
- DocumentP52100051358 · 4 (1).pdf · uploaded 15 Mar 2024Source
- DocumentP52100046870 · Layout.pdf · uploaded 2 May 2024Source
- DocumentP52100046870 · Floor plan_11zon.pdf · uploaded 2 May 2024Source
- DocumentP52100046870 · Floor plan 2_11zon.pdf · uploaded 2 May 2024Source
- DocumentP52100046870 · Floor plan 3_11zon.pdf · uploaded 2 May 2024Source
- DocumentP52100051358 · LAYOUT_compressed.pdf · uploaded 24 Dec 2024Source
- DocumentP52100051358 · 2_compressed.pdf · uploaded 24 Dec 2024Source
- DocumentP52100051358 · 3_compressed.pdf · uploaded 24 Dec 2024Source
- DocumentP52100051358 · 4_compressed (1).pdf · uploaded 24 Dec 2024Source
Technical (Architect)
Technical (Engineer)
- DocumentP52100051358 · F2 akshara serinity.pdf · uploaded 13 Jan 2025Source
- DocumentP52100046870 · Serenity june 2024 (1).pdf · uploaded 3 Mar 2025Source
- DocumentP52100046870 · Serenity sep 2024 (1).pdf · uploaded 3 Mar 2025Source
- DocumentP52100046870 · serenity f2 (1).pdf · uploaded 5 May 2025Source
- DocumentP52100046870 · f2 serenityyyy (1).pdf · uploaded 5 May 2025Source
- DocumentP52100046870 · f222 (1).pdf · uploaded 5 May 2025Source
- DocumentP52100046870 · f222222 (1).pdf · uploaded 5 May 2025Source
- DocumentP52100046870 · f33 (1).pdf · uploaded 5 May 2025Source
- DocumentP52100051358 · F2.pdf · uploaded 27 Jul 2026Source
- DocumentP52100046870 · F3-JUNE-26.pdf · uploaded 27 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S no 171/2 P, S.NO. 171/2 THATHWADE
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Phases
- 2
- Unit types
- 2BHK, 3BHK, 1RK77 units in all
- Address
- S no 171/2 P, Tathwade, TathwadePIN 411057
- Village
- Tathwade, Mulshi taluka
- Location
- 18.63333, 73.74958
- Land area for this project
- 351 sq m (3,781 sq ft)
- Permissible built-up area
- 2,480 sq m (26,696 sq ft)
- Sanctioned built-up area
- 2,459 sq m (26,469 sq ft)
- Designated bank account
- 89
- Developed in phases
- No
- Also registered as
- Akshara Serenity B and C
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S no 171/2 P
Boundaries
- North
- By Nala
- South
- By 20ft Wide Road
- East
- By Land of Mr Shinde
- West
- By Remaining area from S no 171 2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking77 units
8 of 77 units booked (10%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100046870 | A Building | 2BHK | 60.56 sq m · 652 sq ft | 14 | 2 |
| P52100046870 | A Building | 2BHK | 60.88 sq m · 655 sq ft | 7 | 0 |
| P52100046870 | A Building | 3BHK | 76.54 sq m · 824 sq ft | 7 | 6 |
| P52100051358 | B Bldg | 2BHK | 60.51 sq m · 651 sq ft | 7 | 0 |
| P52100051358 | B Bldg | 2BHK | 60.56 sq m · 652 sq ft | 7 | 0 |
| P52100051358 | B Bldg | 2BHK | 60.75 sq m · 654 sq ft | 7 | 0 |
| P52100051358 | B Bldg | 3BHK | 76.54 sq m · 824 sq ft | 7 | 0 |
| P52100051358 | C Bldg | 1RK | 34.78 sq m · 374 sq ft | 1 | 0 |
Show all 13 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100051358 | C Bldg | 2BHK | 60.53 sq m · 652 sq ft | 1 | 0 |
| P52100051358 | C Bldg | 2BHK | 60.53 sq m · 652 sq ft | 6 | 0 |
| P52100051358 | C Bldg | 2BHK | 60.85 sq m · 655 sq ft | 6 | 0 |
| P52100051358 | C Bldg | 2BHK | 60.85 sq m · 655 sq ft | 1 | 0 |
| P52100051358 | C Bldg | 3BHK | 75.61 sq m · 814 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals9
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Architect | Shree Spaces | — | P52100046870 |
| Architect | Shree Spaces | — | P52100051358 |
| Chartered accountant | CA Chandrakant Kale | — | P52100051358 |
| Chartered accountant | CA Chandrakant Kale | — | P52100046870 |
| Chartered accountant | Pravin Pise & Associates | — | P52100046870 |
| Chartered accountant | Vaibhav Bhise And Associates | — | P52100046870 |
| Engineer | Mr Nikhil Kamble Kamble | — | P52100046870 |
| Engineer | Nikhil Kamble | — | P52100051358 |
| Engineer | Rohinee Badgujar | — | P52100051358 |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Tathwade
- Bhagawati ChambersRERA PC1260002601422
- SiennaRERA PC1260002601395
- Avenue 7RERA PM1260002601199
- The PrivveRERA PM1260002600993
- Oriana WorldRERA PR1261012600520
- Alpine 21RERA PR1260002600172
- 6 BoulevardRERA PR1261012600142
- NeopolisRERA PR1260002600009
All 171 projects in Tathwade · Compare Akshara Serenity with another project
