RegisteredCompletion date passed1 extensionMahaRERA status: Certificate Signed

P52100046870

Akshara Serenity · Tathwade, Pune · Garve Developers and Promoters

Promised for 1 Oct 2026 — that date has passed and MahaRERA does not mark the project complete.

1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Risk: The latest completion date on record, 1 Oct 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate20 Aug 2026View
Registration certificate21 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100046870

Is Akshara Serenity delayed?

Yes. MahaRERA records a promised completion of 1 Oct 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100046870.

Who is the promoter?

MahaRERA records Garve Developers and Promoters as the promoter of P52100046870.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100046870.

Answers are generated from the record.

Data through9 Nov 2026, 02:24SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology