Garve Developers and Promoters
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects34 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Akshara SerenityP52100046870 | Tathwade | Certificate Signed | 1 Oct 2026 | 1 Oct 2026 | On date |
| Akshara SerenityP52100051358 | Tathwade | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Akshara HarmonyP52100052405 | Wakad | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Akshara MeadowsP52100055428 | Tathwade | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology