Residential / Group Housing · 1 building · 12 unitsRERA P52100079768

Yashoda Heights

Deedo IDDP-PUN-E3M2

Completion was pushed back 4 months, to Mar 2027; no MahaRERA orders on record; 0% of its units are booked.

Sangavi, Pune 411027 · Property rates in Sangavi · by Paras Shivajirao Dhore

DeliveryExtended 4 moPromised Nov 2026 · now due Mar 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 12 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Mar 2027

  • This projectRegistered 26 Mar 2025, completion promised 23 Nov 2026, revised to 23 Mar 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100079768
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007976826 Mar 202523 Nov 202623 Mar 2027Paras Shivajirao DhoreProject page
Documents68

1 document held by Deedo, 67 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPancard - Paras Dhore.pdf · uploaded 31 May 2024Source
  • Other – FinanceLand Cost NIL Declaration v1[1].pdf · uploaded 14 Feb 2025Source

Legal

  • Declaration Form BForm B.pdf · uploaded 31 May 2024Source
  • Other – Legalबक्षिसपत्र १.pdf · uploaded 3 Aug 2024Source
  • Legal Title reportParas Search Pdf.pdf · uploaded 3 Aug 2024Source

Migrated

  • 1 PAN CardPancard - Paras Dhore.pdf · uploaded 31 May 2024Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 31 May 2024Source
Show all 68 documentsShow fewer documents

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Scan 04 Mar 25 16·36·00.pdf · uploaded 31 May 2024Source
  • 4 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 May 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Adobe Scan Mar 04, 2025.pdf · uploaded 27 Jul 2024Source
  • 1 Proforma of Agreement for saleAgreement for sale123.pdf · uploaded 27 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Paras Dhore.pdf · uploaded 27 Jul 2024Source
  • 1 Copy of the legal title reportParas Search Pdf.pdf · uploaded 3 Aug 2024Source
  • 1 a Details of encumbrances concerned to Finance5 Encumbrunce.pdf · uploaded 3 Aug 2024Source
  • 1 Copy of Layout Approval (in case of layout)Layout_11zon.pdf · uploaded 3 Aug 2024Source
  • 1 Proforma of Allotment letterAllotment of Yashoda construction11.pdf · uploaded 3 Aug 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentFloor plan.pdf · uploaded 3 Aug 2024Source
  • 1 Other – Legalबक्षिसपत्र १.pdf · uploaded 3 Aug 2024Source
  • 1 Declaration about Commencement Certificate3 Decalaration commencement.pdf · uploaded 3 Aug 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_Yashoda.pdf · uploaded 3 Aug 2024Source
  • 2 CERSAI detailsCERSAI Report Decleration.pdf · uploaded 3 Aug 2024Source
  • 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter (28) (1).pdf · uploaded 3 Aug 2024Source
  • 1 b Details of encumbrances concerned to Legal5 Encumbrunce.pdf · uploaded 3 Aug 2024Source
  • 1 Other – TechnicalOrder 50 Annexure A.pdf · uploaded 3 Aug 2024Source
  • 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement (27) (1).pdf · uploaded 3 Aug 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 CA Certificate Yashoda.pdf · uploaded 9 Aug 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)PDF_20250213_0002 (1).pdf · uploaded 9 Aug 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Bank Declaratn (Format A)1 (1).pdf · uploaded 10 Aug 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure Secured Unsecured.pdf · uploaded 10 Aug 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentYashoda CC Mail .pdf · uploaded 1 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Land Cost NIL Declaration v1[1].pdf · uploaded 12 Feb 2025Source
  • 1 Other – FinanceLand Cost NIL Declaration v1[1].pdf · uploaded 14 Feb 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentPARAS DHORE PLINTH.pdf · uploaded 4 Mar 2025Source
  • 3 Commencement Certificates / NA Order for plotted developmentDate (1).pdf · uploaded 17 Mar 2025Source
  • Form 1March 2025 Form 1.pdf · uploaded 10 Jun 2025Source
  • Form 2March 2025 Form 2.pdf · uploaded 10 Jun 2025Source
  • Form 3March 2025 Form 3.pdf · uploaded 10 Jun 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold (15).pdf · uploaded 10 Jun 2025Source
  • Self-declaration of Quarterly ProgressQ Declaration.pdf · uploaded 10 Jun 2025Source
  • Form 1Form 1 Jun 2025 s.pdf · uploaded 26 Sep 2025Source
  • Form 2YASHODA HEIGHTS june 25 s.pdf · uploaded 26 Sep 2025Source
  • Form 3Jun 2025 Form 3.pdf · uploaded 26 Sep 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Jun 2025.pdf · uploaded 26 Sep 2025Source
  • Form 1Form 1 s.pdf · uploaded 20 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 20 Nov 2025Source
  • Form 3Form 3_compressed (20) (1).pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 20 Nov 2025Source
  • Form 5 (FY 2024-2025)Yashoda Heights Form 5 2024-25.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 1Form 1 (2).pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 2yashoda heights Dec 25 (1).pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 3Form 3 (1).pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 1Form 1 (3) (1).pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2yashoda heights March 26 (1).pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3Form 3 (2) (1).pdf · uploaded 23 Jun 2026Source
  • Form 2A (FY 2024-2025)2024-2025 (1).pdf · uploaded 18 Jul 2026Source
  • Form 2A (FY 2025-2026)2025-2026 (8).pdf · uploaded 18 Jul 2026Source
  • Form 2A (FY 2026-2027)2026-2027 (6).pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1Form 1 (24).pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 2yashoda heights june 26 (1).pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 3Form 3 (2) (1).pdf · uploaded 13 Aug 2026Source

Technical

  • DocumentLayout_11zon.pdf · uploaded 3 Aug 2024Source
  • DocumentFloor plan.pdf · uploaded 3 Aug 2024Source
  • Other – TechnicalOrder 50 Annexure A.pdf · uploaded 3 Aug 2024Source
  • DocumentHPSC1741.pdf · uploaded 8 Dec 2025Source
  • DocumentHPSC1740.pdf · uploaded 8 Dec 2025Source

Technical (Architect)

  • DocumentForm 1 (24).pdf · uploaded 13 Aug 2026Source

Technical (Engineer)

  • Documentyashoda heights june 26 (1).pdf · uploaded 13 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Sr No 9C 42 Sangavi

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK12 units in all
Address
Sr No 9C 42 Sangavi, Lane No 1, Dhore Nagar, Old SangaviPIN 411027
Village
Sangavi, Haveli taluka
Land area for this project
800 sq m (8,611 sq ft)
Permissible built-up area
2,512 sq m (27,042 sq ft)
Sanctioned built-up area
1,089 sq m (11,724 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
43
Developed in phases
No

Survey, CTS, gat or plot numbers

Sr No 9C 42 Sangavi

Land as published on MahaRERA's project page

Sr No 9C 42 Sangavi

Boundaries

North
PLot No 41 and ShalimarApartment
South
Plot No 43 and MrJadhav and Kalapures Plot
East
plot of S No 8
West
30 Sq Ft Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking12 units

0 of 12 units booked (0%), as the promoter reported to MahaRERA

2BHK · 9 units3BHK · 3 units
TypeCarpet areaUnitsBooked
2BHK68.74 sq m · 740 sq ft30
2BHK69.83 sq m · 752 sq ft30
2BHK70.24 sq m · 756 sq ft30
3BHK94.31 sq m · 1,015 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShankar Nimbalkar SUNIL DESHPANDE—
Chartered accountantSheetal S Sathe—
Chartered accountantSuhas S Sathe—
EngineerRohinee Badgujar—
EngineerUmesh Madhukar Shinde—

Source: MahaRERA project page. Contact details are not shown.