RERA projects in Sangavi

11 projects under 11 MahaRERA registrations, registered 2021–2026. 45% have a completion date extended beyond the one promised.

Locality
11RERA projects
11Registrations
5Completion still due6 past their completion date
4 monthsMedian extension beyond promised date45% of registrations extended
1Regulatory caseson 1 project
11Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20212
20222
20233
20241
20252
20261

Projects in Sangavi

11 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Premraj Niketan 2.0Sankalp BuildconPR126000250294418 Mar 202631 Dec 202931 Dec 2029Not yet due0
Yashoda HeightsParas Shivajirao DhoreP5210007976826 Mar 202523 Nov 202623 Mar 2027Extended 4 mo0
Meenakshi ApartmentSankalp BuildconP521000794867 Mar 202531 Mar 202631 Jul 2026Extended 4 mo0
Santiago SunriseSantiago Realtech VenturesP5210007779230 Oct 202431 Dec 202730 Apr 2028Extended 4 mo0
Pemraj SkyonePemraj Associates through its Proprietor Sharad Narayan DhoreP5210005112330 May 202331 Dec 202731 Dec 2027Not yet due1
SRK HeritageSRK YN ConstructionP521000503485 Apr 202331 Dec 202531 Dec 2025Promised date passed0
West 9 Buissness ArcS R K Realty & AS DevelopersP521000500516 Mar 202331 Dec 202730 Apr 2028Extended 4 mo0
Kapila Co-Operative Housing SocietySandip Chandrakant ShitoleP521000456686 Jun 202231 Mar 202531 Mar 2025Promised date passed0
Vastu AppartmentsVastu DevelopersP5210003252910 Jan 202231 Jul 202231 Jul 2022Promised date passed0
Kamal ClassicVenkateshwara BuildconP5210002971726 Jun 202131 Mar 202230 Nov 2022Extended 8 mo0
Sai NilanjanSai Nilanjan AssociatesP5210002822518 Feb 202130 Sep 202230 Sep 2022Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sankalp Buildcon2 projects
  2. Paras Shivajirao Dhore1 project
  3. Pemraj Associates through its Proprietor Sharad Narayan Dhore1 project
  4. Sai Nilanjan Associates1 project
  5. Sandip Chandrakant Shitole1 project
  6. Santiago Realtech Ventures1 project
  7. S R K Realty & AS Developers1 project
  8. SRK YN Construction1 project
  9. Vastu Developers1 project
  10. Venkateshwara Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology